A RACI chart lists activities down the side and roles across the top. Each cell holds a letter:
- R, Responsible: does the work. There can be more than one.
- A, Accountable: owns the result and signs it off. Exactly one per activity. Two people accountable means nobody is.
- C, Consulted: asked for input before the work is done. Two-way conversation.
- I, Informed: told about the result afterwards. One-way.
Two rules catch most mistakes: every activity has exactly one A, and every activity has at least one R (the A can also be the R). Too many Cs slow everything down; a role with no letters on a busy row is often a forgotten stakeholder.
A BA uses a RACI to agree, early and in writing, who signs off requirements, who must be asked about business rules and who just needs to know.
One A per row, at least one R.