Once you have the list, sort it. A power and interest grid has two questions: how much power does this stakeholder have over the change (budget, approval, the ability to stop it), and how much do they care about it?
- High power, high interest: manage closely. Involve them in decisions, meet them often. A sponsor usually sits here.
- High power, low interest: keep satisfied. Give them short updates and the decisions they must make; do not bury them in detail. A CFO who approves the budget but not the screens.
- Low power, high interest: keep informed. They care and know the work; consult them and tell them what changed. Front-line staff often sit here.
- Low power, low interest: monitor. Light-touch updates, and watch whether that changes.
Positions move. A quiet department becomes very interested the day it learns its process changes. Revisit the grid at each milestone.
The power and interest grid.