Weighted shortest job first (WSJF) orders work by economics: do first what costs the most to delay, per unit of effort. It is used in the Scaled Agile Framework, after Don Reinertsen's work on product development flow.
Cost of delay = business value + time criticality + risk reduction (or opportunity enablement)
WSJF = cost of delay ÷ job size
Each part is scored relative to the other jobs, often on a scale like 1, 2, 3, 5, 8, 13, 20. The smallest job in a column gets the lowest score.
The effect: a small job with a high cost of delay jumps the queue, even when a bigger job has more value. Fixing duplicate refunds (urgent, risky, small) beats a large new feature. It is a relative comparison among the jobs on the table, not an absolute number to carry from one list to another.