- Project manager
- Junior
- 30 min
The critical path: forward and backward pass: A dependency-driven finish
Calculate the earliest finish day from the activity table. Both parallel activities start after A; the project ends when both finish.
Skills and rubricForward and backward pass
- I calculate the longest dependency path and check resource availability because an unconstrained early finish can assign the same specialist to overlapping work.
- I recalculate the affected date and present bounded scope, sequencing or resource choices because hiding the slip does not recover time.
- I retain the source material, the saved answer and the decision owner because a plausible answer alone does not show which requirement was checked.