Takt is the pace required to meet demand over the chosen period. Divide net available time by required units. Remove planned unavailable time first. Compare takt with measured station cycles to locate a capacity gap. Takt changes with demand; it is not a stopwatch observation or a guarantee that the process can keep up.
You work with original records from fictional operations teams. Start by checking what each column means and which cases belong in the denominator. A precise calculation can still answer the wrong business question if the population or time boundary changes. Use the worksheet to leave an audit trail: preserve the inputs, record the intermediate outputs and check the stated exception. The transfer case uses new data so you must apply the method again.
Translate demand into a pace using net available time.