A schedule starts as a list of activities, each with a duration, joined by links (dependencies) that say what has to happen first. There are four kinds:
- Finish to start (FS): B can start once A finishes. Most links are this one.
- Start to start (SS): B can start once A starts. Writing the user guide can start when testing starts.
- Finish to finish (FF): B can finish only once A finishes. Fixing defects cannot finish before testing does.
- Start to finish (SF): B cannot finish until A starts. Rare: the old alarm stays on until the new one starts.
A lag adds waiting time to a link: concrete that must cure for 3 days before framing is P FS +3. A lead is a negative lag that lets work overlap. A lag is not an activity: nobody works during it.
In the workbench you write links the way scheduling tools do: A for finish to start, A:SS, A:FF+2, A+3.
A finish to start link with a lag, written the way scheduling tools write it.