A burndown shows work remaining over time. A burnup shows completed work and, when included, a separate total-scope line. Both are useful only when you know what their units and completion rules mean. A flat burndown could reflect a blockage, large items waiting to finish, or added scope offsetting completions.
A cumulative flow diagram shows how many items occupy each workflow state over time. A widening review band suggests work is entering review faster than it leaves. Inspect the cause with the team.
Velocity helps one team plan using a stable estimation scale. It is not a fair ranking of teams. Use delivery measures alongside outcomes and quality: closing more tickets is no improvement if customers still cannot complete their task.
Different charts answer different questions.