The baseline records the approved schedule. The current schedule records what you now expect to happen. Keep both: one supports comparison, and the other supports decisions about the remaining work. Finish variance is current finish minus baseline finish, so a positive value means late under this convention. State the convention in a report.
An activity can finish later than its baseline without delaying the project if it has enough total float. Once that float is consumed, the longest path can change. Recalculate the whole network before recommending recovery work. An approved scope change may justify a baseline revision through change control, but normal forecasting does not. Preserve the earlier version and its approval history instead of making the delay disappear.
A positive finish variance under the current-minus-baseline convention.