A duration is incomplete until you know its calendar. Five working days can cross a weekend, and a holiday can move the finish again. Count the first working date as day one when you report an inclusive finish date. A finish-to-start successor can start at the next working boundary; it cannot consume the same hours that its predecessor still needs.
The workbench Gantt uses Monday through Friday and skips weekends. It does not apply custom holidays or separate resource calendars. The holiday and supplier examples here are manual calendar calculations with all exceptions stated in the record. On a job, record the calendar assumptions beside the schedule and confirm them with the people who will do the work.
Five working days across a weekend.