Client question
Ashby's sponsor asks whether to crash, overlap or cut scope. Use the original quotes and schedule in the case file.
Decision record
Calculate the gap, choose critical crash days, price them, test the inspection constraint and budget, then choose a recommendation that cites the evidence.
Ashby Engineering needs three working days back. Compare the available offers and the nonnegotiable inspection before making a recommendation. Your final choice must meet the target within the recovery allowance.