The cost baseline is the approved, time-phased budget you measure performance against. It is built up in layers:
- Add the work package estimates (from the WBS dictionary) into control accounts.
- Add the contingency reserve: money for identified risks, the "known unknowns". The project manager manages it, and it is inside the cost baseline.
- The result is the cost baseline, also called the budget at completion (BAC).
- Add the management reserve: money for problems nobody can foresee, the "unknown unknowns". It is outside the baseline, controlled by management or the sponsor, and using it changes the baseline.
Cost baseline + management reserve = the project budget.
Spread over time, the baseline forms an S-curve: slow spending at the start, fast in the middle, slow at the end. You compare actual spending against it month by month.
How the cost baseline and the budget are built.