Crashing shortens a schedule by adding resources: overtime, an extra crew, a faster machine. It costs money, so you do it as cheaply as you can:
- Work out each activity's cost per day saved: (crash cost - normal cost) ÷ (normal days - crash days).
- Crash only activities on the critical path. Shortening anything else costs money and saves nothing.
- Crash the cheapest critical day first, then the next cheapest.
- Stop at each activity's crash limit: no amount of money makes concrete set faster than it does.
- After every day you take off, check the paths again: a shorter critical path can make another path critical, and then both must be shortened together.