Earned value management answers two questions at once: are we on schedule, and are we on budget? It needs three numbers, all in money:
- Planned value (PV): the budget for the work scheduled to be done by now. Budget × planned % complete.
- Earned value (EV): the budget for the work actually done by now. Budget × actual % complete.
- Actual cost (AC): what the work done has actually cost, from the accounts.
The project's total budget is the budget at completion (BAC).
The trap is computing EV from money spent. If half the budget is spent, that says nothing about how much work is done: EV comes from progress, measured against the budget for the work. A package that is 50% complete earns 50% of its budget, whatever it has cost.
The three earned value numbers for one package.