Plotted month by month, the cumulative PV, EV and AC make three S-curves: slow at the start, steep in the middle, flat at the end.
Reading them is reading the gaps:
- EV below PV: behind schedule. The gap is the schedule variance.
- AC above EV: over budget. The gap is the cost variance.
- EV above PV with AC above EV: ahead of schedule but over budget, often from paid overtime.
- EV flattening while PV climbs: progress has stalled; find out why before the gap grows.
The workbench shows the curves as a table of cumulative figures, month by month: each row is one point on each of the three lines. The PV line runs to the end of the project and finishes at the BAC; EV and AC stop at the status date.
S-curve data read month by month.