Expected monetary value (EMV) puts a number on a risk: EMV = probability × impact. Threats have negative impact and opportunities positive, so:
- a 30% chance of a $20,000 overrun: 0.3 × -20,000 = -$6,000;
- a 20% chance of a $5,000 discount: 0.2 × 5,000 = +$1,000.
Adding the EMV of the threats gives a reasonable size for the contingency reserve. Do not subtract opportunities from it unless the organization has agreed to count on them.
A decision tree compares options that carry different risks: work out each option's expected cost (its fixed cost plus the probability-weighted extra costs) and pick the lowest, or the highest expected value when comparing gains.
EMV is an average over many projects. On this one project the overrun either happens or it does not; EMV helps you size reserves and compare options, not predict the outcome.
EMV for risks and a decision tree.