Fast tracking shortens a schedule without buying resources: activities that were planned in sequence are partly overlapped. Building starts before design is complete; testing starts before the build is finished.
In the schedule you change a link:
- Finish to start becomes start to start with a lag:
A:SS+5 starts B five days after A starts.
- Or keep finish to start with a lead (a negative lag):
B-3 starts C three days before B finishes.
Fast tracking costs no money up front but adds risk: work started on an unfinished design may have to be redone when the design changes. Only overlap where the later activity can safely start with partial information, and only on the critical path, or the overlap saves nothing.
Some pairs cannot overlap at all: concrete must be poured before it cures, and a parcel must be packed before it ships.
Fast tracking design and build with a start to start link and a lag.