Total float is how long an activity can slip without moving the project finish. Free float is how long it can slip without moving the early start of the activity right after it.
Free float = the earliest ES of the successors - EF of the activity. It is never more than total float.
The difference matters when you plan around a delay:
- A delay within free float disturbs nobody.
- A delay between free float and total float keeps the finish date but pushes the next activity later, and that team needs to know.
- A delay beyond total float moves the project finish by the difference.
Float belongs to the path, not to one activity: if an early activity on a path uses up the float, the later ones on the same path lose it. And when a deadline is earlier than the computed finish, float turns negative: the plan is already late by that many days.
Total float against free float on one activity.