Earned value turns today's performance into a forecast. The estimate at completion (EAC) depends on what you expect from the rest of the work:
- The overrun will continue at the same rate: EAC = BAC ÷ CPI.
- The overrun was a one-off and the rest will go to plan: EAC = AC + (BAC - EV).
- Both cost and schedule will keep affecting the remaining work: EAC = AC + (BAC - EV) ÷ (CPI × SPI).
Then:
- Estimate to complete: ETC = EAC - AC (what is still to be spent).
- Variance at completion: VAC = BAC - EAC (negative is the expected overrun).
- To-complete performance index: TCPI = (BAC - EV) ÷ (BAC - AC): the CPI the remaining work must achieve to finish on budget. A TCPI well above 1 means the budget is out of reach without a change.
Pick the formula from the cause of the variance, not from the answer you would like.
Forecasts from earned value.