A Gantt chart draws each activity as a bar on a calendar, so the schedule can be read at a glance. In the workbench, as in most scheduling tools:
- Each row has the activity's start and finish dates beside its bar.
- Critical activities are red. A thin line after a bar shows its total float.
- A milestone is an event with no duration, drawn as a diamond: "Keys handed over", "Store opens". It takes no time and no one works on it.
- Durations count working days. Weekends are skipped, so a 5-day activity that starts on a Wednesday ends the next Tuesday.
A date on a Gantt is a promise someone will hear. Read it carefully: the finish date is the last day of work, and the next activity starts the working day after.
A Gantt chart on working days, with a milestone.