A life cycle is the series of phases a project goes through. The main choice is how much you plan up front.
- Predictive (often called waterfall): scope, schedule and cost are planned in detail early, and work moves through phases such as design, build and test. It suits work whose requirements are well known and unlikely to change: a building to a fixed design, a regulatory report.
- Adaptive (agile): work is delivered in short iterations, and the plan is revisited after each one with what the team has learned. It suits work with uncertain or changing requirements: a new app, a service nobody has run before.
- Hybrid: parts of the project run each way. A fixed regulatory deadline and contract, with the features built in iterations inside it, is a common hybrid.
The deciding questions are about the work: how certain are the requirements, how likely are they to change, and can the result be delivered in useful pieces?
Choosing an approach from how certain the requirements are.