Not every risk deserves the same attention. A probability and impact matrix ranks them:
- Score probability on an agreed scale, for example 1 (very unlikely) to 5 (very likely).
- Score impact on the same kind of scale, defined for the project: 5 might mean "a delay of over a month" or "a cost over $100,000".
- Score = probability × impact. The project agrees the bands: here 15 and over is High, 8 to 14 Medium, 7 and under Low.
Two traps:
- Words are not numbers. "Low × High = Medium" is not arithmetic. Turn each label into its number on the agreed scale first.
- Rare but severe risks can score Low and still deserve a response: a 1 × 5 that would close the project is not something to forget. Many projects flag any impact of 5 regardless of score.
Re-score risks as the project moves: probabilities change, and a risk that has passed can be closed.
Scoring and rating risks on an agreed matrix.