A relationship states which event controls another activity. Finish to start (FS) waits for the predecessor to finish. Start to start (SS) measures from its start; finish to finish (FF) measures from its finish. A positive lag adds waiting time, and a negative lag allows an earlier event. Read the two linked events before doing any arithmetic.
An FF link can move a successor's start because its duration must fit before the required finish. Long lags also deserve inspection. If the wait is work with an owner, such as an approval, a named activity makes its status visible. The lab uses a neutral Gantt editor and original schedules, without reproducing a vendor interface.
A three-day lag measured from the predecessor's start.