A schedule can be logically right and still impossible: two activities at the same time that both need the one electrician. That person is over-allocated.
Resource leveling fixes it by moving work so the resource is never needed twice at once, usually by making one activity wait for the other (a new link). The cost: if the activity that waits has no float, the finish moves.
Resource smoothing is the gentler version: it only moves work within its float, so the finish never moves, but it may not remove every peak.
How to work it:
- Load the resource day by day and find the days it is needed more than it is available.
- Move the activity with the most float, so the delay is absorbed.
- Recompute: leveling can create a new critical path.
If no activity has enough float and the date is fixed, the choice is a second resource (cost) or a later finish (time): that is the sponsor's decision.