Resource loading compares required work with the people available on each working day. Add simultaneous assignments before comparing them with capacity. A person assigned half time to each of two tasks is fully loaded, while two full-time assignments create an overload. The average across a month can hide a shortage on Tuesday.
Inspect the peak first, then check whether a task can move inside its float. Smoothing preserves the finish; leveling can change it when no float remains. Overtime and extra people need agreement, and a specialist cannot always be replaced at short notice. The Gantt stores a resource name but does not calculate fractional loading or automatically level work. Use the stated loading records for these calculations, then edit dependencies when sequencing is the chosen remedy.
Two half-time tasks use one full-time allocation.