A risk is an uncertain event that, if it happens, affects the project's objectives. Most risks are threats; some are opportunities. An issue is different: it has already happened and needs action now. A risk that occurs becomes an issue.
The risk register lists each risk with its probability, impact, response, owner and trigger. Write each one in three parts so everyone reads it the same way:
Because of [cause], [risk event] may happen, which would [effect on objectives].
- Cause: a fact today ("the steel comes from one mill").
- Risk: the uncertain event ("the steel arrives late").
- Effect: what it does to the project ("the ramp opens two weeks late").
Each risk gets an owner: the person best placed to watch for its trigger (the early warning sign) and carry out the response. Vague entries such as "weather" or "resources" cannot be owned or acted on.
A risk register entry in cause, risk and effect form.