Each risk gets a planned response, chosen by its owner. For threats:
- Avoid: change the plan so the threat cannot happen (assemble at ground level to eliminate the crane lift).
- Transfer: move the impact to someone else, usually for a fee: insurance, a fixed-price contract, a warranty. The risk still exists; someone else pays.
- Mitigate: make it less likely or less damaging (order steel early; book a backup crane).
- Accept: do nothing now, perhaps keeping a contingency reserve or a fallback plan.
- Escalate: the risk is outside the project's authority, so hand it to the person who owns it.
For opportunities, the mirror images: exploit (make sure it happens), share (partner with someone who can capture it), enhance (make it more likely or bigger), accept and escalate.
A common slip is calling insurance "mitigation": insurance does not make the storm less likely, it moves who pays.
Five responses to one threat.