Scope will change. The question is whether it changes on purpose. Change control is the route:
- Log the change request.
- Assess its impact on scope, schedule, cost, quality and risk.
- Decide: the sponsor or a change control board approves, rejects or defers it.
- Update the plan and baselines if approved.
- Communicate the decision.
Two ways scope changes without permission:
- Scope creep: requests added without assessment or approval, one small favor at a time.
- Gold plating: the team adds features nobody asked for, often with good intentions. It costs time and money and adds risk, and the customer may not want it.
An approved change is not creep, even a large one: it was assessed and decided by the people who own the scope.
One change request through change control.