A stakeholder is anyone who affects or is affected by the project. Two tools decide how to work with each one.
The power and interest grid sets the default approach: manage closely (high power, high interest), keep satisfied (high power, low interest), keep informed (low power, high interest), monitor (low power, low interest).
The engagement assessment matrix compares each stakeholder's current engagement with the desired level:
- Unaware of the project;
- Resistant to the change;
- Neutral: aware, neither for nor against;
- Supportive of the change;
- Leading: actively making it succeed.
The gap between current and desired is where your effort goes. A resistant stakeholder with high power is the biggest risk. A stakeholder who is already where you need them needs keeping there, not winning over: spend the time where the gaps are.