A status report tells the people who fund and guide the project where it really stands. The usual shorthand is RAG:
- Green: on track.
- Amber: at risk; the team has a recovery plan within its authority.
- Red: off track; the sponsor needs to decide or help.
Agree the thresholds in advance (for example, more than 10% over budget is red), and rate the forecast, not the effort. A project where the critical path has slipped past its float is not green, however hard the team is working. "Watermelon" reports, green outside and red inside, destroy trust when the truth comes out.
The RAID log keeps four lists the report draws on: Risks (might happen), Assumptions (believed true, not proven), Issues (happening now) and Dependencies (work or decisions the project relies on).
A good report leads with the headline, shows progress against the plan, names issues and risks with actions and owners, and says plainly what decision is needed and by when.
An honest RAG status with its thresholds.