A single number hides uncertainty. A three-point estimate asks for three:
- O, optimistic: if things go well;
- M, most likely;
- P, pessimistic: if things go badly (but not a disaster).
Two formulas combine them:
- Triangular: (O + M + P) ÷ 3.
- Beta, also called PERT: (O + 4M + P) ÷ 6. It weights the most likely value four times.
The spread of one activity's estimate is its standard deviation, (P - O) ÷ 6. For a whole path, do not add standard deviations: add the variances (each standard deviation squared), then take the square root of the total. Adding standard deviations makes the path look far riskier than it is.
When someone says "PERT estimate", they mean the beta formula.
Three-point estimates and the spread of a path.