From PV, EV and AC come four numbers:
- Schedule variance: SV = EV - PV. Negative means behind schedule.
- Cost variance: CV = EV - AC. Negative means over budget.
- Schedule performance index: SPI = EV ÷ PV. Below 1 means behind schedule: 0.85 means 85% of the planned work is done.
- Cost performance index: CPI = EV ÷ AC. Below 1 means over budget: 0.80 means 80 cents of work for every dollar spent.
Both variances start with EV, which makes them easy to remember. The indices are useful because they compare across projects of different sizes and feed straight into forecasts.
The two can disagree. A project can be ahead of schedule and over budget (SPI above 1, CPI below 1) because it bought speed with overtime. Read them separately, and ask what is behind each.
One caution: SPI drifts back toward 1 near the end of a project, even a late one, because all the planned work is eventually earned. Late in a project, check the critical path too.