A WBS shows the pieces; the WBS dictionary says what each piece means. For every work package it records:
- a description of the work and its deliverable;
- the owner (the person or organization responsible);
- the acceptance criteria: how the deliverable will be judged complete;
- the estimate of cost and duration;
- key dependencies and milestones.
The dictionary stops the classic argument at handover ("I thought the shelving included the brackets"). An entry without acceptance criteria is the most common gap: the work gets done, but nobody agreed what done looks like, so it is never quite finished.
Estimates in the dictionary roll up: the work packages under a deliverable add up to its estimate, which keeps the 100% rule honest in money as well as in scope.
One WBS dictionary entry.