Required processing hours equal planned units times minutes per unit divided by sixty. Compare with productive hours after downtime, not calendar hours. This task reports only positive overload. A zero gap does not prove every SKU can run on every line; routing constraints still matter.
You work on Pine Harbor Distribution's fictional planning file. Before calculating, check the time period, the unit and which business event each input records. Keep those definitions in the workbook so another analyst can reproduce the result. The first task gives you the steps. Later tasks use new quantities, a boundary case and a handoff to another planner. Your answer is recalculated on a second copy of the inputs, so enter a formula rather than a number copied from the example.
Calculate positive overload hours: MAX(0, planned units*minutes per unit/60 - available productive hours).