        PMP exam questions: original practice with answers

        Our PMP question banks contain 360 original scenarios with worked answers. They cover People, Process and Business Environment under the July 2026 outline.

        Version
        PMP Examination Content Outline, July 2026; PMI doesn't list a separate alphanumeric exam code
        Official format
        180 questions in 240 minutes: 170 scored and 10 unscored pretest questions
        Official domains
        People 33%; Process 41%; Business Environment 26%
        Official question types
        Single and multiple response, matching and drag-and-drop, case studies, graphics and practicum tasks; availability varies by delivery mode
        Official breaks
        Two 10-minute breaks; completed sections can't be reopened. Check the current delivery rules with PMI
        Official pass score
        PMI doesn't publish a fixed percentage of correct answers. Our 80% target is for practice only
        Our format
        Two different 180-question single-response knowledge mocks. Checked practical tasks are separate; our mocks don't reproduce the official interface, break schedule or scoring
        Training hours
        Our practice provides no contact hours, 35-hour eligibility certificate or PDUs
        Booking
        Apply to PMI, obtain approval, pay and schedule. Pearson VUE test centers and online proctoring have local availability and exceptions
        Exam fee
        PMI displays USD 405 for members and USD 655 at full price. Check your country, currency, taxes and membership at checkout

        Question review

        Choose the best next action using the facts in the scenario: who has authority, whether the issue is already happening, and what the team has already tried. Read every alternative before answering. A familiar word such as escalate doesn't make an action right in every context.

        After answering, name the objective and explain why the nearest distractor fails. Keep guesses in your mistake log even when they were correct. Our bank is original practice, not recalled or leaked exam content.

        Knowledge and practical work

        The full mocks use single-response choices. PMI also uses multiple response, matching, case work and interactive tasks. Use the shortened course mock for matching and multiple response, and the project course for checked worksheets and schedules.

        The official outline weights domains at 33%, 41% and 26%. Our rounded 180-question mock counts are 59, 74 and 47. A correct-answer percentage here isn't PMI's certification score.

        180 questions

        1. 1.1 Shared outcomes and understanding

          A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: the operators’ intended outcomes. Verified evidence in the review file: an agreed vision with measurable success criteria. Verified evidence in the review file: evidence that each operator interprets the vision consistently. Verified evidence in the review file: a communication owner and a date to review the vision. Which action should the project manager take next based on this evidence?

          1. Interview the operators about their intended outcomes.
          2. Agree a shared vision and measurable success criteria.
          3. Test understanding and investigate conflicting interpretations.
          4. Assign the vision’s communication owner and review date.
          Answer: A

          ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.

        2. 1.2 Conflict diagnosis and resolution

          Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Verified evidence in the review file: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Verified evidence in the review file: a neutral account of the underlying approval dispute. Which action should the project manager take next based on this evidence?

          1. Establish and enforce respectful discussion rules.
          2. Hear both teams and establish the source of the dispute.
          3. Facilitate an agreement on approval responsibilities.
          4. Review the next approval cycle with both teams.
          Answer: A

          ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.

        3. 1.3 Team authority and tailored support

          A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Verified evidence in the review file: a tailored delegation and coaching arrangement. Verified evidence in the review file: a feedback review of delegation and team concerns. Evidence not yet verified: a shared release goal and clear decision responsibilities. Verified evidence in the review file: a review of members’ experience and support needs. Which action should the project manager take next based on this evidence?

          1. Agree the release goal and each role’s decision authority.
          2. Assess experience and ask members what support they need.
          3. Delegate within agreed limits and coach where support is needed.
          4. Review results with the team and adjust leadership support.
          Answer: A

          ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.

        4. 1.5 Negotiating shared expectations

          A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Verified evidence in the review file: support for department leads applying the agreed target. Verified evidence in the review file: a negotiated response-time target and accepted trade-offs. Verified evidence in the review file: explicit response-time expectations from both departments. Evidence not yet verified: a classification of stakeholder groups and decision authority. Which action should the project manager take next based on this evidence?

          1. Ask both departments to state measurable expectations.
          2. Classify stakeholders by role and decision authority.
          3. Facilitate agreement on the target and its trade-offs.
          4. Coach department leads on applying the agreed target.
          Answer: B

          ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.

        5. 1.7 Operational knowledge handover

          A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: captured diagnostic examples and decision rules. Verified evidence in the review file: guided practice for the receiving operations team. Verified evidence in the review file: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Which action should the project manager take next based on this evidence?

          1. Run paired diagnostic practice with the receiving team.
          2. Have operations diagnose a fresh failure without coaching.
          3. Identify critical knowledge with the specialist and operations.
          4. Capture failure examples and the specialist’s decision rules.
          Answer: C

          ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.

        6. 1.4 Stakeholder involvement

          A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Evidence not yet verified: an assessment of each group’s influence and needs. Verified evidence in the review file: a complete list of affected groups. Verified evidence in the review file: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Which action should the project manager take next based on this evidence?

          1. Agree suitable workshops, updates, and responsible owners.
          2. Analyze influence, impact, and information needs.
          3. Check participation and adjust the engagement approach.
          4. Identify the affected groups with operations representatives.
          Answer: B

          ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an assessment of each group’s influence and needs. An inventory names people; analysis determines how to engage them.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.

        7. 1.6 Customer satisfaction evidence

          A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Verified evidence in the review file: confirmed expectations of internal and external customers. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Verified evidence in the review file: an agreed response to the confirmed satisfaction gap. Verified evidence in the review file: a repeat measurement after the agreed response. Which action should the project manager take next based on this evidence?

          1. Agree a response with customers and the accountable owner.
          2. Measure satisfaction again after the response is applied.
          3. Confirm expectations with internal and external customers.
          4. Compare pilot evidence with the confirmed expectations.
          Answer: D

          ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. A complaint needs evidence about the gap before the response is selected.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.

        8. 1.8 Audience-specific reporting

          A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Verified evidence in the review file: confirmation that recipients understand and can respond. Verified evidence in the review file: delivery of a tailored report through the agreed channels. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Which action should the project manager take next based on this evidence?

          1. Agree the communication plan with the intended audiences.
          2. Distribute the tailored report using the agreed plan.
          3. Ask recipients for feedback and adjust future reports.
          4. Determine reporting needs and confidentiality requirements.
          Answer: A

          ECO task 1.8: Audience-specific reporting. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Planning makes reporting responsibilities and feedback explicit before information is distributed.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.

        9. 1.1 Shared outcomes and understanding

          A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: evidence that each operator interprets the vision consistently. Verified evidence in the review file: a communication owner and a date to review the vision. Verified evidence in the review file: the operators’ intended outcomes. Verified evidence in the review file: an agreed vision with measurable success criteria. Which action should the project manager take next based on this evidence?

          1. Assign the vision’s communication owner and review date.
          2. Interview the operators about their intended outcomes.
          3. Agree a shared vision and measurable success criteria.
          4. Test understanding and investigate conflicting interpretations.
          Answer: D

          ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: evidence that each operator interprets the vision consistently. A signature doesn't prove shared understanding; conflicting interpretations need examination.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.

        10. 1.2 Conflict diagnosis and resolution

          Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Verified evidence in the review file: a follow-up check that the agreement is working. Evidence not yet verified: a mutually agreed resolution and decision rights. Verified evidence in the review file: a neutral account of the underlying approval dispute. Verified evidence in the review file: the immediate enforcement of respectful discussion rules. Which action should the project manager take next based on this evidence?

          1. Review the next approval cycle with both teams.
          2. Establish and enforce respectful discussion rules.
          3. Hear both teams and establish the source of the dispute.
          4. Facilitate an agreement on approval responsibilities.
          Answer: D

          ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: a mutually agreed resolution and decision rights. An understood conflict still needs a resolution the parties can implement.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.

        11. 1.3 Team authority and tailored support

          A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Verified evidence in the review file: a review of members’ experience and support needs. Evidence not yet verified: a tailored delegation and coaching arrangement. Verified evidence in the review file: a feedback review of delegation and team concerns. Verified evidence in the review file: a shared release goal and clear decision responsibilities. Which action should the project manager take next based on this evidence?

          1. Delegate within agreed limits and coach where support is needed.
          2. Review results with the team and adjust leadership support.
          3. Agree the release goal and each role’s decision authority.
          4. Assess experience and ask members what support they need.
          Answer: A

          ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a tailored delegation and coaching arrangement. Experienced members can own decisions while less experienced members receive focused coaching.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.

        12. 1.5 Negotiating shared expectations

          A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Verified evidence in the review file: explicit response-time expectations from both departments. Verified evidence in the review file: a classification of stakeholder groups and decision authority. Verified evidence in the review file: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Which action should the project manager take next based on this evidence?

          1. Coach department leads on applying the agreed target.
          2. Facilitate agreement on the target and its trade-offs.
          3. Classify stakeholders by role and decision authority.
          4. Ask both departments to state measurable expectations.
          Answer: B

          ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Alignment requires agreement on competing expectations rather than silently choosing one department.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.

        13. 1.7 Operational knowledge handover

          A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: an inventory of critical diagnostic knowledge. Verified evidence in the review file: captured diagnostic examples and decision rules. Evidence not yet verified: guided practice for the receiving operations team. Verified evidence in the review file: an independent diagnosis and accepted handover evidence. Which action should the project manager take next based on this evidence?

          1. Identify critical knowledge with the specialist and operations.
          2. Capture failure examples and the specialist’s decision rules.
          3. Have operations diagnose a fresh failure without coaching.
          4. Run paired diagnostic practice with the receiving team.
          Answer: D

          ECO task 1.7: Operational knowledge handover. Evidence not yet verified: guided practice for the receiving operations team. Documents need practice so that the receiving team can apply the reasoning.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.

        14. 1.4 Stakeholder involvement

          A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Verified evidence in the review file: a complete list of affected groups. Evidence not yet verified: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Verified evidence in the review file: an assessment of each group’s influence and needs. Which action should the project manager take next based on this evidence?

          1. Check participation and adjust the engagement approach.
          2. Identify the affected groups with operations representatives.
          3. Analyze influence, impact, and information needs.
          4. Agree suitable workshops, updates, and responsible owners.
          Answer: A

          ECO task 1.4: Stakeholder involvement. Evidence not yet verified: feedback showing whether engagement reaches each group. An approved plan needs feedback to show whether it builds involvement and trust.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.

        15. 1.6 Customer satisfaction evidence

          A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Verified evidence in the review file: an agreed response to the confirmed satisfaction gap. Evidence not yet verified: a repeat measurement after the agreed response. Verified evidence in the review file: confirmed expectations of internal and external customers. Verified evidence in the review file: a comparison between pilot outcomes and customer expectations. Which action should the project manager take next based on this evidence?

          1. Confirm expectations with internal and external customers.
          2. Compare pilot evidence with the confirmed expectations.
          3. Agree a response with customers and the accountable owner.
          4. Measure satisfaction again after the response is applied.
          Answer: D

          ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: a repeat measurement after the agreed response. Customer expectations require continuing monitoring; an agreed action doesn't prove improvement.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.

        16. 1.8 Audience-specific reporting

          A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Evidence not yet verified: confirmation that recipients understand and can respond. Verified evidence in the review file: delivery of a tailored report through the agreed channels. Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Which action should the project manager take next based on this evidence?

          1. Determine reporting needs and confidentiality requirements.
          2. Agree the communication plan with the intended audiences.
          3. Ask recipients for feedback and adjust future reports.
          4. Distribute the tailored report using the agreed plan.
          Answer: C

          ECO task 1.8: Audience-specific reporting. Evidence not yet verified: confirmation that recipients understand and can respond. Successful transmission doesn't prove understanding; feedback closes the communication loop.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.

        17. 1.1 Shared outcomes and understanding

          A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: an agreed vision with measurable success criteria. Verified evidence in the review file: evidence that each operator interprets the vision consistently. Verified evidence in the review file: a communication owner and a date to review the vision. Evidence not yet verified: the operators’ intended outcomes. Which action should the project manager take next based on this evidence?

          1. Test understanding and investigate conflicting interpretations.
          2. Assign the vision’s communication owner and review date.
          3. Interview the operators about their intended outcomes.
          4. Agree a shared vision and measurable success criteria.
          Answer: C

          ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.

        18. 1.2 Conflict diagnosis and resolution

          Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: a neutral account of the underlying approval dispute. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Verified evidence in the review file: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Which action should the project manager take next based on this evidence?

          1. Facilitate an agreement on approval responsibilities.
          2. Review the next approval cycle with both teams.
          3. Hear both teams and establish the source of the dispute.
          4. Establish and enforce respectful discussion rules.
          Answer: D

          ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.

        19. 1.3 Team authority and tailored support

          A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Evidence not yet verified: a review of members’ experience and support needs. Verified evidence in the review file: a tailored delegation and coaching arrangement. Verified evidence in the review file: a feedback review of delegation and team concerns. Which action should the project manager take next based on this evidence?

          1. Delegate within agreed limits and coach where support is needed.
          2. Agree the release goal and each role’s decision authority.
          3. Review results with the team and adjust leadership support.
          4. Assess experience and ask members what support they need.
          Answer: B

          ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.

        20. 1.5 Negotiating shared expectations

          A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Verified evidence in the review file: support for department leads applying the agreed target. Verified evidence in the review file: a negotiated response-time target and accepted trade-offs. Evidence not yet verified: explicit response-time expectations from both departments. Which action should the project manager take next based on this evidence?

          1. Classify stakeholders by role and decision authority.
          2. Facilitate agreement on the target and its trade-offs.
          3. Coach department leads on applying the agreed target.
          4. Ask both departments to state measurable expectations.
          Answer: A

          ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.

        21. 1.7 Operational knowledge handover

          A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: guided practice for the receiving operations team. Verified evidence in the review file: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Evidence not yet verified: captured diagnostic examples and decision rules. Which action should the project manager take next based on this evidence?

          1. Have operations diagnose a fresh failure without coaching.
          2. Identify critical knowledge with the specialist and operations.
          3. Capture failure examples and the specialist’s decision rules.
          4. Run paired diagnostic practice with the receiving team.
          Answer: B

          ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.

        22. 1.4 Stakeholder involvement

          A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Verified evidence in the review file: feedback showing whether engagement reaches each group. Evidence not yet verified: an engagement approach agreed with affected groups. Verified evidence in the review file: an assessment of each group’s influence and needs. Evidence not yet verified: a complete list of affected groups. Which action should the project manager take next based on this evidence?

          1. Check participation and adjust the engagement approach.
          2. Analyze influence, impact, and information needs.
          3. Identify the affected groups with operations representatives.
          4. Agree suitable workshops, updates, and responsible owners.
          Answer: C

          ECO task 1.4: Stakeholder involvement. Evidence not yet verified: a complete list of affected groups. You can't tailor engagement for stakeholders you haven't identified.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.

        23. 1.6 Customer satisfaction evidence

          A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Verified evidence in the review file: a comparison between pilot outcomes and customer expectations. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. Verified evidence in the review file: a repeat measurement after the agreed response. Evidence not yet verified: confirmed expectations of internal and external customers. Which action should the project manager take next based on this evidence?

          1. Measure satisfaction again after the response is applied.
          2. Confirm expectations with internal and external customers.
          3. Compare pilot evidence with the confirmed expectations.
          4. Agree a response with customers and the accountable owner.
          Answer: B

          ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: confirmed expectations of internal and external customers. The team needs actual customer expectations before judging satisfaction.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.

        24. 1.8 Audience-specific reporting

          A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. Verified evidence in the review file: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Which action should the project manager take next based on this evidence?

          1. Determine reporting needs and confidentiality requirements.
          2. Ask recipients for feedback and adjust future reports.
          3. Agree the communication plan with the intended audiences.
          4. Distribute the tailored report using the agreed plan.
          Answer: A

          ECO task 1.8: Audience-specific reporting. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. The communication method must follow audience needs and mandatory restrictions.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.

        25. 1.1 Shared outcomes and understanding

          A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: the operators’ intended outcomes. Verified evidence in the review file: an agreed vision with measurable success criteria. Verified evidence in the review file: evidence that each operator interprets the vision consistently. Evidence not yet verified: a communication owner and a date to review the vision. Which action should the project manager take next based on this evidence?

          1. Agree a shared vision and measurable success criteria.
          2. Interview the operators about their intended outcomes.
          3. Test understanding and investigate conflicting interpretations.
          4. Assign the vision’s communication owner and review date.
          Answer: B

          ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.

        26. 1.2 Conflict diagnosis and resolution

          Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Evidence not yet verified: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Verified evidence in the review file: a neutral account of the underlying approval dispute. Which action should the project manager take next based on this evidence?

          1. Hear both teams and establish the source of the dispute.
          2. Establish and enforce respectful discussion rules.
          3. Facilitate an agreement on approval responsibilities.
          4. Review the next approval cycle with both teams.
          Answer: B

          ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.

        27. 1.3 Team authority and tailored support

          A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Verified evidence in the review file: a tailored delegation and coaching arrangement. Evidence not yet verified: a feedback review of delegation and team concerns. Evidence not yet verified: a shared release goal and clear decision responsibilities. Verified evidence in the review file: a review of members’ experience and support needs. Which action should the project manager take next based on this evidence?

          1. Agree the release goal and each role’s decision authority.
          2. Assess experience and ask members what support they need.
          3. Delegate within agreed limits and coach where support is needed.
          4. Review results with the team and adjust leadership support.
          Answer: A

          ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.

        28. 1.5 Negotiating shared expectations

          A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: support for department leads applying the agreed target. Verified evidence in the review file: a negotiated response-time target and accepted trade-offs. Verified evidence in the review file: explicit response-time expectations from both departments. Evidence not yet verified: a classification of stakeholder groups and decision authority. Which action should the project manager take next based on this evidence?

          1. Classify stakeholders by role and decision authority.
          2. Ask both departments to state measurable expectations.
          3. Facilitate agreement on the target and its trade-offs.
          4. Coach department leads on applying the agreed target.
          Answer: A

          ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.

        29. 1.7 Operational knowledge handover

          A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: captured diagnostic examples and decision rules. Verified evidence in the review file: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Which action should the project manager take next based on this evidence?

          1. Identify critical knowledge with the specialist and operations.
          2. Run paired diagnostic practice with the receiving team.
          3. Have operations diagnose a fresh failure without coaching.
          4. Capture failure examples and the specialist’s decision rules.
          Answer: A

          ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.

        30. 1.4 Stakeholder involvement

          A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Evidence not yet verified: an assessment of each group’s influence and needs. Verified evidence in the review file: a complete list of affected groups. Verified evidence in the review file: feedback showing whether engagement reaches each group. Evidence not yet verified: an engagement approach agreed with affected groups. Which action should the project manager take next based on this evidence?

          1. Agree suitable workshops, updates, and responsible owners.
          2. Check participation and adjust the engagement approach.
          3. Analyze influence, impact, and information needs.
          4. Identify the affected groups with operations representatives.
          Answer: C

          ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an assessment of each group’s influence and needs. An inventory names people; analysis determines how to engage them.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.

        31. 1.6 Customer satisfaction evidence

          A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Verified evidence in the review file: confirmed expectations of internal and external customers. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. Verified evidence in the review file: a repeat measurement after the agreed response. Which action should the project manager take next based on this evidence?

          1. Agree a response with customers and the accountable owner.
          2. Measure satisfaction again after the response is applied.
          3. Confirm expectations with internal and external customers.
          4. Compare pilot evidence with the confirmed expectations.
          Answer: D

          ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. A complaint needs evidence about the gap before the response is selected.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.

        32. 1.8 Audience-specific reporting

          A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Verified evidence in the review file: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Which action should the project manager take next based on this evidence?

          1. Distribute the tailored report using the agreed plan.
          2. Ask recipients for feedback and adjust future reports.
          3. Determine reporting needs and confidentiality requirements.
          4. Agree the communication plan with the intended audiences.
          Answer: D

          ECO task 1.8: Audience-specific reporting. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Planning makes reporting responsibilities and feedback explicit before information is distributed.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.

        33. 1.1 Shared outcomes and understanding

          A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Verified evidence in the review file: evidence that each operator interprets the vision consistently. Evidence not yet verified: a communication owner and a date to review the vision. Verified evidence in the review file: the operators’ intended outcomes. Evidence not yet verified: an agreed vision with measurable success criteria. Which action should the project manager take next based on this evidence?

          1. Assign the vision’s communication owner and review date.
          2. Interview the operators about their intended outcomes.
          3. Test understanding and investigate conflicting interpretations.
          4. Agree a shared vision and measurable success criteria.
          Answer: D

          ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: an agreed vision with measurable success criteria. Agreeing the outcome resolves competing definitions of success before promotion.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.

        34. 1.2 Conflict diagnosis and resolution

          Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Evidence not yet verified: a neutral account of the underlying approval dispute. Verified evidence in the review file: the immediate enforcement of respectful discussion rules. Which action should the project manager take next based on this evidence?

          1. Review the next approval cycle with both teams.
          2. Establish and enforce respectful discussion rules.
          3. Facilitate an agreement on approval responsibilities.
          4. Hear both teams and establish the source of the dispute.
          Answer: D

          ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: a neutral account of the underlying approval dispute. Selecting a resolution without the source and context risks treating the wrong problem.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.

        35. 1.3 Team authority and tailored support

          A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a review of members’ experience and support needs. Verified evidence in the review file: a tailored delegation and coaching arrangement. Evidence not yet verified: a feedback review of delegation and team concerns. Verified evidence in the review file: a shared release goal and clear decision responsibilities. Which action should the project manager take next based on this evidence?

          1. Assess experience and ask members what support they need.
          2. Review results with the team and adjust leadership support.
          3. Agree the release goal and each role’s decision authority.
          4. Delegate within agreed limits and coach where support is needed.
          Answer: A

          ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a review of members’ experience and support needs. A leadership style should respond to demonstrated capability and needs, not one rule for everyone.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.

        36. 1.5 Negotiating shared expectations

          A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: explicit response-time expectations from both departments. Verified evidence in the review file: a classification of stakeholder groups and decision authority. Evidence not yet verified: support for department leads applying the agreed target. Verified evidence in the review file: a negotiated response-time target and accepted trade-offs. Which action should the project manager take next based on this evidence?

          1. Coach department leads on applying the agreed target.
          2. Classify stakeholders by role and decision authority.
          3. Ask both departments to state measurable expectations.
          4. Facilitate agreement on the target and its trade-offs.
          Answer: C

          ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: explicit response-time expectations from both departments. Vague expectations can't be compared or negotiated reliably.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.

        37. 1.7 Operational knowledge handover

          A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: an inventory of critical diagnostic knowledge. Evidence not yet verified: captured diagnostic examples and decision rules. Verified evidence in the review file: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Which action should the project manager take next based on this evidence?

          1. Capture failure examples and the specialist’s decision rules.
          2. Identify critical knowledge with the specialist and operations.
          3. Run paired diagnostic practice with the receiving team.
          4. Have operations diagnose a fresh failure without coaching.
          Answer: A

          ECO task 1.7: Operational knowledge handover. Evidence not yet verified: captured diagnostic examples and decision rules. Capturing tacit reasoning makes more knowledge available than a list of system components.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.

        38. 1.4 Stakeholder involvement

          A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Verified evidence in the review file: a complete list of affected groups. Evidence not yet verified: feedback showing whether engagement reaches each group. Evidence not yet verified: an engagement approach agreed with affected groups. Verified evidence in the review file: an assessment of each group’s influence and needs. Which action should the project manager take next based on this evidence?

          1. Identify the affected groups with operations representatives.
          2. Agree suitable workshops, updates, and responsible owners.
          3. Analyze influence, impact, and information needs.
          4. Check participation and adjust the engagement approach.
          Answer: B

          ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an engagement approach agreed with affected groups. The approach should reflect the assessed needs instead of sending everyone identical reports.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.

        39. 1.6 Customer satisfaction evidence

          A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. Evidence not yet verified: a repeat measurement after the agreed response. Verified evidence in the review file: confirmed expectations of internal and external customers. Verified evidence in the review file: a comparison between pilot outcomes and customer expectations. Which action should the project manager take next based on this evidence?

          1. Confirm expectations with internal and external customers.
          2. Agree a response with customers and the accountable owner.
          3. Compare pilot evidence with the confirmed expectations.
          4. Measure satisfaction again after the response is applied.
          Answer: B

          ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. The response should address the measured gap through the appropriate decision process.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.

        40. 1.8 Audience-specific reporting

          A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Evidence not yet verified: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Which action should the project manager take next based on this evidence?

          1. Determine reporting needs and confidentiality requirements.
          2. Agree the communication plan with the intended audiences.
          3. Ask recipients for feedback and adjust future reports.
          4. Distribute the tailored report using the agreed plan.
          Answer: D

          ECO task 1.8: Audience-specific reporting. Evidence not yet verified: delivery of a tailored report through the agreed channels. A communication plan produces no shared information until the report reaches its audience.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.

        41. 1.1 Shared outcomes and understanding

          A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: an agreed vision with measurable success criteria. Evidence not yet verified: evidence that each operator interprets the vision consistently. Verified evidence in the review file: a communication owner and a date to review the vision. Evidence not yet verified: the operators’ intended outcomes. Which action should the project manager take next based on this evidence?

          1. Test understanding and investigate conflicting interpretations.
          2. Assign the vision’s communication owner and review date.
          3. Interview the operators about their intended outcomes.
          4. Agree a shared vision and measurable success criteria.
          Answer: C

          ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.

        42. 1.2 Conflict diagnosis and resolution

          Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: a neutral account of the underlying approval dispute. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Verified evidence in the review file: a follow-up check that the agreement is working. Evidence not yet verified: a mutually agreed resolution and decision rights. Which action should the project manager take next based on this evidence?

          1. Facilitate an agreement on approval responsibilities.
          2. Establish and enforce respectful discussion rules.
          3. Review the next approval cycle with both teams.
          4. Hear both teams and establish the source of the dispute.
          Answer: B

          ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.

        43. 1.3 Team authority and tailored support

          A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Evidence not yet verified: a review of members’ experience and support needs. Evidence not yet verified: a tailored delegation and coaching arrangement. Verified evidence in the review file: a feedback review of delegation and team concerns. Which action should the project manager take next based on this evidence?

          1. Delegate within agreed limits and coach where support is needed.
          2. Review results with the team and adjust leadership support.
          3. Agree the release goal and each role’s decision authority.
          4. Assess experience and ask members what support they need.
          Answer: C

          ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.

        44. 1.5 Negotiating shared expectations

          A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Verified evidence in the review file: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Evidence not yet verified: explicit response-time expectations from both departments. Which action should the project manager take next based on this evidence?

          1. Facilitate agreement on the target and its trade-offs.
          2. Classify stakeholders by role and decision authority.
          3. Coach department leads on applying the agreed target.
          4. Ask both departments to state measurable expectations.
          Answer: B

          ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.

        45. 1.7 Operational knowledge handover

          A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Evidence not yet verified: guided practice for the receiving operations team. Verified evidence in the review file: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Evidence not yet verified: captured diagnostic examples and decision rules. Which action should the project manager take next based on this evidence?

          1. Have operations diagnose a fresh failure without coaching.
          2. Identify critical knowledge with the specialist and operations.
          3. Capture failure examples and the specialist’s decision rules.
          4. Run paired diagnostic practice with the receiving team.
          Answer: B

          ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.

        46. 1.4 Stakeholder involvement

          A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Evidence not yet verified: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Evidence not yet verified: an assessment of each group’s influence and needs. Evidence not yet verified: a complete list of affected groups. Which action should the project manager take next based on this evidence?

          1. Identify the affected groups with operations representatives.
          2. Check participation and adjust the engagement approach.
          3. Analyze influence, impact, and information needs.
          4. Agree suitable workshops, updates, and responsible owners.
          Answer: A

          ECO task 1.4: Stakeholder involvement. Evidence not yet verified: a complete list of affected groups. You can't tailor engagement for stakeholders you haven't identified.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.

        47. 1.6 Customer satisfaction evidence

          A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Verified evidence in the review file: an agreed response to the confirmed satisfaction gap. Evidence not yet verified: a repeat measurement after the agreed response. Evidence not yet verified: confirmed expectations of internal and external customers. Which action should the project manager take next based on this evidence?

          1. Measure satisfaction again after the response is applied.
          2. Confirm expectations with internal and external customers.
          3. Compare pilot evidence with the confirmed expectations.
          4. Agree a response with customers and the accountable owner.
          Answer: B

          ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: confirmed expectations of internal and external customers. The team needs actual customer expectations before judging satisfaction.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.

        48. 1.8 Audience-specific reporting

          A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. Evidence not yet verified: confirmation that recipients understand and can respond. Verified evidence in the review file: delivery of a tailored report through the agreed channels. Which action should the project manager take next based on this evidence?

          1. Ask recipients for feedback and adjust future reports.
          2. Agree the communication plan with the intended audiences.
          3. Determine reporting needs and confidentiality requirements.
          4. Distribute the tailored report using the agreed plan.
          Answer: C

          ECO task 1.8: Audience-specific reporting. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. The communication method must follow audience needs and mandatory restrictions.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.

        49. 1.1 Shared outcomes and understanding

          A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: the operators’ intended outcomes. Verified evidence in the review file: an agreed vision with measurable success criteria. Evidence not yet verified: evidence that each operator interprets the vision consistently. Evidence not yet verified: a communication owner and a date to review the vision. Which action should the project manager take next based on this evidence?

          1. Agree a shared vision and measurable success criteria.
          2. Interview the operators about their intended outcomes.
          3. Test understanding and investigate conflicting interpretations.
          4. Assign the vision’s communication owner and review date.
          Answer: B

          ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.

        50. 1.2 Conflict diagnosis and resolution

          Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Evidence not yet verified: a follow-up check that the agreement is working. Evidence not yet verified: a mutually agreed resolution and decision rights. Verified evidence in the review file: a neutral account of the underlying approval dispute. Which action should the project manager take next based on this evidence?

          1. Hear both teams and establish the source of the dispute.
          2. Facilitate an agreement on approval responsibilities.
          3. Review the next approval cycle with both teams.
          4. Establish and enforce respectful discussion rules.
          Answer: D

          ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.

        51. 1.3 Team authority and tailored support

          A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a tailored delegation and coaching arrangement. Evidence not yet verified: a feedback review of delegation and team concerns. Evidence not yet verified: a shared release goal and clear decision responsibilities. Verified evidence in the review file: a review of members’ experience and support needs. Which action should the project manager take next based on this evidence?

          1. Assess experience and ask members what support they need.
          2. Delegate within agreed limits and coach where support is needed.
          3. Review results with the team and adjust leadership support.
          4. Agree the release goal and each role’s decision authority.
          Answer: D

          ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.

        52. 1.5 Negotiating shared expectations

          A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Verified evidence in the review file: explicit response-time expectations from both departments. Evidence not yet verified: a classification of stakeholder groups and decision authority. Which action should the project manager take next based on this evidence?

          1. Classify stakeholders by role and decision authority.
          2. Ask both departments to state measurable expectations.
          3. Facilitate agreement on the target and its trade-offs.
          4. Coach department leads on applying the agreed target.
          Answer: A

          ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.

        53. 1.7 Operational knowledge handover

          A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: captured diagnostic examples and decision rules. Evidence not yet verified: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Which action should the project manager take next based on this evidence?

          1. Run paired diagnostic practice with the receiving team.
          2. Identify critical knowledge with the specialist and operations.
          3. Have operations diagnose a fresh failure without coaching.
          4. Capture failure examples and the specialist’s decision rules.
          Answer: B

          ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.

        54. 1.4 Stakeholder involvement

          A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Evidence not yet verified: an assessment of each group’s influence and needs. Verified evidence in the review file: a complete list of affected groups. Evidence not yet verified: feedback showing whether engagement reaches each group. Evidence not yet verified: an engagement approach agreed with affected groups. Which action should the project manager take next based on this evidence?

          1. Analyze influence, impact, and information needs.
          2. Agree suitable workshops, updates, and responsible owners.
          3. Check participation and adjust the engagement approach.
          4. Identify the affected groups with operations representatives.
          Answer: A

          ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an assessment of each group’s influence and needs. An inventory names people; analysis determines how to engage them.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.

        55. 1.6 Customer satisfaction evidence

          A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Verified evidence in the review file: confirmed expectations of internal and external customers. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. Evidence not yet verified: a repeat measurement after the agreed response. Which action should the project manager take next based on this evidence?

          1. Agree a response with customers and the accountable owner.
          2. Compare pilot evidence with the confirmed expectations.
          3. Measure satisfaction again after the response is applied.
          4. Confirm expectations with internal and external customers.
          Answer: B

          ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. A complaint needs evidence about the gap before the response is selected.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.

        56. 1.8 Audience-specific reporting

          A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Evidence not yet verified: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Which action should the project manager take next based on this evidence?

          1. Distribute the tailored report using the agreed plan.
          2. Ask recipients for feedback and adjust future reports.
          3. Agree the communication plan with the intended audiences.
          4. Determine reporting needs and confidentiality requirements.
          Answer: C

          ECO task 1.8: Audience-specific reporting. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Planning makes reporting responsibilities and feedback explicit before information is distributed.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.

        57. 1.3 Team authority and tailored support

          A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a tailored delegation and coaching arrangement. Evidence not yet verified: a feedback review of delegation and team concerns. Evidence not yet verified: a shared release goal and clear decision responsibilities. Evidence not yet verified: a review of members’ experience and support needs. Which action should the project manager take next based on this evidence?

          1. Agree the release goal and each role’s decision authority.
          2. Review results with the team and adjust leadership support.
          3. Assess experience and ask members what support they need.
          4. Delegate within agreed limits and coach where support is needed.
          Answer: A

          ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.

        58. 1.5 Negotiating shared expectations

          A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Evidence not yet verified: explicit response-time expectations from both departments. Evidence not yet verified: a classification of stakeholder groups and decision authority. Which action should the project manager take next based on this evidence?

          1. Coach department leads on applying the agreed target.
          2. Classify stakeholders by role and decision authority.
          3. Ask both departments to state measurable expectations.
          4. Facilitate agreement on the target and its trade-offs.
          Answer: B

          ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.

        59. 1.7 Operational knowledge handover

          A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Evidence not yet verified: captured diagnostic examples and decision rules. Evidence not yet verified: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Which action should the project manager take next based on this evidence?

          1. Have operations diagnose a fresh failure without coaching.
          2. Identify critical knowledge with the specialist and operations.
          3. Capture failure examples and the specialist’s decision rules.
          4. Run paired diagnostic practice with the receiving team.
          Answer: B

          ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.

        60. 2.1 Integrated delivery planning

          A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Evidence not yet verified: an assessment of requirement stability and delivery constraints. Verified evidence in the review file: an agreed hybrid approach for installation and iterative software. Verified evidence in the review file: an integrated dependency, resource, and delivery plan. Verified evidence in the review file: a review of plan gaps and continuing business value. Which action should the project manager take next based on this evidence?

          1. Agree a hybrid approach with explicit integration points.
          2. Integrate dependencies, resources, and delivery milestones.
          3. Assess uncertainty, constraints, and required delivery outcomes.
          4. Review the integrated plan for gaps and continued value.
          Answer: C

          ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.

        61. 2.2 Release boundaries and work breakdown

          A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Evidence not yet verified: documented requirements and acceptance criteria. Verified evidence in the review file: a completeness review of the scope breakdown. Verified evidence in the review file: a breakdown into assignable work with traceability. Verified evidence in the review file: an agreed release boundary and explicit exclusions. Which action should the project manager take next based on this evidence?

          1. Agree included services and exclusions with stakeholders.
          2. Break the agreed scope into traceable work packages.
          3. Check the breakdown for omissions and unauthorized additions.
          4. Elicit requirements and define testable acceptance criteria.
          Answer: D

          ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.

        62. 2.3 Incremental benefit realization

          A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Verified evidence in the review file: an agreed usable increment and release test. Verified evidence in the review file: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Verified evidence in the review file: a ranked comparison of delivery options and dependencies. Which action should the project manager take next based on this evidence?

          1. Rank delivery options by benefit, feedback, and dependencies.
          2. Plan a usable increment that tests the prioritized benefit.
          3. Measure realized benefit and use it to reprioritize work.
          4. Agree the benefit metric and its accountable business owner.
          Answer: D

          ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.

        63. 2.5 Supplier selection and acceptance

          A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Verified evidence in the review file: verified supplier performance and acceptance evidence. Verified evidence in the review file: an authorized contract with measurable acceptance terms. Verified evidence in the review file: a documented supplier evaluation under the agreed criteria. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Which action should the project manager take next based on this evidence?

          1. Evaluate bids using the published procurement criteria.
          2. Negotiate and authorize the contract’s acceptance obligations.
          3. Define evaluation criteria and select suitable contract terms.
          4. Compare supplier evidence with the contractual acceptance terms.
          Answer: C

          ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.

        64. 2.7 Quality evidence and improvement

          A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Verified evidence in the review file: a quality plan with preventive controls and test methods. Verified evidence in the review file: pilot measurements collected using the approved test method. Verified evidence in the review file: an evidence-based improvement and effectiveness review. Evidence not yet verified: testable quality requirements and applicable standards. Which action should the project manager take next based on this evidence?

          1. Execute the approved tests and record pilot results.
          2. Confirm quality criteria and mandatory seal standards.
          3. Analyze defects, improve the process, and verify the result.
          4. Plan prevention, inspection, and evidence collection.
          Answer: B

          ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.

        65. 2.9 Reconciled project reporting

          A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Verified evidence in the review file: reconciled data from the authoritative project records. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Verified evidence in the review file: an accessible version-controlled report for decision makers. Verified evidence in the review file: an interpretation of progress, variance, and forecast implications. Which action should the project manager take next based on this evidence?

          1. Analyze reconciled progress and explain forecast implications.
          2. Agree metric definitions and the reporting cutoff.
          3. Publish the reviewed report with access and version controls.
          4. Reconcile the report data against authoritative records.
          Answer: B

          ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.

        66. 2.4 Capacity and resource commitments

          Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: the required skills and estimated effort for each test. Evidence not yet verified: confirmed technician and laboratory availability. Verified evidence in the review file: an agreed allocation that respects authorized capacity. Verified evidence in the review file: a utilization check against the agreed allocation. Which action should the project manager take next based on this evidence?

          1. Negotiate a feasible allocation with both project owners.
          2. Monitor utilization and address new resource conflicts.
          3. Define test resource requirements and estimate the effort.
          4. Confirm calendars and competing resource commitments.
          Answer: D

          ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: confirmed technician and laboratory availability. A resource plan can't assume availability across competing projects.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.

        67. 2.6 Financial forecasting and control

          A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an estimate of costs and identified financial risks. Verified evidence in the review file: a governance review of the forecast and funding variance. Verified evidence in the review file: reconciled actual spending and remaining cost estimates. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Which action should the project manager take next based on this evidence?

          1. Reconcile actual costs and estimate the remaining work.
          2. Obtain baseline approval and justify contingency reserves.
          3. Report the forecast and seek required funding decisions.
          4. Estimate costs and identify relevant financial uncertainty.
          Answer: B

          ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Contingency addresses identified risk and needs authorization under the funding rules.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.

        68. 2.8 Schedule dependencies and baselines

          A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Verified evidence in the review file: an approved schedule baseline coordinated with operations. Verified evidence in the review file: an analysis of actual progress and schedule variation. Verified evidence in the review file: validated activity dependencies and external operating constraints. Evidence not yet verified: duration estimates and resource calendars. Which action should the project manager take next based on this evidence?

          1. Compare actual progress with the baseline and assess impact.
          2. Validate dependencies and the permitted shutdown window.
          3. Estimate durations using team input and resource calendars.
          4. Coordinate dates with operations and approve the baseline.
          Answer: C

          ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: duration estimates and resource calendars. Dependency order alone doesn't establish feasible dates without durations and availability.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.

        69. 2.10 Acceptance and operational transition

          A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release. Verified evidence in the review file: operations readiness and an accepted support handover. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Obtain acceptance evidence from the authorized stakeholders.
          2. Complete financial closure, archive lessons, and release resources.
          3. Confirm the contractual and project closure criteria.
          4. Validate operations readiness and complete the support handover.
          Answer: A

          ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Completion claims need authorized acceptance against the agreed criteria.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.

        70. 2.1 Integrated delivery planning

          A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Verified evidence in the review file: an agreed hybrid approach for installation and iterative software. Evidence not yet verified: an integrated dependency, resource, and delivery plan. Verified evidence in the review file: a review of plan gaps and continuing business value. Verified evidence in the review file: an assessment of requirement stability and delivery constraints. Which action should the project manager take next based on this evidence?

          1. Review the integrated plan for gaps and continued value.
          2. Integrate dependencies, resources, and delivery milestones.
          3. Assess uncertainty, constraints, and required delivery outcomes.
          4. Agree a hybrid approach with explicit integration points.
          Answer: B

          ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an integrated dependency, resource, and delivery plan. Separate component plans need reconciliation at their shared dependencies.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.

        71. 2.2 Release boundaries and work breakdown

          A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Verified evidence in the review file: an agreed release boundary and explicit exclusions. Verified evidence in the review file: documented requirements and acceptance criteria. Verified evidence in the review file: a completeness review of the scope breakdown. Evidence not yet verified: a breakdown into assignable work with traceability. Which action should the project manager take next based on this evidence?

          1. Check the breakdown for omissions and unauthorized additions.
          2. Elicit requirements and define testable acceptance criteria.
          3. Break the agreed scope into traceable work packages.
          4. Agree included services and exclusions with stakeholders.
          Answer: C

          ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: a breakdown into assignable work with traceability. Decomposition translates an agreed boundary into manageable work.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.

        72. 2.3 Incremental benefit realization

          A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Verified evidence in the review file: a measurable benefit agreed with the business owner. Verified evidence in the review file: a ranked comparison of delivery options and dependencies. Evidence not yet verified: an agreed usable increment and release test. Verified evidence in the review file: benefit measurement after customers use the increment. Which action should the project manager take next based on this evidence?

          1. Agree the benefit metric and its accountable business owner.
          2. Rank delivery options by benefit, feedback, and dependencies.
          3. Plan a usable increment that tests the prioritized benefit.
          4. Measure realized benefit and use it to reprioritize work.
          Answer: C

          ECO task 2.3: Incremental benefit realization. Evidence not yet verified: an agreed usable increment and release test. A usable increment tests value sooner than a collection of unfinished components.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.

        73. 2.5 Supplier selection and acceptance

          A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Verified evidence in the review file: evaluation criteria and an appropriate allocation of contract risk. Verified evidence in the review file: verified supplier performance and acceptance evidence. Evidence not yet verified: an authorized contract with measurable acceptance terms. Verified evidence in the review file: a documented supplier evaluation under the agreed criteria. Which action should the project manager take next based on this evidence?

          1. Define evaluation criteria and select suitable contract terms.
          2. Evaluate bids using the published procurement criteria.
          3. Compare supplier evidence with the contractual acceptance terms.
          4. Negotiate and authorize the contract’s acceptance obligations.
          Answer: D

          ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: an authorized contract with measurable acceptance terms. A preferred bidder still needs an authorized agreement before contractual work starts.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.

        74. 2.7 Quality evidence and improvement

          A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Evidence not yet verified: pilot measurements collected using the approved test method. Verified evidence in the review file: an evidence-based improvement and effectiveness review. Verified evidence in the review file: testable quality requirements and applicable standards. Verified evidence in the review file: a quality plan with preventive controls and test methods. Which action should the project manager take next based on this evidence?

          1. Confirm quality criteria and mandatory seal standards.
          2. Execute the approved tests and record pilot results.
          3. Plan prevention, inspection, and evidence collection.
          4. Analyze defects, improve the process, and verify the result.
          Answer: B

          ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: pilot measurements collected using the approved test method. Inspection evidence is needed before diagnosing the production process from pilot results.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.

        75. 2.9 Reconciled project reporting

          A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Verified evidence in the review file: an accessible version-controlled report for decision makers. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Verified evidence in the review file: reconciled data from the authoritative project records. Verified evidence in the review file: metric definitions, data owners, and a common reporting date. Which action should the project manager take next based on this evidence?

          1. Agree metric definitions and the reporting cutoff.
          2. Reconcile the report data against authoritative records.
          3. Analyze reconciled progress and explain forecast implications.
          4. Publish the reviewed report with access and version controls.
          Answer: C

          ECO task 2.9: Reconciled project reporting. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Reporting should explain the meaning of the measures, not only reproduce their values.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.

        76. 2.4 Capacity and resource commitments

          Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: confirmed technician and laboratory availability. Verified evidence in the review file: an agreed allocation that respects authorized capacity. Evidence not yet verified: a utilization check against the agreed allocation. Verified evidence in the review file: the required skills and estimated effort for each test. Which action should the project manager take next based on this evidence?

          1. Monitor utilization and address new resource conflicts.
          2. Confirm calendars and competing resource commitments.
          3. Negotiate a feasible allocation with both project owners.
          4. Define test resource requirements and estimate the effort.
          Answer: A

          ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: a utilization check against the agreed allocation. Resource availability changes during delivery and requires ongoing adjustment.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.

        77. 2.6 Financial forecasting and control

          A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an authorized baseline and risk-based contingency allocation. Verified evidence in the review file: an estimate of costs and identified financial risks. Evidence not yet verified: a governance review of the forecast and funding variance. Verified evidence in the review file: reconciled actual spending and remaining cost estimates. Which action should the project manager take next based on this evidence?

          1. Report the forecast and seek required funding decisions.
          2. Obtain baseline approval and justify contingency reserves.
          3. Reconcile actual costs and estimate the remaining work.
          4. Estimate costs and identify relevant financial uncertainty.
          Answer: A

          ECO task 2.6: Financial forecasting and control. Evidence not yet verified: a governance review of the forecast and funding variance. A projected overrun must follow governance thresholds rather than silently consuming reserves.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.

        78. 2.8 Schedule dependencies and baselines

          A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Verified evidence in the review file: validated activity dependencies and external operating constraints. Verified evidence in the review file: duration estimates and resource calendars. Verified evidence in the review file: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Which action should the project manager take next based on this evidence?

          1. Estimate durations using team input and resource calendars.
          2. Compare actual progress with the baseline and assess impact.
          3. Coordinate dates with operations and approve the baseline.
          4. Validate dependencies and the permitted shutdown window.
          Answer: B

          ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: an analysis of actual progress and schedule variation. Activity slippage matters through its dependencies and available float, not lateness alone.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.

        79. 2.10 Acceptance and operational transition

          A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria. Evidence not yet verified: closed contracts, archived lessons, and authorized resource release. Verified evidence in the review file: operations readiness and an accepted support handover. Verified evidence in the review file: formal stakeholder acceptance of completed deliverables. Which action should the project manager take next based on this evidence?

          1. Obtain acceptance evidence from the authorized stakeholders.
          2. Complete financial closure, archive lessons, and release resources.
          3. Validate operations readiness and complete the support handover.
          4. Confirm the contractual and project closure criteria.
          Answer: B

          ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: closed contracts, archived lessons, and authorized resource release. Administrative closure follows acceptance and transition so that obligations remain covered.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.

        80. 2.1 Integrated delivery planning

          A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Verified evidence in the review file: an integrated dependency, resource, and delivery plan. Verified evidence in the review file: a review of plan gaps and continuing business value. Evidence not yet verified: an assessment of requirement stability and delivery constraints. Evidence not yet verified: an agreed hybrid approach for installation and iterative software. Which action should the project manager take next based on this evidence?

          1. Review the integrated plan for gaps and continued value.
          2. Assess uncertainty, constraints, and required delivery outcomes.
          3. Agree a hybrid approach with explicit integration points.
          4. Integrate dependencies, resources, and delivery milestones.
          Answer: B

          ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.

        81. 2.2 Release boundaries and work breakdown

          A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Verified evidence in the review file: a completeness review of the scope breakdown. Verified evidence in the review file: a breakdown into assignable work with traceability. Evidence not yet verified: an agreed release boundary and explicit exclusions. Evidence not yet verified: documented requirements and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Check the breakdown for omissions and unauthorized additions.
          2. Elicit requirements and define testable acceptance criteria.
          3. Agree included services and exclusions with stakeholders.
          4. Break the agreed scope into traceable work packages.
          Answer: B

          ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.

        82. 2.3 Incremental benefit realization

          A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Verified evidence in the review file: an agreed usable increment and release test. Verified evidence in the review file: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Which action should the project manager take next based on this evidence?

          1. Agree the benefit metric and its accountable business owner.
          2. Measure realized benefit and use it to reprioritize work.
          3. Rank delivery options by benefit, feedback, and dependencies.
          4. Plan a usable increment that tests the prioritized benefit.
          Answer: A

          ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.

        83. 2.5 Supplier selection and acceptance

          A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Evidence not yet verified: a documented supplier evaluation under the agreed criteria. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Verified evidence in the review file: verified supplier performance and acceptance evidence. Verified evidence in the review file: an authorized contract with measurable acceptance terms. Which action should the project manager take next based on this evidence?

          1. Compare supplier evidence with the contractual acceptance terms.
          2. Define evaluation criteria and select suitable contract terms.
          3. Evaluate bids using the published procurement criteria.
          4. Negotiate and authorize the contract’s acceptance obligations.
          Answer: B

          ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.

        84. 2.7 Quality evidence and improvement

          A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Evidence not yet verified: testable quality requirements and applicable standards. Evidence not yet verified: a quality plan with preventive controls and test methods. Verified evidence in the review file: pilot measurements collected using the approved test method. Verified evidence in the review file: an evidence-based improvement and effectiveness review. Which action should the project manager take next based on this evidence?

          1. Plan prevention, inspection, and evidence collection.
          2. Execute the approved tests and record pilot results.
          3. Analyze defects, improve the process, and verify the result.
          4. Confirm quality criteria and mandatory seal standards.
          Answer: D

          ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.

        85. 2.9 Reconciled project reporting

          A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Verified evidence in the review file: an accessible version-controlled report for decision makers. Verified evidence in the review file: an interpretation of progress, variance, and forecast implications. Evidence not yet verified: reconciled data from the authoritative project records. Which action should the project manager take next based on this evidence?

          1. Reconcile the report data against authoritative records.
          2. Agree metric definitions and the reporting cutoff.
          3. Analyze reconciled progress and explain forecast implications.
          4. Publish the reviewed report with access and version controls.
          Answer: B

          ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.

        86. 2.4 Capacity and resource commitments

          Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Evidence not yet verified: an agreed allocation that respects authorized capacity. Verified evidence in the review file: a utilization check against the agreed allocation. Evidence not yet verified: the required skills and estimated effort for each test. Verified evidence in the review file: confirmed technician and laboratory availability. Which action should the project manager take next based on this evidence?

          1. Confirm calendars and competing resource commitments.
          2. Define test resource requirements and estimate the effort.
          3. Negotiate a feasible allocation with both project owners.
          4. Monitor utilization and address new resource conflicts.
          Answer: B

          ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: the required skills and estimated effort for each test. Allocation needs the required capabilities and workload, not only headcount.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.

        87. 2.6 Financial forecasting and control

          A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: a governance review of the forecast and funding variance. Evidence not yet verified: reconciled actual spending and remaining cost estimates. Verified evidence in the review file: an authorized baseline and risk-based contingency allocation. Evidence not yet verified: an estimate of costs and identified financial risks. Which action should the project manager take next based on this evidence?

          1. Obtain baseline approval and justify contingency reserves.
          2. Reconcile actual costs and estimate the remaining work.
          3. Report the forecast and seek required funding decisions.
          4. Estimate costs and identify relevant financial uncertainty.
          Answer: D

          ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an estimate of costs and identified financial risks. Reserves and forecasts require a cost estimate and identified uncertainties.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.

        88. 2.8 Schedule dependencies and baselines

          A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Verified evidence in the review file: duration estimates and resource calendars. Evidence not yet verified: an approved schedule baseline coordinated with operations. Verified evidence in the review file: an analysis of actual progress and schedule variation. Evidence not yet verified: validated activity dependencies and external operating constraints. Which action should the project manager take next based on this evidence?

          1. Coordinate dates with operations and approve the baseline.
          2. Compare actual progress with the baseline and assess impact.
          3. Validate dependencies and the permitted shutdown window.
          4. Estimate durations using team input and resource calendars.
          Answer: C

          ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: validated activity dependencies and external operating constraints. The schedule logic must respect prerequisites and external constraints.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.

        89. 2.10 Acceptance and operational transition

          A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Verified evidence in the review file: formal stakeholder acceptance of completed deliverables. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release. Evidence not yet verified: operations readiness and an accepted support handover. Which action should the project manager take next based on this evidence?

          1. Validate operations readiness and complete the support handover.
          2. Complete financial closure, archive lessons, and release resources.
          3. Confirm the contractual and project closure criteria.
          4. Obtain acceptance evidence from the authorized stakeholders.
          Answer: C

          ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Closure requires known criteria instead of assuming that the planned end date is enough.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.

        90. 2.1 Integrated delivery planning

          A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Evidence not yet verified: an assessment of requirement stability and delivery constraints. Verified evidence in the review file: an agreed hybrid approach for installation and iterative software. Verified evidence in the review file: an integrated dependency, resource, and delivery plan. Evidence not yet verified: a review of plan gaps and continuing business value. Which action should the project manager take next based on this evidence?

          1. Integrate dependencies, resources, and delivery milestones.
          2. Review the integrated plan for gaps and continued value.
          3. Agree a hybrid approach with explicit integration points.
          4. Assess uncertainty, constraints, and required delivery outcomes.
          Answer: D

          ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.

        91. 2.2 Release boundaries and work breakdown

          A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Evidence not yet verified: documented requirements and acceptance criteria. Evidence not yet verified: a completeness review of the scope breakdown. Verified evidence in the review file: a breakdown into assignable work with traceability. Verified evidence in the review file: an agreed release boundary and explicit exclusions. Which action should the project manager take next based on this evidence?

          1. Break the agreed scope into traceable work packages.
          2. Check the breakdown for omissions and unauthorized additions.
          3. Elicit requirements and define testable acceptance criteria.
          4. Agree included services and exclusions with stakeholders.
          Answer: C

          ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.

        92. 2.3 Incremental benefit realization

          A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Verified evidence in the review file: an agreed usable increment and release test. Evidence not yet verified: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Verified evidence in the review file: a ranked comparison of delivery options and dependencies. Which action should the project manager take next based on this evidence?

          1. Measure realized benefit and use it to reprioritize work.
          2. Rank delivery options by benefit, feedback, and dependencies.
          3. Agree the benefit metric and its accountable business owner.
          4. Plan a usable increment that tests the prioritized benefit.
          Answer: C

          ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.

        93. 2.5 Supplier selection and acceptance

          A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Evidence not yet verified: verified supplier performance and acceptance evidence. Verified evidence in the review file: an authorized contract with measurable acceptance terms. Verified evidence in the review file: a documented supplier evaluation under the agreed criteria. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Which action should the project manager take next based on this evidence?

          1. Compare supplier evidence with the contractual acceptance terms.
          2. Evaluate bids using the published procurement criteria.
          3. Define evaluation criteria and select suitable contract terms.
          4. Negotiate and authorize the contract’s acceptance obligations.
          Answer: C

          ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.

        94. 2.7 Quality evidence and improvement

          A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Verified evidence in the review file: a quality plan with preventive controls and test methods. Verified evidence in the review file: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Evidence not yet verified: testable quality requirements and applicable standards. Which action should the project manager take next based on this evidence?

          1. Analyze defects, improve the process, and verify the result.
          2. Plan prevention, inspection, and evidence collection.
          3. Execute the approved tests and record pilot results.
          4. Confirm quality criteria and mandatory seal standards.
          Answer: D

          ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.

        95. 2.9 Reconciled project reporting

          A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Verified evidence in the review file: reconciled data from the authoritative project records. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Evidence not yet verified: an accessible version-controlled report for decision makers. Verified evidence in the review file: an interpretation of progress, variance, and forecast implications. Which action should the project manager take next based on this evidence?

          1. Publish the reviewed report with access and version controls.
          2. Agree metric definitions and the reporting cutoff.
          3. Reconcile the report data against authoritative records.
          4. Analyze reconciled progress and explain forecast implications.
          Answer: B

          ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.

        96. 2.4 Capacity and resource commitments

          Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: the required skills and estimated effort for each test. Evidence not yet verified: confirmed technician and laboratory availability. Evidence not yet verified: an agreed allocation that respects authorized capacity. Verified evidence in the review file: a utilization check against the agreed allocation. Which action should the project manager take next based on this evidence?

          1. Define test resource requirements and estimate the effort.
          2. Negotiate a feasible allocation with both project owners.
          3. Monitor utilization and address new resource conflicts.
          4. Confirm calendars and competing resource commitments.
          Answer: D

          ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: confirmed technician and laboratory availability. A resource plan can't assume availability across competing projects.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.

        97. 2.6 Financial forecasting and control

          A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an estimate of costs and identified financial risks. Verified evidence in the review file: a governance review of the forecast and funding variance. Evidence not yet verified: reconciled actual spending and remaining cost estimates. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Which action should the project manager take next based on this evidence?

          1. Estimate costs and identify relevant financial uncertainty.
          2. Reconcile actual costs and estimate the remaining work.
          3. Report the forecast and seek required funding decisions.
          4. Obtain baseline approval and justify contingency reserves.
          Answer: D

          ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Contingency addresses identified risk and needs authorization under the funding rules.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.

        98. 2.8 Schedule dependencies and baselines

          A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Evidence not yet verified: an approved schedule baseline coordinated with operations. Verified evidence in the review file: an analysis of actual progress and schedule variation. Verified evidence in the review file: validated activity dependencies and external operating constraints. Evidence not yet verified: duration estimates and resource calendars. Which action should the project manager take next based on this evidence?

          1. Validate dependencies and the permitted shutdown window.
          2. Coordinate dates with operations and approve the baseline.
          3. Compare actual progress with the baseline and assess impact.
          4. Estimate durations using team input and resource calendars.
          Answer: D

          ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: duration estimates and resource calendars. Dependency order alone doesn't establish feasible dates without durations and availability.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.

        99. 2.10 Acceptance and operational transition

          A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release. Evidence not yet verified: operations readiness and an accepted support handover. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Confirm the contractual and project closure criteria.
          2. Validate operations readiness and complete the support handover.
          3. Complete financial closure, archive lessons, and release resources.
          4. Obtain acceptance evidence from the authorized stakeholders.
          Answer: D

          ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Completion claims need authorized acceptance against the agreed criteria.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.

        100. 2.1 Integrated delivery planning

          A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Evidence not yet verified: an agreed hybrid approach for installation and iterative software. Verified evidence in the review file: an integrated dependency, resource, and delivery plan. Evidence not yet verified: a review of plan gaps and continuing business value. Verified evidence in the review file: an assessment of requirement stability and delivery constraints. Which action should the project manager take next based on this evidence?

          1. Agree a hybrid approach with explicit integration points.
          2. Integrate dependencies, resources, and delivery milestones.
          3. Review the integrated plan for gaps and continued value.
          4. Assess uncertainty, constraints, and required delivery outcomes.
          Answer: A

          ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an agreed hybrid approach for installation and iterative software. Stable installation milestones and evolving software can use different approaches within one plan.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.

        101. 2.2 Release boundaries and work breakdown

          A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Evidence not yet verified: an agreed release boundary and explicit exclusions. Verified evidence in the review file: documented requirements and acceptance criteria. Evidence not yet verified: a completeness review of the scope breakdown. Verified evidence in the review file: a breakdown into assignable work with traceability. Which action should the project manager take next based on this evidence?

          1. Break the agreed scope into traceable work packages.
          2. Check the breakdown for omissions and unauthorized additions.
          3. Elicit requirements and define testable acceptance criteria.
          4. Agree included services and exclusions with stakeholders.
          Answer: D

          ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: an agreed release boundary and explicit exclusions. A requirement list alone doesn't settle competing release expectations.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.

        102. 2.3 Incremental benefit realization

          A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Verified evidence in the review file: a measurable benefit agreed with the business owner. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Verified evidence in the review file: an agreed usable increment and release test. Evidence not yet verified: benefit measurement after customers use the increment. Which action should the project manager take next based on this evidence?

          1. Rank delivery options by benefit, feedback, and dependencies.
          2. Plan a usable increment that tests the prioritized benefit.
          3. Measure realized benefit and use it to reprioritize work.
          4. Agree the benefit metric and its accountable business owner.
          Answer: A

          ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Early delivery helps only when the selected increment can produce the intended value.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.

        103. 2.5 Supplier selection and acceptance

          A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Verified evidence in the review file: evaluation criteria and an appropriate allocation of contract risk. Evidence not yet verified: verified supplier performance and acceptance evidence. Verified evidence in the review file: an authorized contract with measurable acceptance terms. Evidence not yet verified: a documented supplier evaluation under the agreed criteria. Which action should the project manager take next based on this evidence?

          1. Evaluate bids using the published procurement criteria.
          2. Negotiate and authorize the contract’s acceptance obligations.
          3. Compare supplier evidence with the contractual acceptance terms.
          4. Define evaluation criteria and select suitable contract terms.
          Answer: A

          ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: a documented supplier evaluation under the agreed criteria. Supplier evaluation must apply the agreed criteria instead of favoring a familiar bidder.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.

        104. 2.7 Quality evidence and improvement

          A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Verified evidence in the review file: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Verified evidence in the review file: testable quality requirements and applicable standards. Evidence not yet verified: a quality plan with preventive controls and test methods. Which action should the project manager take next based on this evidence?

          1. Analyze defects, improve the process, and verify the result.
          2. Confirm quality criteria and mandatory seal standards.
          3. Execute the approved tests and record pilot results.
          4. Plan prevention, inspection, and evidence collection.
          Answer: D

          ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: a quality plan with preventive controls and test methods. Quality planning defines how conformity will be achieved and demonstrated.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.

        105. 2.9 Reconciled project reporting

          A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: an accessible version-controlled report for decision makers. Verified evidence in the review file: an interpretation of progress, variance, and forecast implications. Evidence not yet verified: reconciled data from the authoritative project records. Verified evidence in the review file: metric definitions, data owners, and a common reporting date. Which action should the project manager take next based on this evidence?

          1. Publish the reviewed report with access and version controls.
          2. Agree metric definitions and the reporting cutoff.
          3. Analyze reconciled progress and explain forecast implications.
          4. Reconcile the report data against authoritative records.
          Answer: D

          ECO task 2.9: Reconciled project reporting. Evidence not yet verified: reconciled data from the authoritative project records. Analysis based on unreconciled data can create false variances and misleading conclusions.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.

        106. 2.4 Capacity and resource commitments

          Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: confirmed technician and laboratory availability. Evidence not yet verified: an agreed allocation that respects authorized capacity. Evidence not yet verified: a utilization check against the agreed allocation. Verified evidence in the review file: the required skills and estimated effort for each test. Which action should the project manager take next based on this evidence?

          1. Negotiate a feasible allocation with both project owners.
          2. Monitor utilization and address new resource conflicts.
          3. Define test resource requirements and estimate the effort.
          4. Confirm calendars and competing resource commitments.
          Answer: A

          ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: an agreed allocation that respects authorized capacity. Negotiation resolves competing commitments without silently assuming overtime.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.

        107. 2.6 Financial forecasting and control

          A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an authorized baseline and risk-based contingency allocation. Verified evidence in the review file: an estimate of costs and identified financial risks. Evidence not yet verified: a governance review of the forecast and funding variance. Evidence not yet verified: reconciled actual spending and remaining cost estimates. Which action should the project manager take next based on this evidence?

          1. Report the forecast and seek required funding decisions.
          2. Estimate costs and identify relevant financial uncertainty.
          3. Reconcile actual costs and estimate the remaining work.
          4. Obtain baseline approval and justify contingency reserves.
          Answer: C

          ECO task 2.6: Financial forecasting and control. Evidence not yet verified: reconciled actual spending and remaining cost estimates. A forecast needs current actuals and a remaining-work estimate, not the original budget alone.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.

        108. 2.8 Schedule dependencies and baselines

          A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Verified evidence in the review file: validated activity dependencies and external operating constraints. Verified evidence in the review file: duration estimates and resource calendars. Evidence not yet verified: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Which action should the project manager take next based on this evidence?

          1. Validate dependencies and the permitted shutdown window.
          2. Estimate durations using team input and resource calendars.
          3. Coordinate dates with operations and approve the baseline.
          4. Compare actual progress with the baseline and assess impact.
          Answer: C

          ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: an approved schedule baseline coordinated with operations. A baseline provides an authorized reference for monitoring schedule variance.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.

        109. 2.10 Acceptance and operational transition

          A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria. Evidence not yet verified: closed contracts, archived lessons, and authorized resource release. Evidence not yet verified: operations readiness and an accepted support handover. Verified evidence in the review file: formal stakeholder acceptance of completed deliverables. Which action should the project manager take next based on this evidence?

          1. Confirm the contractual and project closure criteria.
          2. Obtain acceptance evidence from the authorized stakeholders.
          3. Validate operations readiness and complete the support handover.
          4. Complete financial closure, archive lessons, and release resources.
          Answer: C

          ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: operations readiness and an accepted support handover. Acceptance of the product doesn't by itself establish operational readiness.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.

        110. 2.1 Integrated delivery planning

          A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Evidence not yet verified: an integrated dependency, resource, and delivery plan. Verified evidence in the review file: a review of plan gaps and continuing business value. Evidence not yet verified: an assessment of requirement stability and delivery constraints. Evidence not yet verified: an agreed hybrid approach for installation and iterative software. Which action should the project manager take next based on this evidence?

          1. Agree a hybrid approach with explicit integration points.
          2. Assess uncertainty, constraints, and required delivery outcomes.
          3. Integrate dependencies, resources, and delivery milestones.
          4. Review the integrated plan for gaps and continued value.
          Answer: B

          ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.

        111. 2.2 Release boundaries and work breakdown

          A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Verified evidence in the review file: a completeness review of the scope breakdown. Evidence not yet verified: a breakdown into assignable work with traceability. Evidence not yet verified: an agreed release boundary and explicit exclusions. Evidence not yet verified: documented requirements and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Elicit requirements and define testable acceptance criteria.
          2. Agree included services and exclusions with stakeholders.
          3. Break the agreed scope into traceable work packages.
          4. Check the breakdown for omissions and unauthorized additions.
          Answer: A

          ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.

        112. 2.3 Incremental benefit realization

          A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Evidence not yet verified: an agreed usable increment and release test. Verified evidence in the review file: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Which action should the project manager take next based on this evidence?

          1. Agree the benefit metric and its accountable business owner.
          2. Plan a usable increment that tests the prioritized benefit.
          3. Measure realized benefit and use it to reprioritize work.
          4. Rank delivery options by benefit, feedback, and dependencies.
          Answer: A

          ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.

        113. 2.5 Supplier selection and acceptance

          A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Evidence not yet verified: a documented supplier evaluation under the agreed criteria. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Verified evidence in the review file: verified supplier performance and acceptance evidence. Evidence not yet verified: an authorized contract with measurable acceptance terms. Which action should the project manager take next based on this evidence?

          1. Negotiate and authorize the contract’s acceptance obligations.
          2. Define evaluation criteria and select suitable contract terms.
          3. Compare supplier evidence with the contractual acceptance terms.
          4. Evaluate bids using the published procurement criteria.
          Answer: B

          ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.

        114. 2.7 Quality evidence and improvement

          A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Evidence not yet verified: testable quality requirements and applicable standards. Evidence not yet verified: a quality plan with preventive controls and test methods. Evidence not yet verified: pilot measurements collected using the approved test method. Verified evidence in the review file: an evidence-based improvement and effectiveness review. Which action should the project manager take next based on this evidence?

          1. Execute the approved tests and record pilot results.
          2. Analyze defects, improve the process, and verify the result.
          3. Plan prevention, inspection, and evidence collection.
          4. Confirm quality criteria and mandatory seal standards.
          Answer: D

          ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.

        115. 2.9 Reconciled project reporting

          A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Verified evidence in the review file: an accessible version-controlled report for decision makers. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Evidence not yet verified: reconciled data from the authoritative project records. Which action should the project manager take next based on this evidence?

          1. Agree metric definitions and the reporting cutoff.
          2. Analyze reconciled progress and explain forecast implications.
          3. Publish the reviewed report with access and version controls.
          4. Reconcile the report data against authoritative records.
          Answer: A

          ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.

        116. 2.4 Capacity and resource commitments

          Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: an agreed allocation that respects authorized capacity. Evidence not yet verified: a utilization check against the agreed allocation. Evidence not yet verified: the required skills and estimated effort for each test. Evidence not yet verified: confirmed technician and laboratory availability. Which action should the project manager take next based on this evidence?

          1. Monitor utilization and address new resource conflicts.
          2. Confirm calendars and competing resource commitments.
          3. Negotiate a feasible allocation with both project owners.
          4. Define test resource requirements and estimate the effort.
          Answer: D

          ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: the required skills and estimated effort for each test. Allocation needs the required capabilities and workload, not only headcount.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.

        117. 2.6 Financial forecasting and control

          A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Evidence not yet verified: a governance review of the forecast and funding variance. Verified evidence in the review file: reconciled actual spending and remaining cost estimates. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Evidence not yet verified: an estimate of costs and identified financial risks. Which action should the project manager take next based on this evidence?

          1. Report the forecast and seek required funding decisions.
          2. Estimate costs and identify relevant financial uncertainty.
          3. Obtain baseline approval and justify contingency reserves.
          4. Reconcile actual costs and estimate the remaining work.
          Answer: B

          ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an estimate of costs and identified financial risks. Reserves and forecasts require a cost estimate and identified uncertainties.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.

        118. 2.8 Schedule dependencies and baselines

          A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Evidence not yet verified: duration estimates and resource calendars. Verified evidence in the review file: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Evidence not yet verified: validated activity dependencies and external operating constraints. Which action should the project manager take next based on this evidence?

          1. Compare actual progress with the baseline and assess impact.
          2. Validate dependencies and the permitted shutdown window.
          3. Estimate durations using team input and resource calendars.
          4. Coordinate dates with operations and approve the baseline.
          Answer: B

          ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: validated activity dependencies and external operating constraints. The schedule logic must respect prerequisites and external constraints.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.

        119. 2.10 Acceptance and operational transition

          A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Evidence not yet verified: closed contracts, archived lessons, and authorized resource release. Verified evidence in the review file: operations readiness and an accepted support handover. Which action should the project manager take next based on this evidence?

          1. Confirm the contractual and project closure criteria.
          2. Complete financial closure, archive lessons, and release resources.
          3. Obtain acceptance evidence from the authorized stakeholders.
          4. Validate operations readiness and complete the support handover.
          Answer: A

          ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Closure requires known criteria instead of assuming that the planned end date is enough.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.

        120. 2.1 Integrated delivery planning

          A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Evidence not yet verified: an assessment of requirement stability and delivery constraints. Verified evidence in the review file: an agreed hybrid approach for installation and iterative software. Evidence not yet verified: an integrated dependency, resource, and delivery plan. Evidence not yet verified: a review of plan gaps and continuing business value. Which action should the project manager take next based on this evidence?

          1. Agree a hybrid approach with explicit integration points.
          2. Integrate dependencies, resources, and delivery milestones.
          3. Assess uncertainty, constraints, and required delivery outcomes.
          4. Review the integrated plan for gaps and continued value.
          Answer: C

          ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.

        121. 2.2 Release boundaries and work breakdown

          A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Evidence not yet verified: documented requirements and acceptance criteria. Evidence not yet verified: a completeness review of the scope breakdown. Evidence not yet verified: a breakdown into assignable work with traceability. Verified evidence in the review file: an agreed release boundary and explicit exclusions. Which action should the project manager take next based on this evidence?

          1. Elicit requirements and define testable acceptance criteria.
          2. Agree included services and exclusions with stakeholders.
          3. Break the agreed scope into traceable work packages.
          4. Check the breakdown for omissions and unauthorized additions.
          Answer: A

          ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.

        122. 2.3 Incremental benefit realization

          A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Evidence not yet verified: an agreed usable increment and release test. Evidence not yet verified: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Verified evidence in the review file: a ranked comparison of delivery options and dependencies. Which action should the project manager take next based on this evidence?

          1. Rank delivery options by benefit, feedback, and dependencies.
          2. Plan a usable increment that tests the prioritized benefit.
          3. Agree the benefit metric and its accountable business owner.
          4. Measure realized benefit and use it to reprioritize work.
          Answer: C

          ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.

        123. 2.5 Supplier selection and acceptance

          A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Evidence not yet verified: verified supplier performance and acceptance evidence. Evidence not yet verified: an authorized contract with measurable acceptance terms. Verified evidence in the review file: a documented supplier evaluation under the agreed criteria. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Which action should the project manager take next based on this evidence?

          1. Evaluate bids using the published procurement criteria.
          2. Negotiate and authorize the contract’s acceptance obligations.
          3. Compare supplier evidence with the contractual acceptance terms.
          4. Define evaluation criteria and select suitable contract terms.
          Answer: D

          ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.

        124. 2.7 Quality evidence and improvement

          A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Verified evidence in the review file: a quality plan with preventive controls and test methods. Evidence not yet verified: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Evidence not yet verified: testable quality requirements and applicable standards. Which action should the project manager take next based on this evidence?

          1. Execute the approved tests and record pilot results.
          2. Analyze defects, improve the process, and verify the result.
          3. Confirm quality criteria and mandatory seal standards.
          4. Plan prevention, inspection, and evidence collection.
          Answer: C

          ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.

        125. 2.9 Reconciled project reporting

          A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Verified evidence in the review file: reconciled data from the authoritative project records. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Evidence not yet verified: an accessible version-controlled report for decision makers. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Which action should the project manager take next based on this evidence?

          1. Analyze reconciled progress and explain forecast implications.
          2. Publish the reviewed report with access and version controls.
          3. Agree metric definitions and the reporting cutoff.
          4. Reconcile the report data against authoritative records.
          Answer: C

          ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.

        126. 2.4 Capacity and resource commitments

          Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: the required skills and estimated effort for each test. Evidence not yet verified: confirmed technician and laboratory availability. Evidence not yet verified: an agreed allocation that respects authorized capacity. Evidence not yet verified: a utilization check against the agreed allocation. Which action should the project manager take next based on this evidence?

          1. Negotiate a feasible allocation with both project owners.
          2. Confirm calendars and competing resource commitments.
          3. Monitor utilization and address new resource conflicts.
          4. Define test resource requirements and estimate the effort.
          Answer: B

          ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: confirmed technician and laboratory availability. A resource plan can't assume availability across competing projects.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.

        127. 2.6 Financial forecasting and control

          A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an estimate of costs and identified financial risks. Evidence not yet verified: a governance review of the forecast and funding variance. Evidence not yet verified: reconciled actual spending and remaining cost estimates. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Which action should the project manager take next based on this evidence?

          1. Obtain baseline approval and justify contingency reserves.
          2. Reconcile actual costs and estimate the remaining work.
          3. Report the forecast and seek required funding decisions.
          4. Estimate costs and identify relevant financial uncertainty.
          Answer: A

          ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Contingency addresses identified risk and needs authorization under the funding rules.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.

        128. 2.8 Schedule dependencies and baselines

          A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Evidence not yet verified: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Verified evidence in the review file: validated activity dependencies and external operating constraints. Evidence not yet verified: duration estimates and resource calendars. Which action should the project manager take next based on this evidence?

          1. Compare actual progress with the baseline and assess impact.
          2. Estimate durations using team input and resource calendars.
          3. Validate dependencies and the permitted shutdown window.
          4. Coordinate dates with operations and approve the baseline.
          Answer: B

          ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: duration estimates and resource calendars. Dependency order alone doesn't establish feasible dates without durations and availability.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.

        129. 2.10 Acceptance and operational transition

          A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Evidence not yet verified: closed contracts, archived lessons, and authorized resource release. Evidence not yet verified: operations readiness and an accepted support handover. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Complete financial closure, archive lessons, and release resources.
          2. Confirm the contractual and project closure criteria.
          3. Obtain acceptance evidence from the authorized stakeholders.
          4. Validate operations readiness and complete the support handover.
          Answer: C

          ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Completion claims need authorized acceptance against the agreed criteria.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.

        130. 2.3 Incremental benefit realization

          A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Evidence not yet verified: an agreed usable increment and release test. Evidence not yet verified: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Which action should the project manager take next based on this evidence?

          1. Measure realized benefit and use it to reprioritize work.
          2. Rank delivery options by benefit, feedback, and dependencies.
          3. Plan a usable increment that tests the prioritized benefit.
          4. Agree the benefit metric and its accountable business owner.
          Answer: D

          ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.

        131. 2.5 Supplier selection and acceptance

          A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Evidence not yet verified: a documented supplier evaluation under the agreed criteria. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Evidence not yet verified: verified supplier performance and acceptance evidence. Evidence not yet verified: an authorized contract with measurable acceptance terms. Which action should the project manager take next based on this evidence?

          1. Compare supplier evidence with the contractual acceptance terms.
          2. Evaluate bids using the published procurement criteria.
          3. Negotiate and authorize the contract’s acceptance obligations.
          4. Define evaluation criteria and select suitable contract terms.
          Answer: D

          ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.

        132. 2.7 Quality evidence and improvement

          A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Evidence not yet verified: testable quality requirements and applicable standards. Evidence not yet verified: a quality plan with preventive controls and test methods. Evidence not yet verified: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Which action should the project manager take next based on this evidence?

          1. Plan prevention, inspection, and evidence collection.
          2. Execute the approved tests and record pilot results.
          3. Confirm quality criteria and mandatory seal standards.
          4. Analyze defects, improve the process, and verify the result.
          Answer: C

          ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.

        133. 2.9 Reconciled project reporting

          A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Evidence not yet verified: an accessible version-controlled report for decision makers. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Evidence not yet verified: reconciled data from the authoritative project records. Which action should the project manager take next based on this evidence?

          1. Reconcile the report data against authoritative records.
          2. Agree metric definitions and the reporting cutoff.
          3. Analyze reconciled progress and explain forecast implications.
          4. Publish the reviewed report with access and version controls.
          Answer: B

          ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.

        134. 3.1 Decision authority and oversight

          A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Verified evidence in the review file: approved success measures and governance reporting arrangements. Verified evidence in the review file: a check that teams follow the approved authority model. Which action should the project manager take next based on this evidence?

          1. Agree decision rights, escalation paths, and thresholds.
          2. Review each partner’s mandatory governance requirements.
          3. Approve success measures and the governance reporting cycle.
          4. Check decision records against the approved authority model.
          Answer: B

          ECO task 3.1: Decision authority and oversight. Evidence not yet verified: the applicable organizational policies and authority constraints. Project rules must respect existing authority, ethics, and mandatory policies.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.

        135. 3.3 Authorized change execution

          A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Evidence not yet verified: a recorded change request with a clear business rationale. Verified evidence in the review file: implementation records and updated baselines for the approved change. Verified evidence in the review file: a documented decision by the authorized change authority. Verified evidence in the review file: an integrated impact analysis of the requested feature. Which action should the project manager take next based on this evidence?

          1. Assess scope, cost, schedule, risk, and benefit impacts.
          2. Submit the analysis to the authorized change authority.
          3. Record the request, its rationale, and requested outcome.
          4. Implement the approved change and update controlled documents.
          Answer: C

          ECO task 3.3: Authorized change execution. Evidence not yet verified: a recorded change request with a clear business rationale. A controlled change needs a traceable request before analysis and decision.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.

        136. 3.4 Resolving realized blockers

          A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Verified evidence in the review file: an authorized workaround or corrective intervention. Verified evidence in the review file: a retest proving that testing can resume safely. Evidence not yet verified: a current issue record and confirmed impact. Verified evidence in the review file: an agreed priority, resolution owner, and escalation path. Which action should the project manager take next based on this evidence?

          1. Record the realized issue and assess its current impact.
          2. Assign an issue owner and prioritize the required intervention.
          3. Coordinate and apply the authorized corrective intervention.
          4. Retest the blocked workflow before closing the issue.
          Answer: A

          ECO task 3.4: Resolving realized blockers. Evidence not yet verified: a current issue record and confirmed impact. An event that has occurred requires issue management, even if it began as a risk.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.

        137. 3.5 Uncertainty and response monitoring

          A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Verified evidence in the review file: a monitoring check of triggers and residual exposure. Verified evidence in the review file: an approved response, trigger, and contingency owner. Verified evidence in the review file: an assessed probability, impact, and risk priority. Evidence not yet verified: a cause-event-effect risk statement and an owner. Which action should the project manager take next based on this evidence?

          1. Analyze probability and impact against the agreed risk criteria.
          2. Agree the risk response, trigger, and contingency responsibility.
          3. Record the uncertain event, causes, effects, and risk owner.
          4. Monitor triggers, residual risk, and response effectiveness.
          Answer: C

          ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: a cause-event-effect risk statement and an owner. A useful risk record distinguishes uncertainty from an issue that has already occurred.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.

        138. 3.6 Testing and reusing improvements

          A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: a small improvement experiment and an outcome measure. Verified evidence in the review file: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Which action should the project manager take next based on this evidence?

          1. Run the experiment and compare outcomes with the baseline.
          2. Update the standard process and publish the validated lesson.
          3. Design a limited experiment with a measurable outcome.
          4. Analyze rework evidence and identify the root cause.
          Answer: D

          ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.

        139. 3.7 Readiness and organizational adoption

          A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: a role-impact assessment and agreed transition support. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Verified evidence in the review file: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Which action should the project manager take next based on this evidence?

          1. Run a supported pilot before the wider transition.
          2. Measure adoption and adjust support using user feedback.
          3. Map role impacts and agree training and transition support.
          4. Assess culture and discuss concerns with affected departments.
          Answer: D

          ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Resistance can reflect real impacts that need understanding before a transition is planned.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.

        140. 3.8 Responding to external change

          A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Verified evidence in the review file: an assessment of impacts on value, scope, and delivery. Verified evidence in the review file: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Which action should the project manager take next based on this evidence?

          1. Obtain the required decision and update the delivery plan.
          2. Verify the external change with authoritative sources.
          3. Assign ongoing monitoring and review further impacts.
          4. Assess and prioritize the change’s project impacts.
          Answer: B

          ECO task 3.8: Responding to external change. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Unverified announcements can't provide a reliable basis for changing project commitments.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.

        141. 3.2 Obligations and conformity evidence

          A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Verified evidence in the review file: a register of applicable legal and contractual obligations. Verified evidence in the review file: evidence that implemented controls satisfy the obligations. Verified evidence in the review file: assigned compliance controls and required approvals. Evidence not yet verified: a gap assessment and consequences of noncompliance. Which action should the project manager take next based on this evidence?

          1. Assess current gaps, threats, and consequences of noncompliance.
          2. Assign controls, owners, and required approval checkpoints.
          3. Verify compliance evidence before authorizing the release.
          4. Confirm and classify the applicable compliance obligations.
          Answer: A

          ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: a gap assessment and consequences of noncompliance. Controls should respond to assessed compliance gaps rather than assumed coverage.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.

        142. 3.1 Decision authority and oversight

          A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: approved success measures and governance reporting arrangements. Verified evidence in the review file: a check that teams follow the approved authority model. Verified evidence in the review file: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Which action should the project manager take next based on this evidence?

          1. Check decision records against the approved authority model.
          2. Review each partner’s mandatory governance requirements.
          3. Agree decision rights, escalation paths, and thresholds.
          4. Approve success measures and the governance reporting cycle.
          Answer: D

          ECO task 3.1: Decision authority and oversight. Evidence not yet verified: approved success measures and governance reporting arrangements. Governance needs a defined basis for judging outcomes and receiving decisions.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.

        143. 3.3 Authorized change execution

          A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Verified evidence in the review file: implementation records and updated baselines for the approved change. Evidence not yet verified: a documented decision by the authorized change authority. Verified evidence in the review file: an integrated impact analysis of the requested feature. Verified evidence in the review file: a recorded change request with a clear business rationale. Which action should the project manager take next based on this evidence?

          1. Submit the analysis to the authorized change authority.
          2. Implement the approved change and update controlled documents.
          3. Record the request, its rationale, and requested outcome.
          4. Assess scope, cost, schedule, risk, and benefit impacts.
          Answer: A

          ECO task 3.3: Authorized change execution. Evidence not yet verified: a documented decision by the authorized change authority. A customer request or favorable analysis doesn't replace the required approval.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.

        144. 3.4 Resolving realized blockers

          A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Verified evidence in the review file: an agreed priority, resolution owner, and escalation path. Evidence not yet verified: an authorized workaround or corrective intervention. Verified evidence in the review file: a retest proving that testing can resume safely. Verified evidence in the review file: a current issue record and confirmed impact. Which action should the project manager take next based on this evidence?

          1. Retest the blocked workflow before closing the issue.
          2. Record the realized issue and assess its current impact.
          3. Coordinate and apply the authorized corrective intervention.
          4. Assign an issue owner and prioritize the required intervention.
          Answer: C

          ECO task 3.4: Resolving realized blockers. Evidence not yet verified: an authorized workaround or corrective intervention. The assigned owner needs an implemented intervention rather than only an issue entry.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.

        145. 3.5 Uncertainty and response monitoring

          A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Verified evidence in the review file: an assessed probability, impact, and risk priority. Verified evidence in the review file: a cause-event-effect risk statement and an owner. Verified evidence in the review file: a monitoring check of triggers and residual exposure. Evidence not yet verified: an approved response, trigger, and contingency owner. Which action should the project manager take next based on this evidence?

          1. Monitor triggers, residual risk, and response effectiveness.
          2. Record the uncertain event, causes, effects, and risk owner.
          3. Analyze probability and impact against the agreed risk criteria.
          4. Agree the risk response, trigger, and contingency responsibility.
          Answer: D

          ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: an approved response, trigger, and contingency owner. A response needs an owner and an activation condition to be executable.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.

        146. 3.6 Testing and reusing improvements

          A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: evidence of the recurring defect and its root cause. Verified evidence in the review file: a small improvement experiment and an outcome measure. Evidence not yet verified: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Which action should the project manager take next based on this evidence?

          1. Run the experiment and compare outcomes with the baseline.
          2. Analyze rework evidence and identify the root cause.
          3. Design a limited experiment with a measurable outcome.
          4. Update the standard process and publish the validated lesson.
          Answer: A

          ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: results from the improvement experiment. An attractive proposal still needs observed results before it becomes a standard.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.

        147. 3.7 Readiness and organizational adoption

          A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: an assessment of culture, concerns, and change readiness. Verified evidence in the review file: adoption evidence and adjustments to transition support. Evidence not yet verified: a supported pilot with trained users and escalation access. Verified evidence in the review file: a role-impact assessment and agreed transition support. Which action should the project manager take next based on this evidence?

          1. Run a supported pilot before the wider transition.
          2. Assess culture and discuss concerns with affected departments.
          3. Map role impacts and agree training and transition support.
          4. Measure adoption and adjust support using user feedback.
          Answer: A

          ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: a supported pilot with trained users and escalation access. A supported pilot exposes adoption problems while the rollout remains limited.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.

        148. 3.8 Responding to external change

          A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Evidence not yet verified: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Verified evidence in the review file: verified details, applicability, and the effective date of the rule. Verified evidence in the review file: an assessment of impacts on value, scope, and delivery. Which action should the project manager take next based on this evidence?

          1. Verify the external change with authoritative sources.
          2. Assess and prioritize the change’s project impacts.
          3. Obtain the required decision and update the delivery plan.
          4. Assign ongoing monitoring and review further impacts.
          Answer: C

          ECO task 3.8: Responding to external change. Evidence not yet verified: an authorized response and updated scope or backlog. External pressure doesn't remove internal authorization and planning obligations.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.

        149. 3.2 Obligations and conformity evidence

          A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Verified evidence in the review file: assigned compliance controls and required approvals. Verified evidence in the review file: a gap assessment and consequences of noncompliance. Verified evidence in the review file: a register of applicable legal and contractual obligations. Which action should the project manager take next based on this evidence?

          1. Verify compliance evidence before authorizing the release.
          2. Confirm and classify the applicable compliance obligations.
          3. Assess current gaps, threats, and consequences of noncompliance.
          4. Assign controls, owners, and required approval checkpoints.
          Answer: A

          ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Having a control plan is different from demonstrating that the obligations are satisfied.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.

        150. 3.1 Decision authority and oversight

          A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: agreed decision rights and escalation thresholds. Verified evidence in the review file: approved success measures and governance reporting arrangements. Verified evidence in the review file: a check that teams follow the approved authority model. Evidence not yet verified: the applicable organizational policies and authority constraints. Which action should the project manager take next based on this evidence?

          1. Approve success measures and the governance reporting cycle.
          2. Check decision records against the approved authority model.
          3. Agree decision rights, escalation paths, and thresholds.
          4. Review each partner’s mandatory governance requirements.
          Answer: D

          ECO task 3.1: Decision authority and oversight. Evidence not yet verified: the applicable organizational policies and authority constraints. Project rules must respect existing authority, ethics, and mandatory policies.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.

        151. 3.3 Authorized change execution

          A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Evidence not yet verified: an integrated impact analysis of the requested feature. Evidence not yet verified: a recorded change request with a clear business rationale. Verified evidence in the review file: implementation records and updated baselines for the approved change. Verified evidence in the review file: a documented decision by the authorized change authority. Which action should the project manager take next based on this evidence?

          1. Submit the analysis to the authorized change authority.
          2. Implement the approved change and update controlled documents.
          3. Assess scope, cost, schedule, risk, and benefit impacts.
          4. Record the request, its rationale, and requested outcome.
          Answer: D

          ECO task 3.3: Authorized change execution. Evidence not yet verified: a recorded change request with a clear business rationale. A controlled change needs a traceable request before analysis and decision.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.

        152. 3.4 Resolving realized blockers

          A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Evidence not yet verified: a current issue record and confirmed impact. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Verified evidence in the review file: an authorized workaround or corrective intervention. Verified evidence in the review file: a retest proving that testing can resume safely. Which action should the project manager take next based on this evidence?

          1. Record the realized issue and assess its current impact.
          2. Coordinate and apply the authorized corrective intervention.
          3. Retest the blocked workflow before closing the issue.
          4. Assign an issue owner and prioritize the required intervention.
          Answer: A

          ECO task 3.4: Resolving realized blockers. Evidence not yet verified: a current issue record and confirmed impact. An event that has occurred requires issue management, even if it began as a risk.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.

        153. 3.5 Uncertainty and response monitoring

          A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Evidence not yet verified: a cause-event-effect risk statement and an owner. Verified evidence in the review file: a monitoring check of triggers and residual exposure. Verified evidence in the review file: an approved response, trigger, and contingency owner. Evidence not yet verified: an assessed probability, impact, and risk priority. Which action should the project manager take next based on this evidence?

          1. Agree the risk response, trigger, and contingency responsibility.
          2. Monitor triggers, residual risk, and response effectiveness.
          3. Analyze probability and impact against the agreed risk criteria.
          4. Record the uncertain event, causes, effects, and risk owner.
          Answer: D

          ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: a cause-event-effect risk statement and an owner. A useful risk record distinguishes uncertainty from an issue that has already occurred.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.

        154. 3.6 Testing and reusing improvements

          A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Evidence not yet verified: a small improvement experiment and an outcome measure. Which action should the project manager take next based on this evidence?

          1. Update the standard process and publish the validated lesson.
          2. Design a limited experiment with a measurable outcome.
          3. Analyze rework evidence and identify the root cause.
          4. Run the experiment and compare outcomes with the baseline.
          Answer: C

          ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.

        155. 3.7 Readiness and organizational adoption

          A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Evidence not yet verified: a role-impact assessment and agreed transition support. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Which action should the project manager take next based on this evidence?

          1. Assess culture and discuss concerns with affected departments.
          2. Measure adoption and adjust support using user feedback.
          3. Map role impacts and agree training and transition support.
          4. Run a supported pilot before the wider transition.
          Answer: A

          ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Resistance can reflect real impacts that need understanding before a transition is planned.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.

        156. 3.8 Responding to external change

          A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Evidence not yet verified: an assessment of impacts on value, scope, and delivery. Verified evidence in the review file: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Which action should the project manager take next based on this evidence?

          1. Assign ongoing monitoring and review further impacts.
          2. Verify the external change with authoritative sources.
          3. Assess and prioritize the change’s project impacts.
          4. Obtain the required decision and update the delivery plan.
          Answer: B

          ECO task 3.8: Responding to external change. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Unverified announcements can't provide a reliable basis for changing project commitments.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.

        157. 3.2 Obligations and conformity evidence

          A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Verified evidence in the review file: a gap assessment and consequences of noncompliance. Evidence not yet verified: a register of applicable legal and contractual obligations. Verified evidence in the review file: evidence that implemented controls satisfy the obligations. Evidence not yet verified: assigned compliance controls and required approvals. Which action should the project manager take next based on this evidence?

          1. Verify compliance evidence before authorizing the release.
          2. Confirm and classify the applicable compliance obligations.
          3. Assess current gaps, threats, and consequences of noncompliance.
          4. Assign controls, owners, and required approval checkpoints.
          Answer: B

          ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: a register of applicable legal and contractual obligations. Compliance planning begins with the requirements that apply to the project.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.

        158. 3.1 Decision authority and oversight

          A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Verified evidence in the review file: approved success measures and governance reporting arrangements. Evidence not yet verified: a check that teams follow the approved authority model. Which action should the project manager take next based on this evidence?

          1. Agree decision rights, escalation paths, and thresholds.
          2. Approve success measures and the governance reporting cycle.
          3. Review each partner’s mandatory governance requirements.
          4. Check decision records against the approved authority model.
          Answer: C

          ECO task 3.1: Decision authority and oversight. Evidence not yet verified: the applicable organizational policies and authority constraints. Project rules must respect existing authority, ethics, and mandatory policies.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.

        159. 3.3 Authorized change execution

          A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Evidence not yet verified: a recorded change request with a clear business rationale. Evidence not yet verified: implementation records and updated baselines for the approved change. Verified evidence in the review file: a documented decision by the authorized change authority. Verified evidence in the review file: an integrated impact analysis of the requested feature. Which action should the project manager take next based on this evidence?

          1. Record the request, its rationale, and requested outcome.
          2. Assess scope, cost, schedule, risk, and benefit impacts.
          3. Submit the analysis to the authorized change authority.
          4. Implement the approved change and update controlled documents.
          Answer: A

          ECO task 3.3: Authorized change execution. Evidence not yet verified: a recorded change request with a clear business rationale. A controlled change needs a traceable request before analysis and decision.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.

        160. 3.4 Resolving realized blockers

          A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Verified evidence in the review file: an authorized workaround or corrective intervention. Evidence not yet verified: a retest proving that testing can resume safely. Evidence not yet verified: a current issue record and confirmed impact. Verified evidence in the review file: an agreed priority, resolution owner, and escalation path. Which action should the project manager take next based on this evidence?

          1. Record the realized issue and assess its current impact.
          2. Assign an issue owner and prioritize the required intervention.
          3. Coordinate and apply the authorized corrective intervention.
          4. Retest the blocked workflow before closing the issue.
          Answer: A

          ECO task 3.4: Resolving realized blockers. Evidence not yet verified: a current issue record and confirmed impact. An event that has occurred requires issue management, even if it began as a risk.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.

        161. 3.5 Uncertainty and response monitoring

          A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Evidence not yet verified: a monitoring check of triggers and residual exposure. Verified evidence in the review file: an approved response, trigger, and contingency owner. Verified evidence in the review file: an assessed probability, impact, and risk priority. Evidence not yet verified: a cause-event-effect risk statement and an owner. Which action should the project manager take next based on this evidence?

          1. Analyze probability and impact against the agreed risk criteria.
          2. Agree the risk response, trigger, and contingency responsibility.
          3. Record the uncertain event, causes, effects, and risk owner.
          4. Monitor triggers, residual risk, and response effectiveness.
          Answer: C

          ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: a cause-event-effect risk statement and an owner. A useful risk record distinguishes uncertainty from an issue that has already occurred.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.

        162. 3.6 Testing and reusing improvements

          A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: a small improvement experiment and an outcome measure. Verified evidence in the review file: results from the improvement experiment. Evidence not yet verified: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Which action should the project manager take next based on this evidence?

          1. Run the experiment and compare outcomes with the baseline.
          2. Update the standard process and publish the validated lesson.
          3. Design a limited experiment with a measurable outcome.
          4. Analyze rework evidence and identify the root cause.
          Answer: D

          ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.

        163. 3.7 Readiness and organizational adoption

          A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: a role-impact assessment and agreed transition support. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Evidence not yet verified: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Which action should the project manager take next based on this evidence?

          1. Run a supported pilot before the wider transition.
          2. Measure adoption and adjust support using user feedback.
          3. Map role impacts and agree training and transition support.
          4. Assess culture and discuss concerns with affected departments.
          Answer: D

          ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Resistance can reflect real impacts that need understanding before a transition is planned.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.

        164. 3.8 Responding to external change

          A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Verified evidence in the review file: an assessment of impacts on value, scope, and delivery. Verified evidence in the review file: an authorized response and updated scope or backlog. Evidence not yet verified: a continuing scan for further external changes. Which action should the project manager take next based on this evidence?

          1. Obtain the required decision and update the delivery plan.
          2. Assign ongoing monitoring and review further impacts.
          3. Verify the external change with authoritative sources.
          4. Assess and prioritize the change’s project impacts.
          Answer: C

          ECO task 3.8: Responding to external change. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Unverified announcements can't provide a reliable basis for changing project commitments.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.

        165. 3.2 Obligations and conformity evidence

          A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Verified evidence in the review file: a register of applicable legal and contractual obligations. Verified evidence in the review file: evidence that implemented controls satisfy the obligations. Evidence not yet verified: assigned compliance controls and required approvals. Evidence not yet verified: a gap assessment and consequences of noncompliance. Which action should the project manager take next based on this evidence?

          1. Assign controls, owners, and required approval checkpoints.
          2. Assess current gaps, threats, and consequences of noncompliance.
          3. Verify compliance evidence before authorizing the release.
          4. Confirm and classify the applicable compliance obligations.
          Answer: B

          ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: a gap assessment and consequences of noncompliance. Controls should respond to assessed compliance gaps rather than assumed coverage.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.

        166. 3.1 Decision authority and oversight

          A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Verified evidence in the review file: approved success measures and governance reporting arrangements. Evidence not yet verified: a check that teams follow the approved authority model. Verified evidence in the review file: the applicable organizational policies and authority constraints. Evidence not yet verified: agreed decision rights and escalation thresholds. Which action should the project manager take next based on this evidence?

          1. Agree decision rights, escalation paths, and thresholds.
          2. Check decision records against the approved authority model.
          3. Review each partner’s mandatory governance requirements.
          4. Approve success measures and the governance reporting cycle.
          Answer: A

          ECO task 3.1: Decision authority and oversight. Evidence not yet verified: agreed decision rights and escalation thresholds. Explicit thresholds prevent decisions being made by people without the required authority.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.

        167. 3.3 Authorized change execution

          A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Evidence not yet verified: implementation records and updated baselines for the approved change. Verified evidence in the review file: a documented decision by the authorized change authority. Evidence not yet verified: an integrated impact analysis of the requested feature. Verified evidence in the review file: a recorded change request with a clear business rationale. Which action should the project manager take next based on this evidence?

          1. Implement the approved change and update controlled documents.
          2. Record the request, its rationale, and requested outcome.
          3. Assess scope, cost, schedule, risk, and benefit impacts.
          4. Submit the analysis to the authorized change authority.
          Answer: C

          ECO task 3.3: Authorized change execution. Evidence not yet verified: an integrated impact analysis of the requested feature. Approval requires the combined effects of a change, not one favorable dimension.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.

        168. 3.4 Resolving realized blockers

          A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Verified evidence in the review file: an authorized workaround or corrective intervention. Evidence not yet verified: a retest proving that testing can resume safely. Verified evidence in the review file: a current issue record and confirmed impact. Which action should the project manager take next based on this evidence?

          1. Retest the blocked workflow before closing the issue.
          2. Record the realized issue and assess its current impact.
          3. Assign an issue owner and prioritize the required intervention.
          4. Coordinate and apply the authorized corrective intervention.
          Answer: C

          ECO task 3.4: Resolving realized blockers. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Impact determines urgency and the authority needed to remove the blocker.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.

        169. 3.5 Uncertainty and response monitoring

          A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Evidence not yet verified: an assessed probability, impact, and risk priority. Verified evidence in the review file: a cause-event-effect risk statement and an owner. Evidence not yet verified: a monitoring check of triggers and residual exposure. Verified evidence in the review file: an approved response, trigger, and contingency owner. Which action should the project manager take next based on this evidence?

          1. Monitor triggers, residual risk, and response effectiveness.
          2. Record the uncertain event, causes, effects, and risk owner.
          3. Analyze probability and impact against the agreed risk criteria.
          4. Agree the risk response, trigger, and contingency responsibility.
          Answer: C

          ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: an assessed probability, impact, and risk priority. The response should reflect assessed exposure instead of treating every risk equally.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.

        170. 3.6 Testing and reusing improvements

          A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: evidence of the recurring defect and its root cause. Evidence not yet verified: a small improvement experiment and an outcome measure. Verified evidence in the review file: results from the improvement experiment. Evidence not yet verified: updated organizational standards and reusable lessons. Which action should the project manager take next based on this evidence?

          1. Analyze rework evidence and identify the root cause.
          2. Run the experiment and compare outcomes with the baseline.
          3. Update the standard process and publish the validated lesson.
          4. Design a limited experiment with a measurable outcome.
          Answer: D

          ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: a small improvement experiment and an outcome measure. A controlled trial tests the proposed improvement before organization-wide adoption.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.

        171. 3.7 Readiness and organizational adoption

          A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: an assessment of culture, concerns, and change readiness. Evidence not yet verified: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Evidence not yet verified: a role-impact assessment and agreed transition support. Which action should the project manager take next based on this evidence?

          1. Map role impacts and agree training and transition support.
          2. Assess culture and discuss concerns with affected departments.
          3. Run a supported pilot before the wider transition.
          4. Measure adoption and adjust support using user feedback.
          Answer: A

          ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: a role-impact assessment and agreed transition support. Support must address changed work and responsibilities rather than only announcing the platform.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.

        172. 3.8 Responding to external change

          A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Verified evidence in the review file: an authorized response and updated scope or backlog. Evidence not yet verified: a continuing scan for further external changes. Verified evidence in the review file: verified details, applicability, and the effective date of the rule. Evidence not yet verified: an assessment of impacts on value, scope, and delivery. Which action should the project manager take next based on this evidence?

          1. Assess and prioritize the change’s project impacts.
          2. Verify the external change with authoritative sources.
          3. Obtain the required decision and update the delivery plan.
          4. Assign ongoing monitoring and review further impacts.
          Answer: A

          ECO task 3.8: Responding to external change. Evidence not yet verified: an assessment of impacts on value, scope, and delivery. An external change needs project-specific impact analysis before a response is chosen.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.

        173. 3.2 Obligations and conformity evidence

          A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Evidence not yet verified: assigned compliance controls and required approvals. Verified evidence in the review file: a gap assessment and consequences of noncompliance. Verified evidence in the review file: a register of applicable legal and contractual obligations. Which action should the project manager take next based on this evidence?

          1. Confirm and classify the applicable compliance obligations.
          2. Assess current gaps, threats, and consequences of noncompliance.
          3. Assign controls, owners, and required approval checkpoints.
          4. Verify compliance evidence before authorizing the release.
          Answer: C

          ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: assigned compliance controls and required approvals. Each gap needs a controlled response with ownership and authorized approval.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.

        174. 3.1 Decision authority and oversight

          A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: agreed decision rights and escalation thresholds. Evidence not yet verified: approved success measures and governance reporting arrangements. Verified evidence in the review file: a check that teams follow the approved authority model. Evidence not yet verified: the applicable organizational policies and authority constraints. Which action should the project manager take next based on this evidence?

          1. Approve success measures and the governance reporting cycle.
          2. Check decision records against the approved authority model.
          3. Review each partner’s mandatory governance requirements.
          4. Agree decision rights, escalation paths, and thresholds.
          Answer: C

          ECO task 3.1: Decision authority and oversight. Evidence not yet verified: the applicable organizational policies and authority constraints. Project rules must respect existing authority, ethics, and mandatory policies.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.

        175. 3.3 Authorized change execution

          A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Evidence not yet verified: an integrated impact analysis of the requested feature. Evidence not yet verified: a recorded change request with a clear business rationale. Verified evidence in the review file: implementation records and updated baselines for the approved change. Evidence not yet verified: a documented decision by the authorized change authority. Which action should the project manager take next based on this evidence?

          1. Record the request, its rationale, and requested outcome.
          2. Submit the analysis to the authorized change authority.
          3. Implement the approved change and update controlled documents.
          4. Assess scope, cost, schedule, risk, and benefit impacts.
          Answer: A

          ECO task 3.3: Authorized change execution. Evidence not yet verified: a recorded change request with a clear business rationale. A controlled change needs a traceable request before analysis and decision.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.

        176. 3.4 Resolving realized blockers

          A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Evidence not yet verified: a current issue record and confirmed impact. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Evidence not yet verified: an authorized workaround or corrective intervention. Verified evidence in the review file: a retest proving that testing can resume safely. Which action should the project manager take next based on this evidence?

          1. Coordinate and apply the authorized corrective intervention.
          2. Retest the blocked workflow before closing the issue.
          3. Record the realized issue and assess its current impact.
          4. Assign an issue owner and prioritize the required intervention.
          Answer: C

          ECO task 3.4: Resolving realized blockers. Evidence not yet verified: a current issue record and confirmed impact. An event that has occurred requires issue management, even if it began as a risk.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.

        177. 3.5 Uncertainty and response monitoring

          A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Evidence not yet verified: a cause-event-effect risk statement and an owner. Verified evidence in the review file: a monitoring check of triggers and residual exposure. Evidence not yet verified: an approved response, trigger, and contingency owner. Evidence not yet verified: an assessed probability, impact, and risk priority. Which action should the project manager take next based on this evidence?

          1. Agree the risk response, trigger, and contingency responsibility.
          2. Monitor triggers, residual risk, and response effectiveness.
          3. Record the uncertain event, causes, effects, and risk owner.
          4. Analyze probability and impact against the agreed risk criteria.
          Answer: C

          ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: a cause-event-effect risk statement and an owner. A useful risk record distinguishes uncertainty from an issue that has already occurred.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.

        178. 3.6 Testing and reusing improvements

          A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Evidence not yet verified: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Evidence not yet verified: a small improvement experiment and an outcome measure. Which action should the project manager take next based on this evidence?

          1. Update the standard process and publish the validated lesson.
          2. Design a limited experiment with a measurable outcome.
          3. Run the experiment and compare outcomes with the baseline.
          4. Analyze rework evidence and identify the root cause.
          Answer: D

          ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.

        179. 3.7 Readiness and organizational adoption

          A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: adoption evidence and adjustments to transition support. Evidence not yet verified: a supported pilot with trained users and escalation access. Evidence not yet verified: a role-impact assessment and agreed transition support. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Which action should the project manager take next based on this evidence?

          1. Measure adoption and adjust support using user feedback.
          2. Assess culture and discuss concerns with affected departments.
          3. Map role impacts and agree training and transition support.
          4. Run a supported pilot before the wider transition.
          Answer: B

          ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Resistance can reflect real impacts that need understanding before a transition is planned.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.

        180. 3.8 Responding to external change

          A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Evidence not yet verified: an assessment of impacts on value, scope, and delivery. Evidence not yet verified: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Which action should the project manager take next based on this evidence?

          1. Assign ongoing monitoring and review further impacts.
          2. Assess and prioritize the change’s project impacts.
          3. Obtain the required decision and update the delivery plan.
          4. Verify the external change with authoritative sources.
          Answer: D

          ECO task 3.8: Responding to external change. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Unverified announcements can't provide a reliable basis for changing project commitments.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.

        Full mock exams

        Two different 180-question knowledge papers, each on a 240-minute clock. The first is free; the second is in Full access. Practical work is separate.

        1. PMP knowledge mock 1180 original single-response questions in 240 minutes. Each mock uses different questions. Checked practical tasks are separate. Practice target: 144.180 questions · 4 h
        2. PMP knowledge mock 2180 original single-response questions in 240 minutes. Each mock uses different questions. Checked practical tasks are separate. Practice target: 144.180 questions · 4 h

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.