1.1 Shared outcomes and understanding
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives.
Evidence not yet verified: the operators’ intended outcomes.
Verified evidence in the review file: an agreed vision with measurable success criteria.
Verified evidence in the review file: evidence that each operator interprets the vision consistently.
Verified evidence in the review file: a communication owner and a date to review the vision.
Which action should the project manager take next based on this evidence?
- Interview the operators about their intended outcomes.
- Agree a shared vision and measurable success criteria.
- Test understanding and investigate conflicting interpretations.
- Assign the vision’s communication owner and review date.
Answer: A
ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.
1.2 Conflict diagnosis and resolution
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up.
Evidence not yet verified: the immediate enforcement of respectful discussion rules.
Verified evidence in the review file: a follow-up check that the agreement is working.
Verified evidence in the review file: a mutually agreed resolution and decision rights.
Verified evidence in the review file: a neutral account of the underlying approval dispute.
Which action should the project manager take next based on this evidence?
- Establish and enforce respectful discussion rules.
- Hear both teams and establish the source of the dispute.
- Facilitate an agreement on approval responsibilities.
- Review the next approval cycle with both teams.
Answer: A
ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.
1.3 Team authority and tailored support
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support.
Verified evidence in the review file: a tailored delegation and coaching arrangement.
Verified evidence in the review file: a feedback review of delegation and team concerns.
Evidence not yet verified: a shared release goal and clear decision responsibilities.
Verified evidence in the review file: a review of members’ experience and support needs.
Which action should the project manager take next based on this evidence?
- Agree the release goal and each role’s decision authority.
- Assess experience and ask members what support they need.
- Delegate within agreed limits and coach where support is needed.
- Review results with the team and adjust leadership support.
Answer: A
ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.
1.5 Negotiating shared expectations
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations.
Verified evidence in the review file: support for department leads applying the agreed target.
Verified evidence in the review file: a negotiated response-time target and accepted trade-offs.
Verified evidence in the review file: explicit response-time expectations from both departments.
Evidence not yet verified: a classification of stakeholder groups and decision authority.
Which action should the project manager take next based on this evidence?
- Ask both departments to state measurable expectations.
- Classify stakeholders by role and decision authority.
- Facilitate agreement on the target and its trade-offs.
- Coach department leads on applying the agreed target.
Answer: B
ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.
1.7 Operational knowledge handover
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist.
Verified evidence in the review file: captured diagnostic examples and decision rules.
Verified evidence in the review file: guided practice for the receiving operations team.
Verified evidence in the review file: an independent diagnosis and accepted handover evidence.
Evidence not yet verified: an inventory of critical diagnostic knowledge.
Which action should the project manager take next based on this evidence?
- Run paired diagnostic practice with the receiving team.
- Have operations diagnose a fresh failure without coaching.
- Identify critical knowledge with the specialist and operations.
- Capture failure examples and the specialist’s decision rules.
Answer: C
ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.
1.4 Stakeholder involvement
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator.
Evidence not yet verified: an assessment of each group’s influence and needs.
Verified evidence in the review file: a complete list of affected groups.
Verified evidence in the review file: feedback showing whether engagement reaches each group.
Verified evidence in the review file: an engagement approach agreed with affected groups.
Which action should the project manager take next based on this evidence?
- Agree suitable workshops, updates, and responsible owners.
- Analyze influence, impact, and information needs.
- Check participation and adjust the engagement approach.
- Identify the affected groups with operations representatives.
Answer: B
ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an assessment of each group’s influence and needs. An inventory names people; analysis determines how to engage them.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.
1.6 Customer satisfaction evidence
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements.
Verified evidence in the review file: confirmed expectations of internal and external customers.
Evidence not yet verified: a comparison between pilot outcomes and customer expectations.
Verified evidence in the review file: an agreed response to the confirmed satisfaction gap.
Verified evidence in the review file: a repeat measurement after the agreed response.
Which action should the project manager take next based on this evidence?
- Agree a response with customers and the accountable owner.
- Measure satisfaction again after the response is applied.
- Confirm expectations with internal and external customers.
- Compare pilot evidence with the confirmed expectations.
Answer: D
ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. A complaint needs evidence about the gap before the response is selected.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.
1.8 Audience-specific reporting
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information.
Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations.
Verified evidence in the review file: confirmation that recipients understand and can respond.
Verified evidence in the review file: delivery of a tailored report through the agreed channels.
Evidence not yet verified: an agreed channel, cadence, owner, and feedback method.
Which action should the project manager take next based on this evidence?
- Agree the communication plan with the intended audiences.
- Distribute the tailored report using the agreed plan.
- Ask recipients for feedback and adjust future reports.
- Determine reporting needs and confidentiality requirements.
Answer: A
ECO task 1.8: Audience-specific reporting. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Planning makes reporting responsibilities and feedback explicit before information is distributed.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.
1.1 Shared outcomes and understanding
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives.
Evidence not yet verified: evidence that each operator interprets the vision consistently.
Verified evidence in the review file: a communication owner and a date to review the vision.
Verified evidence in the review file: the operators’ intended outcomes.
Verified evidence in the review file: an agreed vision with measurable success criteria.
Which action should the project manager take next based on this evidence?
- Assign the vision’s communication owner and review date.
- Interview the operators about their intended outcomes.
- Agree a shared vision and measurable success criteria.
- Test understanding and investigate conflicting interpretations.
Answer: D
ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: evidence that each operator interprets the vision consistently. A signature doesn't prove shared understanding; conflicting interpretations need examination.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.
1.2 Conflict diagnosis and resolution
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up.
Verified evidence in the review file: a follow-up check that the agreement is working.
Evidence not yet verified: a mutually agreed resolution and decision rights.
Verified evidence in the review file: a neutral account of the underlying approval dispute.
Verified evidence in the review file: the immediate enforcement of respectful discussion rules.
Which action should the project manager take next based on this evidence?
- Review the next approval cycle with both teams.
- Establish and enforce respectful discussion rules.
- Hear both teams and establish the source of the dispute.
- Facilitate an agreement on approval responsibilities.
Answer: D
ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: a mutually agreed resolution and decision rights. An understood conflict still needs a resolution the parties can implement.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.
1.3 Team authority and tailored support
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support.
Verified evidence in the review file: a review of members’ experience and support needs.
Evidence not yet verified: a tailored delegation and coaching arrangement.
Verified evidence in the review file: a feedback review of delegation and team concerns.
Verified evidence in the review file: a shared release goal and clear decision responsibilities.
Which action should the project manager take next based on this evidence?
- Delegate within agreed limits and coach where support is needed.
- Review results with the team and adjust leadership support.
- Agree the release goal and each role’s decision authority.
- Assess experience and ask members what support they need.
Answer: A
ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a tailored delegation and coaching arrangement. Experienced members can own decisions while less experienced members receive focused coaching.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.
1.5 Negotiating shared expectations
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations.
Verified evidence in the review file: explicit response-time expectations from both departments.
Verified evidence in the review file: a classification of stakeholder groups and decision authority.
Verified evidence in the review file: support for department leads applying the agreed target.
Evidence not yet verified: a negotiated response-time target and accepted trade-offs.
Which action should the project manager take next based on this evidence?
- Coach department leads on applying the agreed target.
- Facilitate agreement on the target and its trade-offs.
- Classify stakeholders by role and decision authority.
- Ask both departments to state measurable expectations.
Answer: B
ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Alignment requires agreement on competing expectations rather than silently choosing one department.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.
1.7 Operational knowledge handover
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist.
Verified evidence in the review file: an inventory of critical diagnostic knowledge.
Verified evidence in the review file: captured diagnostic examples and decision rules.
Evidence not yet verified: guided practice for the receiving operations team.
Verified evidence in the review file: an independent diagnosis and accepted handover evidence.
Which action should the project manager take next based on this evidence?
- Identify critical knowledge with the specialist and operations.
- Capture failure examples and the specialist’s decision rules.
- Have operations diagnose a fresh failure without coaching.
- Run paired diagnostic practice with the receiving team.
Answer: D
ECO task 1.7: Operational knowledge handover. Evidence not yet verified: guided practice for the receiving operations team. Documents need practice so that the receiving team can apply the reasoning.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.
1.4 Stakeholder involvement
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator.
Verified evidence in the review file: a complete list of affected groups.
Evidence not yet verified: feedback showing whether engagement reaches each group.
Verified evidence in the review file: an engagement approach agreed with affected groups.
Verified evidence in the review file: an assessment of each group’s influence and needs.
Which action should the project manager take next based on this evidence?
- Check participation and adjust the engagement approach.
- Identify the affected groups with operations representatives.
- Analyze influence, impact, and information needs.
- Agree suitable workshops, updates, and responsible owners.
Answer: A
ECO task 1.4: Stakeholder involvement. Evidence not yet verified: feedback showing whether engagement reaches each group. An approved plan needs feedback to show whether it builds involvement and trust.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.
1.6 Customer satisfaction evidence
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements.
Verified evidence in the review file: an agreed response to the confirmed satisfaction gap.
Evidence not yet verified: a repeat measurement after the agreed response.
Verified evidence in the review file: confirmed expectations of internal and external customers.
Verified evidence in the review file: a comparison between pilot outcomes and customer expectations.
Which action should the project manager take next based on this evidence?
- Confirm expectations with internal and external customers.
- Compare pilot evidence with the confirmed expectations.
- Agree a response with customers and the accountable owner.
- Measure satisfaction again after the response is applied.
Answer: D
ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: a repeat measurement after the agreed response. Customer expectations require continuing monitoring; an agreed action doesn't prove improvement.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.
1.8 Audience-specific reporting
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information.
Evidence not yet verified: confirmation that recipients understand and can respond.
Verified evidence in the review file: delivery of a tailored report through the agreed channels.
Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method.
Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations.
Which action should the project manager take next based on this evidence?
- Determine reporting needs and confidentiality requirements.
- Agree the communication plan with the intended audiences.
- Ask recipients for feedback and adjust future reports.
- Distribute the tailored report using the agreed plan.
Answer: C
ECO task 1.8: Audience-specific reporting. Evidence not yet verified: confirmation that recipients understand and can respond. Successful transmission doesn't prove understanding; feedback closes the communication loop.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.
1.1 Shared outcomes and understanding
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives.
Evidence not yet verified: an agreed vision with measurable success criteria.
Verified evidence in the review file: evidence that each operator interprets the vision consistently.
Verified evidence in the review file: a communication owner and a date to review the vision.
Evidence not yet verified: the operators’ intended outcomes.
Which action should the project manager take next based on this evidence?
- Test understanding and investigate conflicting interpretations.
- Assign the vision’s communication owner and review date.
- Interview the operators about their intended outcomes.
- Agree a shared vision and measurable success criteria.
Answer: C
ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.
1.2 Conflict diagnosis and resolution
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up.
Evidence not yet verified: a neutral account of the underlying approval dispute.
Evidence not yet verified: the immediate enforcement of respectful discussion rules.
Verified evidence in the review file: a follow-up check that the agreement is working.
Verified evidence in the review file: a mutually agreed resolution and decision rights.
Which action should the project manager take next based on this evidence?
- Facilitate an agreement on approval responsibilities.
- Review the next approval cycle with both teams.
- Hear both teams and establish the source of the dispute.
- Establish and enforce respectful discussion rules.
Answer: D
ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.
1.3 Team authority and tailored support
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support.
Evidence not yet verified: a shared release goal and clear decision responsibilities.
Evidence not yet verified: a review of members’ experience and support needs.
Verified evidence in the review file: a tailored delegation and coaching arrangement.
Verified evidence in the review file: a feedback review of delegation and team concerns.
Which action should the project manager take next based on this evidence?
- Delegate within agreed limits and coach where support is needed.
- Agree the release goal and each role’s decision authority.
- Review results with the team and adjust leadership support.
- Assess experience and ask members what support they need.
Answer: B
ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.
1.5 Negotiating shared expectations
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations.
Evidence not yet verified: a classification of stakeholder groups and decision authority.
Verified evidence in the review file: support for department leads applying the agreed target.
Verified evidence in the review file: a negotiated response-time target and accepted trade-offs.
Evidence not yet verified: explicit response-time expectations from both departments.
Which action should the project manager take next based on this evidence?
- Classify stakeholders by role and decision authority.
- Facilitate agreement on the target and its trade-offs.
- Coach department leads on applying the agreed target.
- Ask both departments to state measurable expectations.
Answer: A
ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.
1.7 Operational knowledge handover
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist.
Verified evidence in the review file: guided practice for the receiving operations team.
Verified evidence in the review file: an independent diagnosis and accepted handover evidence.
Evidence not yet verified: an inventory of critical diagnostic knowledge.
Evidence not yet verified: captured diagnostic examples and decision rules.
Which action should the project manager take next based on this evidence?
- Have operations diagnose a fresh failure without coaching.
- Identify critical knowledge with the specialist and operations.
- Capture failure examples and the specialist’s decision rules.
- Run paired diagnostic practice with the receiving team.
Answer: B
ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.
1.4 Stakeholder involvement
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator.
Verified evidence in the review file: feedback showing whether engagement reaches each group.
Evidence not yet verified: an engagement approach agreed with affected groups.
Verified evidence in the review file: an assessment of each group’s influence and needs.
Evidence not yet verified: a complete list of affected groups.
Which action should the project manager take next based on this evidence?
- Check participation and adjust the engagement approach.
- Analyze influence, impact, and information needs.
- Identify the affected groups with operations representatives.
- Agree suitable workshops, updates, and responsible owners.
Answer: C
ECO task 1.4: Stakeholder involvement. Evidence not yet verified: a complete list of affected groups. You can't tailor engagement for stakeholders you haven't identified.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.
1.6 Customer satisfaction evidence
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements.
Verified evidence in the review file: a comparison between pilot outcomes and customer expectations.
Evidence not yet verified: an agreed response to the confirmed satisfaction gap.
Verified evidence in the review file: a repeat measurement after the agreed response.
Evidence not yet verified: confirmed expectations of internal and external customers.
Which action should the project manager take next based on this evidence?
- Measure satisfaction again after the response is applied.
- Confirm expectations with internal and external customers.
- Compare pilot evidence with the confirmed expectations.
- Agree a response with customers and the accountable owner.
Answer: B
ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: confirmed expectations of internal and external customers. The team needs actual customer expectations before judging satisfaction.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.
1.8 Audience-specific reporting
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information.
Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method.
Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations.
Verified evidence in the review file: confirmation that recipients understand and can respond.
Evidence not yet verified: delivery of a tailored report through the agreed channels.
Which action should the project manager take next based on this evidence?
- Determine reporting needs and confidentiality requirements.
- Ask recipients for feedback and adjust future reports.
- Agree the communication plan with the intended audiences.
- Distribute the tailored report using the agreed plan.
Answer: A
ECO task 1.8: Audience-specific reporting. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. The communication method must follow audience needs and mandatory restrictions.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.
1.1 Shared outcomes and understanding
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives.
Evidence not yet verified: the operators’ intended outcomes.
Verified evidence in the review file: an agreed vision with measurable success criteria.
Verified evidence in the review file: evidence that each operator interprets the vision consistently.
Evidence not yet verified: a communication owner and a date to review the vision.
Which action should the project manager take next based on this evidence?
- Agree a shared vision and measurable success criteria.
- Interview the operators about their intended outcomes.
- Test understanding and investigate conflicting interpretations.
- Assign the vision’s communication owner and review date.
Answer: B
ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.
1.2 Conflict diagnosis and resolution
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up.
Evidence not yet verified: the immediate enforcement of respectful discussion rules.
Evidence not yet verified: a follow-up check that the agreement is working.
Verified evidence in the review file: a mutually agreed resolution and decision rights.
Verified evidence in the review file: a neutral account of the underlying approval dispute.
Which action should the project manager take next based on this evidence?
- Hear both teams and establish the source of the dispute.
- Establish and enforce respectful discussion rules.
- Facilitate an agreement on approval responsibilities.
- Review the next approval cycle with both teams.
Answer: B
ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.
1.3 Team authority and tailored support
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support.
Verified evidence in the review file: a tailored delegation and coaching arrangement.
Evidence not yet verified: a feedback review of delegation and team concerns.
Evidence not yet verified: a shared release goal and clear decision responsibilities.
Verified evidence in the review file: a review of members’ experience and support needs.
Which action should the project manager take next based on this evidence?
- Agree the release goal and each role’s decision authority.
- Assess experience and ask members what support they need.
- Delegate within agreed limits and coach where support is needed.
- Review results with the team and adjust leadership support.
Answer: A
ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.
1.5 Negotiating shared expectations
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations.
Evidence not yet verified: support for department leads applying the agreed target.
Verified evidence in the review file: a negotiated response-time target and accepted trade-offs.
Verified evidence in the review file: explicit response-time expectations from both departments.
Evidence not yet verified: a classification of stakeholder groups and decision authority.
Which action should the project manager take next based on this evidence?
- Classify stakeholders by role and decision authority.
- Ask both departments to state measurable expectations.
- Facilitate agreement on the target and its trade-offs.
- Coach department leads on applying the agreed target.
Answer: A
ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.
1.7 Operational knowledge handover
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist.
Verified evidence in the review file: captured diagnostic examples and decision rules.
Verified evidence in the review file: guided practice for the receiving operations team.
Evidence not yet verified: an independent diagnosis and accepted handover evidence.
Evidence not yet verified: an inventory of critical diagnostic knowledge.
Which action should the project manager take next based on this evidence?
- Identify critical knowledge with the specialist and operations.
- Run paired diagnostic practice with the receiving team.
- Have operations diagnose a fresh failure without coaching.
- Capture failure examples and the specialist’s decision rules.
Answer: A
ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.
1.4 Stakeholder involvement
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator.
Evidence not yet verified: an assessment of each group’s influence and needs.
Verified evidence in the review file: a complete list of affected groups.
Verified evidence in the review file: feedback showing whether engagement reaches each group.
Evidence not yet verified: an engagement approach agreed with affected groups.
Which action should the project manager take next based on this evidence?
- Agree suitable workshops, updates, and responsible owners.
- Check participation and adjust the engagement approach.
- Analyze influence, impact, and information needs.
- Identify the affected groups with operations representatives.
Answer: C
ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an assessment of each group’s influence and needs. An inventory names people; analysis determines how to engage them.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.
1.6 Customer satisfaction evidence
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements.
Verified evidence in the review file: confirmed expectations of internal and external customers.
Evidence not yet verified: a comparison between pilot outcomes and customer expectations.
Evidence not yet verified: an agreed response to the confirmed satisfaction gap.
Verified evidence in the review file: a repeat measurement after the agreed response.
Which action should the project manager take next based on this evidence?
- Agree a response with customers and the accountable owner.
- Measure satisfaction again after the response is applied.
- Confirm expectations with internal and external customers.
- Compare pilot evidence with the confirmed expectations.
Answer: D
ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. A complaint needs evidence about the gap before the response is selected.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.
1.8 Audience-specific reporting
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information.
Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations.
Verified evidence in the review file: confirmation that recipients understand and can respond.
Evidence not yet verified: delivery of a tailored report through the agreed channels.
Evidence not yet verified: an agreed channel, cadence, owner, and feedback method.
Which action should the project manager take next based on this evidence?
- Distribute the tailored report using the agreed plan.
- Ask recipients for feedback and adjust future reports.
- Determine reporting needs and confidentiality requirements.
- Agree the communication plan with the intended audiences.
Answer: D
ECO task 1.8: Audience-specific reporting. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Planning makes reporting responsibilities and feedback explicit before information is distributed.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.
1.1 Shared outcomes and understanding
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives.
Verified evidence in the review file: evidence that each operator interprets the vision consistently.
Evidence not yet verified: a communication owner and a date to review the vision.
Verified evidence in the review file: the operators’ intended outcomes.
Evidence not yet verified: an agreed vision with measurable success criteria.
Which action should the project manager take next based on this evidence?
- Assign the vision’s communication owner and review date.
- Interview the operators about their intended outcomes.
- Test understanding and investigate conflicting interpretations.
- Agree a shared vision and measurable success criteria.
Answer: D
ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: an agreed vision with measurable success criteria. Agreeing the outcome resolves competing definitions of success before promotion.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.
1.2 Conflict diagnosis and resolution
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up.
Evidence not yet verified: a follow-up check that the agreement is working.
Verified evidence in the review file: a mutually agreed resolution and decision rights.
Evidence not yet verified: a neutral account of the underlying approval dispute.
Verified evidence in the review file: the immediate enforcement of respectful discussion rules.
Which action should the project manager take next based on this evidence?
- Review the next approval cycle with both teams.
- Establish and enforce respectful discussion rules.
- Facilitate an agreement on approval responsibilities.
- Hear both teams and establish the source of the dispute.
Answer: D
ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: a neutral account of the underlying approval dispute. Selecting a resolution without the source and context risks treating the wrong problem.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.
1.3 Team authority and tailored support
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support.
Evidence not yet verified: a review of members’ experience and support needs.
Verified evidence in the review file: a tailored delegation and coaching arrangement.
Evidence not yet verified: a feedback review of delegation and team concerns.
Verified evidence in the review file: a shared release goal and clear decision responsibilities.
Which action should the project manager take next based on this evidence?
- Assess experience and ask members what support they need.
- Review results with the team and adjust leadership support.
- Agree the release goal and each role’s decision authority.
- Delegate within agreed limits and coach where support is needed.
Answer: A
ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a review of members’ experience and support needs. A leadership style should respond to demonstrated capability and needs, not one rule for everyone.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.
1.5 Negotiating shared expectations
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations.
Evidence not yet verified: explicit response-time expectations from both departments.
Verified evidence in the review file: a classification of stakeholder groups and decision authority.
Evidence not yet verified: support for department leads applying the agreed target.
Verified evidence in the review file: a negotiated response-time target and accepted trade-offs.
Which action should the project manager take next based on this evidence?
- Coach department leads on applying the agreed target.
- Classify stakeholders by role and decision authority.
- Ask both departments to state measurable expectations.
- Facilitate agreement on the target and its trade-offs.
Answer: C
ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: explicit response-time expectations from both departments. Vague expectations can't be compared or negotiated reliably.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.
1.7 Operational knowledge handover
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist.
Verified evidence in the review file: an inventory of critical diagnostic knowledge.
Evidence not yet verified: captured diagnostic examples and decision rules.
Verified evidence in the review file: guided practice for the receiving operations team.
Evidence not yet verified: an independent diagnosis and accepted handover evidence.
Which action should the project manager take next based on this evidence?
- Capture failure examples and the specialist’s decision rules.
- Identify critical knowledge with the specialist and operations.
- Run paired diagnostic practice with the receiving team.
- Have operations diagnose a fresh failure without coaching.
Answer: A
ECO task 1.7: Operational knowledge handover. Evidence not yet verified: captured diagnostic examples and decision rules. Capturing tacit reasoning makes more knowledge available than a list of system components.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.
1.4 Stakeholder involvement
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator.
Verified evidence in the review file: a complete list of affected groups.
Evidence not yet verified: feedback showing whether engagement reaches each group.
Evidence not yet verified: an engagement approach agreed with affected groups.
Verified evidence in the review file: an assessment of each group’s influence and needs.
Which action should the project manager take next based on this evidence?
- Identify the affected groups with operations representatives.
- Agree suitable workshops, updates, and responsible owners.
- Analyze influence, impact, and information needs.
- Check participation and adjust the engagement approach.
Answer: B
ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an engagement approach agreed with affected groups. The approach should reflect the assessed needs instead of sending everyone identical reports.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.
1.6 Customer satisfaction evidence
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements.
Evidence not yet verified: an agreed response to the confirmed satisfaction gap.
Evidence not yet verified: a repeat measurement after the agreed response.
Verified evidence in the review file: confirmed expectations of internal and external customers.
Verified evidence in the review file: a comparison between pilot outcomes and customer expectations.
Which action should the project manager take next based on this evidence?
- Confirm expectations with internal and external customers.
- Agree a response with customers and the accountable owner.
- Compare pilot evidence with the confirmed expectations.
- Measure satisfaction again after the response is applied.
Answer: B
ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. The response should address the measured gap through the appropriate decision process.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.
1.8 Audience-specific reporting
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information.
Evidence not yet verified: confirmation that recipients understand and can respond.
Evidence not yet verified: delivery of a tailored report through the agreed channels.
Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method.
Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations.
Which action should the project manager take next based on this evidence?
- Determine reporting needs and confidentiality requirements.
- Agree the communication plan with the intended audiences.
- Ask recipients for feedback and adjust future reports.
- Distribute the tailored report using the agreed plan.
Answer: D
ECO task 1.8: Audience-specific reporting. Evidence not yet verified: delivery of a tailored report through the agreed channels. A communication plan produces no shared information until the report reaches its audience.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.
1.1 Shared outcomes and understanding
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives.
Evidence not yet verified: an agreed vision with measurable success criteria.
Evidence not yet verified: evidence that each operator interprets the vision consistently.
Verified evidence in the review file: a communication owner and a date to review the vision.
Evidence not yet verified: the operators’ intended outcomes.
Which action should the project manager take next based on this evidence?
- Test understanding and investigate conflicting interpretations.
- Assign the vision’s communication owner and review date.
- Interview the operators about their intended outcomes.
- Agree a shared vision and measurable success criteria.
Answer: C
ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.
1.2 Conflict diagnosis and resolution
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up.
Evidence not yet verified: a neutral account of the underlying approval dispute.
Evidence not yet verified: the immediate enforcement of respectful discussion rules.
Verified evidence in the review file: a follow-up check that the agreement is working.
Evidence not yet verified: a mutually agreed resolution and decision rights.
Which action should the project manager take next based on this evidence?
- Facilitate an agreement on approval responsibilities.
- Establish and enforce respectful discussion rules.
- Review the next approval cycle with both teams.
- Hear both teams and establish the source of the dispute.
Answer: B
ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.
1.3 Team authority and tailored support
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support.
Evidence not yet verified: a shared release goal and clear decision responsibilities.
Evidence not yet verified: a review of members’ experience and support needs.
Evidence not yet verified: a tailored delegation and coaching arrangement.
Verified evidence in the review file: a feedback review of delegation and team concerns.
Which action should the project manager take next based on this evidence?
- Delegate within agreed limits and coach where support is needed.
- Review results with the team and adjust leadership support.
- Agree the release goal and each role’s decision authority.
- Assess experience and ask members what support they need.
Answer: C
ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.
1.5 Negotiating shared expectations
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations.
Evidence not yet verified: a classification of stakeholder groups and decision authority.
Verified evidence in the review file: support for department leads applying the agreed target.
Evidence not yet verified: a negotiated response-time target and accepted trade-offs.
Evidence not yet verified: explicit response-time expectations from both departments.
Which action should the project manager take next based on this evidence?
- Facilitate agreement on the target and its trade-offs.
- Classify stakeholders by role and decision authority.
- Coach department leads on applying the agreed target.
- Ask both departments to state measurable expectations.
Answer: B
ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.
1.7 Operational knowledge handover
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist.
Evidence not yet verified: guided practice for the receiving operations team.
Verified evidence in the review file: an independent diagnosis and accepted handover evidence.
Evidence not yet verified: an inventory of critical diagnostic knowledge.
Evidence not yet verified: captured diagnostic examples and decision rules.
Which action should the project manager take next based on this evidence?
- Have operations diagnose a fresh failure without coaching.
- Identify critical knowledge with the specialist and operations.
- Capture failure examples and the specialist’s decision rules.
- Run paired diagnostic practice with the receiving team.
Answer: B
ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.
1.4 Stakeholder involvement
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator.
Evidence not yet verified: feedback showing whether engagement reaches each group.
Verified evidence in the review file: an engagement approach agreed with affected groups.
Evidence not yet verified: an assessment of each group’s influence and needs.
Evidence not yet verified: a complete list of affected groups.
Which action should the project manager take next based on this evidence?
- Identify the affected groups with operations representatives.
- Check participation and adjust the engagement approach.
- Analyze influence, impact, and information needs.
- Agree suitable workshops, updates, and responsible owners.
Answer: A
ECO task 1.4: Stakeholder involvement. Evidence not yet verified: a complete list of affected groups. You can't tailor engagement for stakeholders you haven't identified.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.
1.6 Customer satisfaction evidence
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements.
Evidence not yet verified: a comparison between pilot outcomes and customer expectations.
Verified evidence in the review file: an agreed response to the confirmed satisfaction gap.
Evidence not yet verified: a repeat measurement after the agreed response.
Evidence not yet verified: confirmed expectations of internal and external customers.
Which action should the project manager take next based on this evidence?
- Measure satisfaction again after the response is applied.
- Confirm expectations with internal and external customers.
- Compare pilot evidence with the confirmed expectations.
- Agree a response with customers and the accountable owner.
Answer: B
ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: confirmed expectations of internal and external customers. The team needs actual customer expectations before judging satisfaction.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.
1.8 Audience-specific reporting
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information.
Evidence not yet verified: an agreed channel, cadence, owner, and feedback method.
Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations.
Evidence not yet verified: confirmation that recipients understand and can respond.
Verified evidence in the review file: delivery of a tailored report through the agreed channels.
Which action should the project manager take next based on this evidence?
- Ask recipients for feedback and adjust future reports.
- Agree the communication plan with the intended audiences.
- Determine reporting needs and confidentiality requirements.
- Distribute the tailored report using the agreed plan.
Answer: C
ECO task 1.8: Audience-specific reporting. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. The communication method must follow audience needs and mandatory restrictions.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.
1.1 Shared outcomes and understanding
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives.
Evidence not yet verified: the operators’ intended outcomes.
Verified evidence in the review file: an agreed vision with measurable success criteria.
Evidence not yet verified: evidence that each operator interprets the vision consistently.
Evidence not yet verified: a communication owner and a date to review the vision.
Which action should the project manager take next based on this evidence?
- Agree a shared vision and measurable success criteria.
- Interview the operators about their intended outcomes.
- Test understanding and investigate conflicting interpretations.
- Assign the vision’s communication owner and review date.
Answer: B
ECO task 1.1: Shared outcomes and understanding. Evidence not yet verified: the operators’ intended outcomes. A vision needs the affected stakeholders’ outcomes as its basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.1.
1.2 Conflict diagnosis and resolution
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up.
Evidence not yet verified: the immediate enforcement of respectful discussion rules.
Evidence not yet verified: a follow-up check that the agreement is working.
Evidence not yet verified: a mutually agreed resolution and decision rights.
Verified evidence in the review file: a neutral account of the underlying approval dispute.
Which action should the project manager take next based on this evidence?
- Hear both teams and establish the source of the dispute.
- Facilitate an agreement on approval responsibilities.
- Review the next approval cycle with both teams.
- Establish and enforce respectful discussion rules.
Answer: D
ECO task 1.2: Conflict diagnosis and resolution. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Respectful discussion rules provide a safe basis for examining and resolving conflict.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.2.
1.3 Team authority and tailored support
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support.
Evidence not yet verified: a tailored delegation and coaching arrangement.
Evidence not yet verified: a feedback review of delegation and team concerns.
Evidence not yet verified: a shared release goal and clear decision responsibilities.
Verified evidence in the review file: a review of members’ experience and support needs.
Which action should the project manager take next based on this evidence?
- Assess experience and ask members what support they need.
- Delegate within agreed limits and coach where support is needed.
- Review results with the team and adjust leadership support.
- Agree the release goal and each role’s decision authority.
Answer: D
ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.
1.5 Negotiating shared expectations
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations.
Evidence not yet verified: support for department leads applying the agreed target.
Evidence not yet verified: a negotiated response-time target and accepted trade-offs.
Verified evidence in the review file: explicit response-time expectations from both departments.
Evidence not yet verified: a classification of stakeholder groups and decision authority.
Which action should the project manager take next based on this evidence?
- Classify stakeholders by role and decision authority.
- Ask both departments to state measurable expectations.
- Facilitate agreement on the target and its trade-offs.
- Coach department leads on applying the agreed target.
Answer: A
ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.
1.7 Operational knowledge handover
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist.
Verified evidence in the review file: captured diagnostic examples and decision rules.
Evidence not yet verified: guided practice for the receiving operations team.
Evidence not yet verified: an independent diagnosis and accepted handover evidence.
Evidence not yet verified: an inventory of critical diagnostic knowledge.
Which action should the project manager take next based on this evidence?
- Run paired diagnostic practice with the receiving team.
- Identify critical knowledge with the specialist and operations.
- Have operations diagnose a fresh failure without coaching.
- Capture failure examples and the specialist’s decision rules.
Answer: B
ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.
1.4 Stakeholder involvement
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator.
Evidence not yet verified: an assessment of each group’s influence and needs.
Verified evidence in the review file: a complete list of affected groups.
Evidence not yet verified: feedback showing whether engagement reaches each group.
Evidence not yet verified: an engagement approach agreed with affected groups.
Which action should the project manager take next based on this evidence?
- Analyze influence, impact, and information needs.
- Agree suitable workshops, updates, and responsible owners.
- Check participation and adjust the engagement approach.
- Identify the affected groups with operations representatives.
Answer: A
ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an assessment of each group’s influence and needs. An inventory names people; analysis determines how to engage them.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.
1.6 Customer satisfaction evidence
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements.
Verified evidence in the review file: confirmed expectations of internal and external customers.
Evidence not yet verified: a comparison between pilot outcomes and customer expectations.
Evidence not yet verified: an agreed response to the confirmed satisfaction gap.
Evidence not yet verified: a repeat measurement after the agreed response.
Which action should the project manager take next based on this evidence?
- Agree a response with customers and the accountable owner.
- Compare pilot evidence with the confirmed expectations.
- Measure satisfaction again after the response is applied.
- Confirm expectations with internal and external customers.
Answer: B
ECO task 1.6: Customer satisfaction evidence. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. A complaint needs evidence about the gap before the response is selected.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.6.
1.8 Audience-specific reporting
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information.
Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations.
Evidence not yet verified: confirmation that recipients understand and can respond.
Evidence not yet verified: delivery of a tailored report through the agreed channels.
Evidence not yet verified: an agreed channel, cadence, owner, and feedback method.
Which action should the project manager take next based on this evidence?
- Distribute the tailored report using the agreed plan.
- Ask recipients for feedback and adjust future reports.
- Agree the communication plan with the intended audiences.
- Determine reporting needs and confidentiality requirements.
Answer: C
ECO task 1.8: Audience-specific reporting. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Planning makes reporting responsibilities and feedback explicit before information is distributed.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.8.
1.3 Team authority and tailored support
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support.
Evidence not yet verified: a tailored delegation and coaching arrangement.
Evidence not yet verified: a feedback review of delegation and team concerns.
Evidence not yet verified: a shared release goal and clear decision responsibilities.
Evidence not yet verified: a review of members’ experience and support needs.
Which action should the project manager take next based on this evidence?
- Agree the release goal and each role’s decision authority.
- Review results with the team and adjust leadership support.
- Assess experience and ask members what support they need.
- Delegate within agreed limits and coach where support is needed.
Answer: A
ECO task 1.3: Team authority and tailored support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Autonomy needs a clear goal and boundaries so that local decisions serve the project.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.3.
1.5 Negotiating shared expectations
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations.
Evidence not yet verified: support for department leads applying the agreed target.
Evidence not yet verified: a negotiated response-time target and accepted trade-offs.
Evidence not yet verified: explicit response-time expectations from both departments.
Evidence not yet verified: a classification of stakeholder groups and decision authority.
Which action should the project manager take next based on this evidence?
- Coach department leads on applying the agreed target.
- Classify stakeholders by role and decision authority.
- Ask both departments to state measurable expectations.
- Facilitate agreement on the target and its trade-offs.
Answer: B
ECO task 1.5: Negotiating shared expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Knowing the relevant groups and authority identifies whose expectations need agreement.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.5.
1.7 Operational knowledge handover
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist.
Evidence not yet verified: captured diagnostic examples and decision rules.
Evidence not yet verified: guided practice for the receiving operations team.
Evidence not yet verified: an independent diagnosis and accepted handover evidence.
Evidence not yet verified: an inventory of critical diagnostic knowledge.
Which action should the project manager take next based on this evidence?
- Have operations diagnose a fresh failure without coaching.
- Identify critical knowledge with the specialist and operations.
- Capture failure examples and the specialist’s decision rules.
- Run paired diagnostic practice with the receiving team.
Answer: B
ECO task 1.7: Operational knowledge handover. Evidence not yet verified: an inventory of critical diagnostic knowledge. Knowledge transfer starts with identifying what the receiving team must be able to do.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.7.
2.1 Integrated delivery planning
A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials.
Evidence not yet verified: an assessment of requirement stability and delivery constraints.
Verified evidence in the review file: an agreed hybrid approach for installation and iterative software.
Verified evidence in the review file: an integrated dependency, resource, and delivery plan.
Verified evidence in the review file: a review of plan gaps and continuing business value.
Which action should the project manager take next based on this evidence?
- Agree a hybrid approach with explicit integration points.
- Integrate dependencies, resources, and delivery milestones.
- Assess uncertainty, constraints, and required delivery outcomes.
- Review the integrated plan for gaps and continued value.
Answer: C
ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.
2.2 Release boundaries and work breakdown
A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records.
Evidence not yet verified: documented requirements and acceptance criteria.
Verified evidence in the review file: a completeness review of the scope breakdown.
Verified evidence in the review file: a breakdown into assignable work with traceability.
Verified evidence in the review file: an agreed release boundary and explicit exclusions.
Which action should the project manager take next based on this evidence?
- Agree included services and exclusions with stakeholders.
- Break the agreed scope into traceable work packages.
- Check the breakdown for omissions and unauthorized additions.
- Elicit requirements and define testable acceptance criteria.
Answer: D
ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.
2.3 Incremental benefit realization
A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit.
Verified evidence in the review file: an agreed usable increment and release test.
Verified evidence in the review file: benefit measurement after customers use the increment.
Evidence not yet verified: a measurable benefit agreed with the business owner.
Verified evidence in the review file: a ranked comparison of delivery options and dependencies.
Which action should the project manager take next based on this evidence?
- Rank delivery options by benefit, feedback, and dependencies.
- Plan a usable increment that tests the prioritized benefit.
- Measure realized benefit and use it to reprioritize work.
- Agree the benefit metric and its accountable business owner.
Answer: D
ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.
2.5 Supplier selection and acceptance
A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions.
Verified evidence in the review file: verified supplier performance and acceptance evidence.
Verified evidence in the review file: an authorized contract with measurable acceptance terms.
Verified evidence in the review file: a documented supplier evaluation under the agreed criteria.
Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk.
Which action should the project manager take next based on this evidence?
- Evaluate bids using the published procurement criteria.
- Negotiate and authorize the contract’s acceptance obligations.
- Define evaluation criteria and select suitable contract terms.
- Compare supplier evidence with the contractual acceptance terms.
Answer: C
ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.
2.7 Quality evidence and improvement
A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records.
Verified evidence in the review file: a quality plan with preventive controls and test methods.
Verified evidence in the review file: pilot measurements collected using the approved test method.
Verified evidence in the review file: an evidence-based improvement and effectiveness review.
Evidence not yet verified: testable quality requirements and applicable standards.
Which action should the project manager take next based on this evidence?
- Execute the approved tests and record pilot results.
- Confirm quality criteria and mandatory seal standards.
- Analyze defects, improve the process, and verify the result.
- Plan prevention, inspection, and evidence collection.
Answer: B
ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.
2.9 Reconciled project reporting
A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis.
Verified evidence in the review file: reconciled data from the authoritative project records.
Evidence not yet verified: metric definitions, data owners, and a common reporting date.
Verified evidence in the review file: an accessible version-controlled report for decision makers.
Verified evidence in the review file: an interpretation of progress, variance, and forecast implications.
Which action should the project manager take next based on this evidence?
- Analyze reconciled progress and explain forecast implications.
- Agree metric definitions and the reporting cutoff.
- Publish the reviewed report with access and version controls.
- Reconcile the report data against authoritative records.
Answer: B
ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.
2.4 Capacity and resource commitments
Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization.
Verified evidence in the review file: the required skills and estimated effort for each test.
Evidence not yet verified: confirmed technician and laboratory availability.
Verified evidence in the review file: an agreed allocation that respects authorized capacity.
Verified evidence in the review file: a utilization check against the agreed allocation.
Which action should the project manager take next based on this evidence?
- Negotiate a feasible allocation with both project owners.
- Monitor utilization and address new resource conflicts.
- Define test resource requirements and estimate the effort.
- Confirm calendars and competing resource commitments.
Answer: D
ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: confirmed technician and laboratory availability. A resource plan can't assume availability across competing projects.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.
2.6 Financial forecasting and control
A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast.
Verified evidence in the review file: an estimate of costs and identified financial risks.
Verified evidence in the review file: a governance review of the forecast and funding variance.
Verified evidence in the review file: reconciled actual spending and remaining cost estimates.
Evidence not yet verified: an authorized baseline and risk-based contingency allocation.
Which action should the project manager take next based on this evidence?
- Reconcile actual costs and estimate the remaining work.
- Obtain baseline approval and justify contingency reserves.
- Report the forecast and seek required funding decisions.
- Estimate costs and identify relevant financial uncertainty.
Answer: B
ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Contingency addresses identified risk and needs authorization under the funding rules.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.
2.8 Schedule dependencies and baselines
A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window.
Verified evidence in the review file: an approved schedule baseline coordinated with operations.
Verified evidence in the review file: an analysis of actual progress and schedule variation.
Verified evidence in the review file: validated activity dependencies and external operating constraints.
Evidence not yet verified: duration estimates and resource calendars.
Which action should the project manager take next based on this evidence?
- Compare actual progress with the baseline and assess impact.
- Validate dependencies and the permitted shutdown window.
- Estimate durations using team input and resource calendars.
- Coordinate dates with operations and approve the baseline.
Answer: C
ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: duration estimates and resource calendars. Dependency order alone doesn't establish feasible dates without durations and availability.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.
2.10 Acceptance and operational transition
A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses.
Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release.
Verified evidence in the review file: operations readiness and an accepted support handover.
Evidence not yet verified: formal stakeholder acceptance of completed deliverables.
Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria.
Which action should the project manager take next based on this evidence?
- Obtain acceptance evidence from the authorized stakeholders.
- Complete financial closure, archive lessons, and release resources.
- Confirm the contractual and project closure criteria.
- Validate operations readiness and complete the support handover.
Answer: A
ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Completion claims need authorized acceptance against the agreed criteria.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.
2.1 Integrated delivery planning
A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials.
Verified evidence in the review file: an agreed hybrid approach for installation and iterative software.
Evidence not yet verified: an integrated dependency, resource, and delivery plan.
Verified evidence in the review file: a review of plan gaps and continuing business value.
Verified evidence in the review file: an assessment of requirement stability and delivery constraints.
Which action should the project manager take next based on this evidence?
- Review the integrated plan for gaps and continued value.
- Integrate dependencies, resources, and delivery milestones.
- Assess uncertainty, constraints, and required delivery outcomes.
- Agree a hybrid approach with explicit integration points.
Answer: B
ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an integrated dependency, resource, and delivery plan. Separate component plans need reconciliation at their shared dependencies.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.
2.2 Release boundaries and work breakdown
A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records.
Verified evidence in the review file: an agreed release boundary and explicit exclusions.
Verified evidence in the review file: documented requirements and acceptance criteria.
Verified evidence in the review file: a completeness review of the scope breakdown.
Evidence not yet verified: a breakdown into assignable work with traceability.
Which action should the project manager take next based on this evidence?
- Check the breakdown for omissions and unauthorized additions.
- Elicit requirements and define testable acceptance criteria.
- Break the agreed scope into traceable work packages.
- Agree included services and exclusions with stakeholders.
Answer: C
ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: a breakdown into assignable work with traceability. Decomposition translates an agreed boundary into manageable work.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.
2.3 Incremental benefit realization
A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit.
Verified evidence in the review file: a measurable benefit agreed with the business owner.
Verified evidence in the review file: a ranked comparison of delivery options and dependencies.
Evidence not yet verified: an agreed usable increment and release test.
Verified evidence in the review file: benefit measurement after customers use the increment.
Which action should the project manager take next based on this evidence?
- Agree the benefit metric and its accountable business owner.
- Rank delivery options by benefit, feedback, and dependencies.
- Plan a usable increment that tests the prioritized benefit.
- Measure realized benefit and use it to reprioritize work.
Answer: C
ECO task 2.3: Incremental benefit realization. Evidence not yet verified: an agreed usable increment and release test. A usable increment tests value sooner than a collection of unfinished components.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.
2.5 Supplier selection and acceptance
A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions.
Verified evidence in the review file: evaluation criteria and an appropriate allocation of contract risk.
Verified evidence in the review file: verified supplier performance and acceptance evidence.
Evidence not yet verified: an authorized contract with measurable acceptance terms.
Verified evidence in the review file: a documented supplier evaluation under the agreed criteria.
Which action should the project manager take next based on this evidence?
- Define evaluation criteria and select suitable contract terms.
- Evaluate bids using the published procurement criteria.
- Compare supplier evidence with the contractual acceptance terms.
- Negotiate and authorize the contract’s acceptance obligations.
Answer: D
ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: an authorized contract with measurable acceptance terms. A preferred bidder still needs an authorized agreement before contractual work starts.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.
2.7 Quality evidence and improvement
A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records.
Evidence not yet verified: pilot measurements collected using the approved test method.
Verified evidence in the review file: an evidence-based improvement and effectiveness review.
Verified evidence in the review file: testable quality requirements and applicable standards.
Verified evidence in the review file: a quality plan with preventive controls and test methods.
Which action should the project manager take next based on this evidence?
- Confirm quality criteria and mandatory seal standards.
- Execute the approved tests and record pilot results.
- Plan prevention, inspection, and evidence collection.
- Analyze defects, improve the process, and verify the result.
Answer: B
ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: pilot measurements collected using the approved test method. Inspection evidence is needed before diagnosing the production process from pilot results.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.
2.9 Reconciled project reporting
A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis.
Verified evidence in the review file: an accessible version-controlled report for decision makers.
Evidence not yet verified: an interpretation of progress, variance, and forecast implications.
Verified evidence in the review file: reconciled data from the authoritative project records.
Verified evidence in the review file: metric definitions, data owners, and a common reporting date.
Which action should the project manager take next based on this evidence?
- Agree metric definitions and the reporting cutoff.
- Reconcile the report data against authoritative records.
- Analyze reconciled progress and explain forecast implications.
- Publish the reviewed report with access and version controls.
Answer: C
ECO task 2.9: Reconciled project reporting. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Reporting should explain the meaning of the measures, not only reproduce their values.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.
2.4 Capacity and resource commitments
Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization.
Verified evidence in the review file: confirmed technician and laboratory availability.
Verified evidence in the review file: an agreed allocation that respects authorized capacity.
Evidence not yet verified: a utilization check against the agreed allocation.
Verified evidence in the review file: the required skills and estimated effort for each test.
Which action should the project manager take next based on this evidence?
- Monitor utilization and address new resource conflicts.
- Confirm calendars and competing resource commitments.
- Negotiate a feasible allocation with both project owners.
- Define test resource requirements and estimate the effort.
Answer: A
ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: a utilization check against the agreed allocation. Resource availability changes during delivery and requires ongoing adjustment.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.
2.6 Financial forecasting and control
A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast.
Verified evidence in the review file: an authorized baseline and risk-based contingency allocation.
Verified evidence in the review file: an estimate of costs and identified financial risks.
Evidence not yet verified: a governance review of the forecast and funding variance.
Verified evidence in the review file: reconciled actual spending and remaining cost estimates.
Which action should the project manager take next based on this evidence?
- Report the forecast and seek required funding decisions.
- Obtain baseline approval and justify contingency reserves.
- Reconcile actual costs and estimate the remaining work.
- Estimate costs and identify relevant financial uncertainty.
Answer: A
ECO task 2.6: Financial forecasting and control. Evidence not yet verified: a governance review of the forecast and funding variance. A projected overrun must follow governance thresholds rather than silently consuming reserves.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.
2.8 Schedule dependencies and baselines
A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window.
Verified evidence in the review file: validated activity dependencies and external operating constraints.
Verified evidence in the review file: duration estimates and resource calendars.
Verified evidence in the review file: an approved schedule baseline coordinated with operations.
Evidence not yet verified: an analysis of actual progress and schedule variation.
Which action should the project manager take next based on this evidence?
- Estimate durations using team input and resource calendars.
- Compare actual progress with the baseline and assess impact.
- Coordinate dates with operations and approve the baseline.
- Validate dependencies and the permitted shutdown window.
Answer: B
ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: an analysis of actual progress and schedule variation. Activity slippage matters through its dependencies and available float, not lateness alone.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.
2.10 Acceptance and operational transition
A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses.
Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria.
Evidence not yet verified: closed contracts, archived lessons, and authorized resource release.
Verified evidence in the review file: operations readiness and an accepted support handover.
Verified evidence in the review file: formal stakeholder acceptance of completed deliverables.
Which action should the project manager take next based on this evidence?
- Obtain acceptance evidence from the authorized stakeholders.
- Complete financial closure, archive lessons, and release resources.
- Validate operations readiness and complete the support handover.
- Confirm the contractual and project closure criteria.
Answer: B
ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: closed contracts, archived lessons, and authorized resource release. Administrative closure follows acceptance and transition so that obligations remain covered.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.
2.1 Integrated delivery planning
A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials.
Verified evidence in the review file: an integrated dependency, resource, and delivery plan.
Verified evidence in the review file: a review of plan gaps and continuing business value.
Evidence not yet verified: an assessment of requirement stability and delivery constraints.
Evidence not yet verified: an agreed hybrid approach for installation and iterative software.
Which action should the project manager take next based on this evidence?
- Review the integrated plan for gaps and continued value.
- Assess uncertainty, constraints, and required delivery outcomes.
- Agree a hybrid approach with explicit integration points.
- Integrate dependencies, resources, and delivery milestones.
Answer: B
ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.
2.2 Release boundaries and work breakdown
A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records.
Verified evidence in the review file: a completeness review of the scope breakdown.
Verified evidence in the review file: a breakdown into assignable work with traceability.
Evidence not yet verified: an agreed release boundary and explicit exclusions.
Evidence not yet verified: documented requirements and acceptance criteria.
Which action should the project manager take next based on this evidence?
- Check the breakdown for omissions and unauthorized additions.
- Elicit requirements and define testable acceptance criteria.
- Agree included services and exclusions with stakeholders.
- Break the agreed scope into traceable work packages.
Answer: B
ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.
2.3 Incremental benefit realization
A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit.
Evidence not yet verified: a ranked comparison of delivery options and dependencies.
Verified evidence in the review file: an agreed usable increment and release test.
Verified evidence in the review file: benefit measurement after customers use the increment.
Evidence not yet verified: a measurable benefit agreed with the business owner.
Which action should the project manager take next based on this evidence?
- Agree the benefit metric and its accountable business owner.
- Measure realized benefit and use it to reprioritize work.
- Rank delivery options by benefit, feedback, and dependencies.
- Plan a usable increment that tests the prioritized benefit.
Answer: A
ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.
2.5 Supplier selection and acceptance
A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions.
Evidence not yet verified: a documented supplier evaluation under the agreed criteria.
Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk.
Verified evidence in the review file: verified supplier performance and acceptance evidence.
Verified evidence in the review file: an authorized contract with measurable acceptance terms.
Which action should the project manager take next based on this evidence?
- Compare supplier evidence with the contractual acceptance terms.
- Define evaluation criteria and select suitable contract terms.
- Evaluate bids using the published procurement criteria.
- Negotiate and authorize the contract’s acceptance obligations.
Answer: B
ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.
2.7 Quality evidence and improvement
A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records.
Evidence not yet verified: testable quality requirements and applicable standards.
Evidence not yet verified: a quality plan with preventive controls and test methods.
Verified evidence in the review file: pilot measurements collected using the approved test method.
Verified evidence in the review file: an evidence-based improvement and effectiveness review.
Which action should the project manager take next based on this evidence?
- Plan prevention, inspection, and evidence collection.
- Execute the approved tests and record pilot results.
- Analyze defects, improve the process, and verify the result.
- Confirm quality criteria and mandatory seal standards.
Answer: D
ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.
2.9 Reconciled project reporting
A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis.
Evidence not yet verified: metric definitions, data owners, and a common reporting date.
Verified evidence in the review file: an accessible version-controlled report for decision makers.
Verified evidence in the review file: an interpretation of progress, variance, and forecast implications.
Evidence not yet verified: reconciled data from the authoritative project records.
Which action should the project manager take next based on this evidence?
- Reconcile the report data against authoritative records.
- Agree metric definitions and the reporting cutoff.
- Analyze reconciled progress and explain forecast implications.
- Publish the reviewed report with access and version controls.
Answer: B
ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.
2.4 Capacity and resource commitments
Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization.
Evidence not yet verified: an agreed allocation that respects authorized capacity.
Verified evidence in the review file: a utilization check against the agreed allocation.
Evidence not yet verified: the required skills and estimated effort for each test.
Verified evidence in the review file: confirmed technician and laboratory availability.
Which action should the project manager take next based on this evidence?
- Confirm calendars and competing resource commitments.
- Define test resource requirements and estimate the effort.
- Negotiate a feasible allocation with both project owners.
- Monitor utilization and address new resource conflicts.
Answer: B
ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: the required skills and estimated effort for each test. Allocation needs the required capabilities and workload, not only headcount.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.
2.6 Financial forecasting and control
A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast.
Verified evidence in the review file: a governance review of the forecast and funding variance.
Evidence not yet verified: reconciled actual spending and remaining cost estimates.
Verified evidence in the review file: an authorized baseline and risk-based contingency allocation.
Evidence not yet verified: an estimate of costs and identified financial risks.
Which action should the project manager take next based on this evidence?
- Obtain baseline approval and justify contingency reserves.
- Reconcile actual costs and estimate the remaining work.
- Report the forecast and seek required funding decisions.
- Estimate costs and identify relevant financial uncertainty.
Answer: D
ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an estimate of costs and identified financial risks. Reserves and forecasts require a cost estimate and identified uncertainties.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.
2.8 Schedule dependencies and baselines
A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window.
Verified evidence in the review file: duration estimates and resource calendars.
Evidence not yet verified: an approved schedule baseline coordinated with operations.
Verified evidence in the review file: an analysis of actual progress and schedule variation.
Evidence not yet verified: validated activity dependencies and external operating constraints.
Which action should the project manager take next based on this evidence?
- Coordinate dates with operations and approve the baseline.
- Compare actual progress with the baseline and assess impact.
- Validate dependencies and the permitted shutdown window.
- Estimate durations using team input and resource calendars.
Answer: C
ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: validated activity dependencies and external operating constraints. The schedule logic must respect prerequisites and external constraints.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.
2.10 Acceptance and operational transition
A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses.
Verified evidence in the review file: formal stakeholder acceptance of completed deliverables.
Evidence not yet verified: confirmation of the agreed closure and acceptance criteria.
Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release.
Evidence not yet verified: operations readiness and an accepted support handover.
Which action should the project manager take next based on this evidence?
- Validate operations readiness and complete the support handover.
- Complete financial closure, archive lessons, and release resources.
- Confirm the contractual and project closure criteria.
- Obtain acceptance evidence from the authorized stakeholders.
Answer: C
ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Closure requires known criteria instead of assuming that the planned end date is enough.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.
2.1 Integrated delivery planning
A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials.
Evidence not yet verified: an assessment of requirement stability and delivery constraints.
Verified evidence in the review file: an agreed hybrid approach for installation and iterative software.
Verified evidence in the review file: an integrated dependency, resource, and delivery plan.
Evidence not yet verified: a review of plan gaps and continuing business value.
Which action should the project manager take next based on this evidence?
- Integrate dependencies, resources, and delivery milestones.
- Review the integrated plan for gaps and continued value.
- Agree a hybrid approach with explicit integration points.
- Assess uncertainty, constraints, and required delivery outcomes.
Answer: D
ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.
2.2 Release boundaries and work breakdown
A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records.
Evidence not yet verified: documented requirements and acceptance criteria.
Evidence not yet verified: a completeness review of the scope breakdown.
Verified evidence in the review file: a breakdown into assignable work with traceability.
Verified evidence in the review file: an agreed release boundary and explicit exclusions.
Which action should the project manager take next based on this evidence?
- Break the agreed scope into traceable work packages.
- Check the breakdown for omissions and unauthorized additions.
- Elicit requirements and define testable acceptance criteria.
- Agree included services and exclusions with stakeholders.
Answer: C
ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.
2.3 Incremental benefit realization
A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit.
Verified evidence in the review file: an agreed usable increment and release test.
Evidence not yet verified: benefit measurement after customers use the increment.
Evidence not yet verified: a measurable benefit agreed with the business owner.
Verified evidence in the review file: a ranked comparison of delivery options and dependencies.
Which action should the project manager take next based on this evidence?
- Measure realized benefit and use it to reprioritize work.
- Rank delivery options by benefit, feedback, and dependencies.
- Agree the benefit metric and its accountable business owner.
- Plan a usable increment that tests the prioritized benefit.
Answer: C
ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.
2.5 Supplier selection and acceptance
A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions.
Evidence not yet verified: verified supplier performance and acceptance evidence.
Verified evidence in the review file: an authorized contract with measurable acceptance terms.
Verified evidence in the review file: a documented supplier evaluation under the agreed criteria.
Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk.
Which action should the project manager take next based on this evidence?
- Compare supplier evidence with the contractual acceptance terms.
- Evaluate bids using the published procurement criteria.
- Define evaluation criteria and select suitable contract terms.
- Negotiate and authorize the contract’s acceptance obligations.
Answer: C
ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.
2.7 Quality evidence and improvement
A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records.
Verified evidence in the review file: a quality plan with preventive controls and test methods.
Verified evidence in the review file: pilot measurements collected using the approved test method.
Evidence not yet verified: an evidence-based improvement and effectiveness review.
Evidence not yet verified: testable quality requirements and applicable standards.
Which action should the project manager take next based on this evidence?
- Analyze defects, improve the process, and verify the result.
- Plan prevention, inspection, and evidence collection.
- Execute the approved tests and record pilot results.
- Confirm quality criteria and mandatory seal standards.
Answer: D
ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.
2.9 Reconciled project reporting
A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis.
Verified evidence in the review file: reconciled data from the authoritative project records.
Evidence not yet verified: metric definitions, data owners, and a common reporting date.
Evidence not yet verified: an accessible version-controlled report for decision makers.
Verified evidence in the review file: an interpretation of progress, variance, and forecast implications.
Which action should the project manager take next based on this evidence?
- Publish the reviewed report with access and version controls.
- Agree metric definitions and the reporting cutoff.
- Reconcile the report data against authoritative records.
- Analyze reconciled progress and explain forecast implications.
Answer: B
ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.
2.4 Capacity and resource commitments
Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization.
Verified evidence in the review file: the required skills and estimated effort for each test.
Evidence not yet verified: confirmed technician and laboratory availability.
Evidence not yet verified: an agreed allocation that respects authorized capacity.
Verified evidence in the review file: a utilization check against the agreed allocation.
Which action should the project manager take next based on this evidence?
- Define test resource requirements and estimate the effort.
- Negotiate a feasible allocation with both project owners.
- Monitor utilization and address new resource conflicts.
- Confirm calendars and competing resource commitments.
Answer: D
ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: confirmed technician and laboratory availability. A resource plan can't assume availability across competing projects.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.
2.6 Financial forecasting and control
A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast.
Verified evidence in the review file: an estimate of costs and identified financial risks.
Verified evidence in the review file: a governance review of the forecast and funding variance.
Evidence not yet verified: reconciled actual spending and remaining cost estimates.
Evidence not yet verified: an authorized baseline and risk-based contingency allocation.
Which action should the project manager take next based on this evidence?
- Estimate costs and identify relevant financial uncertainty.
- Reconcile actual costs and estimate the remaining work.
- Report the forecast and seek required funding decisions.
- Obtain baseline approval and justify contingency reserves.
Answer: D
ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Contingency addresses identified risk and needs authorization under the funding rules.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.
2.8 Schedule dependencies and baselines
A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window.
Evidence not yet verified: an approved schedule baseline coordinated with operations.
Verified evidence in the review file: an analysis of actual progress and schedule variation.
Verified evidence in the review file: validated activity dependencies and external operating constraints.
Evidence not yet verified: duration estimates and resource calendars.
Which action should the project manager take next based on this evidence?
- Validate dependencies and the permitted shutdown window.
- Coordinate dates with operations and approve the baseline.
- Compare actual progress with the baseline and assess impact.
- Estimate durations using team input and resource calendars.
Answer: D
ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: duration estimates and resource calendars. Dependency order alone doesn't establish feasible dates without durations and availability.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.
2.10 Acceptance and operational transition
A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses.
Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release.
Evidence not yet verified: operations readiness and an accepted support handover.
Evidence not yet verified: formal stakeholder acceptance of completed deliverables.
Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria.
Which action should the project manager take next based on this evidence?
- Confirm the contractual and project closure criteria.
- Validate operations readiness and complete the support handover.
- Complete financial closure, archive lessons, and release resources.
- Obtain acceptance evidence from the authorized stakeholders.
Answer: D
ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Completion claims need authorized acceptance against the agreed criteria.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.
2.1 Integrated delivery planning
A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials.
Evidence not yet verified: an agreed hybrid approach for installation and iterative software.
Verified evidence in the review file: an integrated dependency, resource, and delivery plan.
Evidence not yet verified: a review of plan gaps and continuing business value.
Verified evidence in the review file: an assessment of requirement stability and delivery constraints.
Which action should the project manager take next based on this evidence?
- Agree a hybrid approach with explicit integration points.
- Integrate dependencies, resources, and delivery milestones.
- Review the integrated plan for gaps and continued value.
- Assess uncertainty, constraints, and required delivery outcomes.
Answer: A
ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an agreed hybrid approach for installation and iterative software. Stable installation milestones and evolving software can use different approaches within one plan.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.
2.2 Release boundaries and work breakdown
A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records.
Evidence not yet verified: an agreed release boundary and explicit exclusions.
Verified evidence in the review file: documented requirements and acceptance criteria.
Evidence not yet verified: a completeness review of the scope breakdown.
Verified evidence in the review file: a breakdown into assignable work with traceability.
Which action should the project manager take next based on this evidence?
- Break the agreed scope into traceable work packages.
- Check the breakdown for omissions and unauthorized additions.
- Elicit requirements and define testable acceptance criteria.
- Agree included services and exclusions with stakeholders.
Answer: D
ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: an agreed release boundary and explicit exclusions. A requirement list alone doesn't settle competing release expectations.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.
2.3 Incremental benefit realization
A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit.
Verified evidence in the review file: a measurable benefit agreed with the business owner.
Evidence not yet verified: a ranked comparison of delivery options and dependencies.
Verified evidence in the review file: an agreed usable increment and release test.
Evidence not yet verified: benefit measurement after customers use the increment.
Which action should the project manager take next based on this evidence?
- Rank delivery options by benefit, feedback, and dependencies.
- Plan a usable increment that tests the prioritized benefit.
- Measure realized benefit and use it to reprioritize work.
- Agree the benefit metric and its accountable business owner.
Answer: A
ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Early delivery helps only when the selected increment can produce the intended value.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.
2.5 Supplier selection and acceptance
A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions.
Verified evidence in the review file: evaluation criteria and an appropriate allocation of contract risk.
Evidence not yet verified: verified supplier performance and acceptance evidence.
Verified evidence in the review file: an authorized contract with measurable acceptance terms.
Evidence not yet verified: a documented supplier evaluation under the agreed criteria.
Which action should the project manager take next based on this evidence?
- Evaluate bids using the published procurement criteria.
- Negotiate and authorize the contract’s acceptance obligations.
- Compare supplier evidence with the contractual acceptance terms.
- Define evaluation criteria and select suitable contract terms.
Answer: A
ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: a documented supplier evaluation under the agreed criteria. Supplier evaluation must apply the agreed criteria instead of favoring a familiar bidder.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.
2.7 Quality evidence and improvement
A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records.
Verified evidence in the review file: pilot measurements collected using the approved test method.
Evidence not yet verified: an evidence-based improvement and effectiveness review.
Verified evidence in the review file: testable quality requirements and applicable standards.
Evidence not yet verified: a quality plan with preventive controls and test methods.
Which action should the project manager take next based on this evidence?
- Analyze defects, improve the process, and verify the result.
- Confirm quality criteria and mandatory seal standards.
- Execute the approved tests and record pilot results.
- Plan prevention, inspection, and evidence collection.
Answer: D
ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: a quality plan with preventive controls and test methods. Quality planning defines how conformity will be achieved and demonstrated.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.
2.9 Reconciled project reporting
A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis.
Evidence not yet verified: an accessible version-controlled report for decision makers.
Verified evidence in the review file: an interpretation of progress, variance, and forecast implications.
Evidence not yet verified: reconciled data from the authoritative project records.
Verified evidence in the review file: metric definitions, data owners, and a common reporting date.
Which action should the project manager take next based on this evidence?
- Publish the reviewed report with access and version controls.
- Agree metric definitions and the reporting cutoff.
- Analyze reconciled progress and explain forecast implications.
- Reconcile the report data against authoritative records.
Answer: D
ECO task 2.9: Reconciled project reporting. Evidence not yet verified: reconciled data from the authoritative project records. Analysis based on unreconciled data can create false variances and misleading conclusions.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.
2.4 Capacity and resource commitments
Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization.
Verified evidence in the review file: confirmed technician and laboratory availability.
Evidence not yet verified: an agreed allocation that respects authorized capacity.
Evidence not yet verified: a utilization check against the agreed allocation.
Verified evidence in the review file: the required skills and estimated effort for each test.
Which action should the project manager take next based on this evidence?
- Negotiate a feasible allocation with both project owners.
- Monitor utilization and address new resource conflicts.
- Define test resource requirements and estimate the effort.
- Confirm calendars and competing resource commitments.
Answer: A
ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: an agreed allocation that respects authorized capacity. Negotiation resolves competing commitments without silently assuming overtime.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.
2.6 Financial forecasting and control
A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast.
Verified evidence in the review file: an authorized baseline and risk-based contingency allocation.
Verified evidence in the review file: an estimate of costs and identified financial risks.
Evidence not yet verified: a governance review of the forecast and funding variance.
Evidence not yet verified: reconciled actual spending and remaining cost estimates.
Which action should the project manager take next based on this evidence?
- Report the forecast and seek required funding decisions.
- Estimate costs and identify relevant financial uncertainty.
- Reconcile actual costs and estimate the remaining work.
- Obtain baseline approval and justify contingency reserves.
Answer: C
ECO task 2.6: Financial forecasting and control. Evidence not yet verified: reconciled actual spending and remaining cost estimates. A forecast needs current actuals and a remaining-work estimate, not the original budget alone.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.
2.8 Schedule dependencies and baselines
A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window.
Verified evidence in the review file: validated activity dependencies and external operating constraints.
Verified evidence in the review file: duration estimates and resource calendars.
Evidence not yet verified: an approved schedule baseline coordinated with operations.
Evidence not yet verified: an analysis of actual progress and schedule variation.
Which action should the project manager take next based on this evidence?
- Validate dependencies and the permitted shutdown window.
- Estimate durations using team input and resource calendars.
- Coordinate dates with operations and approve the baseline.
- Compare actual progress with the baseline and assess impact.
Answer: C
ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: an approved schedule baseline coordinated with operations. A baseline provides an authorized reference for monitoring schedule variance.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.
2.10 Acceptance and operational transition
A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses.
Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria.
Evidence not yet verified: closed contracts, archived lessons, and authorized resource release.
Evidence not yet verified: operations readiness and an accepted support handover.
Verified evidence in the review file: formal stakeholder acceptance of completed deliverables.
Which action should the project manager take next based on this evidence?
- Confirm the contractual and project closure criteria.
- Obtain acceptance evidence from the authorized stakeholders.
- Validate operations readiness and complete the support handover.
- Complete financial closure, archive lessons, and release resources.
Answer: C
ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: operations readiness and an accepted support handover. Acceptance of the product doesn't by itself establish operational readiness.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.
2.1 Integrated delivery planning
A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials.
Evidence not yet verified: an integrated dependency, resource, and delivery plan.
Verified evidence in the review file: a review of plan gaps and continuing business value.
Evidence not yet verified: an assessment of requirement stability and delivery constraints.
Evidence not yet verified: an agreed hybrid approach for installation and iterative software.
Which action should the project manager take next based on this evidence?
- Agree a hybrid approach with explicit integration points.
- Assess uncertainty, constraints, and required delivery outcomes.
- Integrate dependencies, resources, and delivery milestones.
- Review the integrated plan for gaps and continued value.
Answer: B
ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.
2.2 Release boundaries and work breakdown
A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records.
Verified evidence in the review file: a completeness review of the scope breakdown.
Evidence not yet verified: a breakdown into assignable work with traceability.
Evidence not yet verified: an agreed release boundary and explicit exclusions.
Evidence not yet verified: documented requirements and acceptance criteria.
Which action should the project manager take next based on this evidence?
- Elicit requirements and define testable acceptance criteria.
- Agree included services and exclusions with stakeholders.
- Break the agreed scope into traceable work packages.
- Check the breakdown for omissions and unauthorized additions.
Answer: A
ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.
2.3 Incremental benefit realization
A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit.
Evidence not yet verified: a ranked comparison of delivery options and dependencies.
Evidence not yet verified: an agreed usable increment and release test.
Verified evidence in the review file: benefit measurement after customers use the increment.
Evidence not yet verified: a measurable benefit agreed with the business owner.
Which action should the project manager take next based on this evidence?
- Agree the benefit metric and its accountable business owner.
- Plan a usable increment that tests the prioritized benefit.
- Measure realized benefit and use it to reprioritize work.
- Rank delivery options by benefit, feedback, and dependencies.
Answer: A
ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.
2.5 Supplier selection and acceptance
A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions.
Evidence not yet verified: a documented supplier evaluation under the agreed criteria.
Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk.
Verified evidence in the review file: verified supplier performance and acceptance evidence.
Evidence not yet verified: an authorized contract with measurable acceptance terms.
Which action should the project manager take next based on this evidence?
- Negotiate and authorize the contract’s acceptance obligations.
- Define evaluation criteria and select suitable contract terms.
- Compare supplier evidence with the contractual acceptance terms.
- Evaluate bids using the published procurement criteria.
Answer: B
ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.
2.7 Quality evidence and improvement
A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records.
Evidence not yet verified: testable quality requirements and applicable standards.
Evidence not yet verified: a quality plan with preventive controls and test methods.
Evidence not yet verified: pilot measurements collected using the approved test method.
Verified evidence in the review file: an evidence-based improvement and effectiveness review.
Which action should the project manager take next based on this evidence?
- Execute the approved tests and record pilot results.
- Analyze defects, improve the process, and verify the result.
- Plan prevention, inspection, and evidence collection.
- Confirm quality criteria and mandatory seal standards.
Answer: D
ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.
2.9 Reconciled project reporting
A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis.
Evidence not yet verified: metric definitions, data owners, and a common reporting date.
Verified evidence in the review file: an accessible version-controlled report for decision makers.
Evidence not yet verified: an interpretation of progress, variance, and forecast implications.
Evidence not yet verified: reconciled data from the authoritative project records.
Which action should the project manager take next based on this evidence?
- Agree metric definitions and the reporting cutoff.
- Analyze reconciled progress and explain forecast implications.
- Publish the reviewed report with access and version controls.
- Reconcile the report data against authoritative records.
Answer: A
ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.
2.4 Capacity and resource commitments
Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization.
Verified evidence in the review file: an agreed allocation that respects authorized capacity.
Evidence not yet verified: a utilization check against the agreed allocation.
Evidence not yet verified: the required skills and estimated effort for each test.
Evidence not yet verified: confirmed technician and laboratory availability.
Which action should the project manager take next based on this evidence?
- Monitor utilization and address new resource conflicts.
- Confirm calendars and competing resource commitments.
- Negotiate a feasible allocation with both project owners.
- Define test resource requirements and estimate the effort.
Answer: D
ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: the required skills and estimated effort for each test. Allocation needs the required capabilities and workload, not only headcount.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.
2.6 Financial forecasting and control
A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast.
Evidence not yet verified: a governance review of the forecast and funding variance.
Verified evidence in the review file: reconciled actual spending and remaining cost estimates.
Evidence not yet verified: an authorized baseline and risk-based contingency allocation.
Evidence not yet verified: an estimate of costs and identified financial risks.
Which action should the project manager take next based on this evidence?
- Report the forecast and seek required funding decisions.
- Estimate costs and identify relevant financial uncertainty.
- Obtain baseline approval and justify contingency reserves.
- Reconcile actual costs and estimate the remaining work.
Answer: B
ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an estimate of costs and identified financial risks. Reserves and forecasts require a cost estimate and identified uncertainties.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.
2.8 Schedule dependencies and baselines
A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window.
Evidence not yet verified: duration estimates and resource calendars.
Verified evidence in the review file: an approved schedule baseline coordinated with operations.
Evidence not yet verified: an analysis of actual progress and schedule variation.
Evidence not yet verified: validated activity dependencies and external operating constraints.
Which action should the project manager take next based on this evidence?
- Compare actual progress with the baseline and assess impact.
- Validate dependencies and the permitted shutdown window.
- Estimate durations using team input and resource calendars.
- Coordinate dates with operations and approve the baseline.
Answer: B
ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: validated activity dependencies and external operating constraints. The schedule logic must respect prerequisites and external constraints.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.
2.10 Acceptance and operational transition
A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses.
Evidence not yet verified: formal stakeholder acceptance of completed deliverables.
Evidence not yet verified: confirmation of the agreed closure and acceptance criteria.
Evidence not yet verified: closed contracts, archived lessons, and authorized resource release.
Verified evidence in the review file: operations readiness and an accepted support handover.
Which action should the project manager take next based on this evidence?
- Confirm the contractual and project closure criteria.
- Complete financial closure, archive lessons, and release resources.
- Obtain acceptance evidence from the authorized stakeholders.
- Validate operations readiness and complete the support handover.
Answer: A
ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Closure requires known criteria instead of assuming that the planned end date is enough.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.
2.1 Integrated delivery planning
A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials.
Evidence not yet verified: an assessment of requirement stability and delivery constraints.
Verified evidence in the review file: an agreed hybrid approach for installation and iterative software.
Evidence not yet verified: an integrated dependency, resource, and delivery plan.
Evidence not yet verified: a review of plan gaps and continuing business value.
Which action should the project manager take next based on this evidence?
- Agree a hybrid approach with explicit integration points.
- Integrate dependencies, resources, and delivery milestones.
- Assess uncertainty, constraints, and required delivery outcomes.
- Review the integrated plan for gaps and continued value.
Answer: C
ECO task 2.1: Integrated delivery planning. Evidence not yet verified: an assessment of requirement stability and delivery constraints. The development approach must fit the work’s uncertainty and constraints.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.1.
2.2 Release boundaries and work breakdown
A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records.
Evidence not yet verified: documented requirements and acceptance criteria.
Evidence not yet verified: a completeness review of the scope breakdown.
Evidence not yet verified: a breakdown into assignable work with traceability.
Verified evidence in the review file: an agreed release boundary and explicit exclusions.
Which action should the project manager take next based on this evidence?
- Elicit requirements and define testable acceptance criteria.
- Agree included services and exclusions with stakeholders.
- Break the agreed scope into traceable work packages.
- Check the breakdown for omissions and unauthorized additions.
Answer: A
ECO task 2.2: Release boundaries and work breakdown. Evidence not yet verified: documented requirements and acceptance criteria. The scope boundary needs evidence about required deliverables and their acceptance.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.2.
2.3 Incremental benefit realization
A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit.
Evidence not yet verified: an agreed usable increment and release test.
Evidence not yet verified: benefit measurement after customers use the increment.
Evidence not yet verified: a measurable benefit agreed with the business owner.
Verified evidence in the review file: a ranked comparison of delivery options and dependencies.
Which action should the project manager take next based on this evidence?
- Rank delivery options by benefit, feedback, and dependencies.
- Plan a usable increment that tests the prioritized benefit.
- Agree the benefit metric and its accountable business owner.
- Measure realized benefit and use it to reprioritize work.
Answer: C
ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.
2.5 Supplier selection and acceptance
A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions.
Evidence not yet verified: verified supplier performance and acceptance evidence.
Evidence not yet verified: an authorized contract with measurable acceptance terms.
Verified evidence in the review file: a documented supplier evaluation under the agreed criteria.
Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk.
Which action should the project manager take next based on this evidence?
- Evaluate bids using the published procurement criteria.
- Negotiate and authorize the contract’s acceptance obligations.
- Compare supplier evidence with the contractual acceptance terms.
- Define evaluation criteria and select suitable contract terms.
Answer: D
ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.
2.7 Quality evidence and improvement
A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records.
Verified evidence in the review file: a quality plan with preventive controls and test methods.
Evidence not yet verified: pilot measurements collected using the approved test method.
Evidence not yet verified: an evidence-based improvement and effectiveness review.
Evidence not yet verified: testable quality requirements and applicable standards.
Which action should the project manager take next based on this evidence?
- Execute the approved tests and record pilot results.
- Analyze defects, improve the process, and verify the result.
- Confirm quality criteria and mandatory seal standards.
- Plan prevention, inspection, and evidence collection.
Answer: C
ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.
2.9 Reconciled project reporting
A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis.
Verified evidence in the review file: reconciled data from the authoritative project records.
Evidence not yet verified: metric definitions, data owners, and a common reporting date.
Evidence not yet verified: an accessible version-controlled report for decision makers.
Evidence not yet verified: an interpretation of progress, variance, and forecast implications.
Which action should the project manager take next based on this evidence?
- Analyze reconciled progress and explain forecast implications.
- Publish the reviewed report with access and version controls.
- Agree metric definitions and the reporting cutoff.
- Reconcile the report data against authoritative records.
Answer: C
ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.
2.4 Capacity and resource commitments
Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization.
Verified evidence in the review file: the required skills and estimated effort for each test.
Evidence not yet verified: confirmed technician and laboratory availability.
Evidence not yet verified: an agreed allocation that respects authorized capacity.
Evidence not yet verified: a utilization check against the agreed allocation.
Which action should the project manager take next based on this evidence?
- Negotiate a feasible allocation with both project owners.
- Confirm calendars and competing resource commitments.
- Monitor utilization and address new resource conflicts.
- Define test resource requirements and estimate the effort.
Answer: B
ECO task 2.4: Capacity and resource commitments. Evidence not yet verified: confirmed technician and laboratory availability. A resource plan can't assume availability across competing projects.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.4.
2.6 Financial forecasting and control
A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast.
Verified evidence in the review file: an estimate of costs and identified financial risks.
Evidence not yet verified: a governance review of the forecast and funding variance.
Evidence not yet verified: reconciled actual spending and remaining cost estimates.
Evidence not yet verified: an authorized baseline and risk-based contingency allocation.
Which action should the project manager take next based on this evidence?
- Obtain baseline approval and justify contingency reserves.
- Reconcile actual costs and estimate the remaining work.
- Report the forecast and seek required funding decisions.
- Estimate costs and identify relevant financial uncertainty.
Answer: A
ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Contingency addresses identified risk and needs authorization under the funding rules.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.
2.8 Schedule dependencies and baselines
A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window.
Evidence not yet verified: an approved schedule baseline coordinated with operations.
Evidence not yet verified: an analysis of actual progress and schedule variation.
Verified evidence in the review file: validated activity dependencies and external operating constraints.
Evidence not yet verified: duration estimates and resource calendars.
Which action should the project manager take next based on this evidence?
- Compare actual progress with the baseline and assess impact.
- Estimate durations using team input and resource calendars.
- Validate dependencies and the permitted shutdown window.
- Coordinate dates with operations and approve the baseline.
Answer: B
ECO task 2.8: Schedule dependencies and baselines. Evidence not yet verified: duration estimates and resource calendars. Dependency order alone doesn't establish feasible dates without durations and availability.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.8.
2.10 Acceptance and operational transition
A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses.
Evidence not yet verified: closed contracts, archived lessons, and authorized resource release.
Evidence not yet verified: operations readiness and an accepted support handover.
Evidence not yet verified: formal stakeholder acceptance of completed deliverables.
Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria.
Which action should the project manager take next based on this evidence?
- Complete financial closure, archive lessons, and release resources.
- Confirm the contractual and project closure criteria.
- Obtain acceptance evidence from the authorized stakeholders.
- Validate operations readiness and complete the support handover.
Answer: C
ECO task 2.10: Acceptance and operational transition. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Completion claims need authorized acceptance against the agreed criteria.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.10.
2.3 Incremental benefit realization
A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit.
Evidence not yet verified: a ranked comparison of delivery options and dependencies.
Evidence not yet verified: an agreed usable increment and release test.
Evidence not yet verified: benefit measurement after customers use the increment.
Evidence not yet verified: a measurable benefit agreed with the business owner.
Which action should the project manager take next based on this evidence?
- Measure realized benefit and use it to reprioritize work.
- Rank delivery options by benefit, feedback, and dependencies.
- Plan a usable increment that tests the prioritized benefit.
- Agree the benefit metric and its accountable business owner.
Answer: D
ECO task 2.3: Incremental benefit realization. Evidence not yet verified: a measurable benefit agreed with the business owner. Value must be defined before delivery options can be compared against it.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.3.
2.5 Supplier selection and acceptance
A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions.
Evidence not yet verified: a documented supplier evaluation under the agreed criteria.
Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk.
Evidence not yet verified: verified supplier performance and acceptance evidence.
Evidence not yet verified: an authorized contract with measurable acceptance terms.
Which action should the project manager take next based on this evidence?
- Compare supplier evidence with the contractual acceptance terms.
- Evaluate bids using the published procurement criteria.
- Negotiate and authorize the contract’s acceptance obligations.
- Define evaluation criteria and select suitable contract terms.
Answer: D
ECO task 2.5: Supplier selection and acceptance. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Procurement criteria and risk allocation need definition before supplier selection.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.5.
2.7 Quality evidence and improvement
A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records.
Evidence not yet verified: testable quality requirements and applicable standards.
Evidence not yet verified: a quality plan with preventive controls and test methods.
Evidence not yet verified: pilot measurements collected using the approved test method.
Evidence not yet verified: an evidence-based improvement and effectiveness review.
Which action should the project manager take next based on this evidence?
- Plan prevention, inspection, and evidence collection.
- Execute the approved tests and record pilot results.
- Confirm quality criteria and mandatory seal standards.
- Analyze defects, improve the process, and verify the result.
Answer: C
ECO task 2.7: Quality evidence and improvement. Evidence not yet verified: testable quality requirements and applicable standards. The team must know the required standard before selecting its quality controls.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.7.
2.9 Reconciled project reporting
A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis.
Evidence not yet verified: metric definitions, data owners, and a common reporting date.
Evidence not yet verified: an accessible version-controlled report for decision makers.
Evidence not yet verified: an interpretation of progress, variance, and forecast implications.
Evidence not yet verified: reconciled data from the authoritative project records.
Which action should the project manager take next based on this evidence?
- Reconcile the report data against authoritative records.
- Agree metric definitions and the reporting cutoff.
- Analyze reconciled progress and explain forecast implications.
- Publish the reviewed report with access and version controls.
Answer: B
ECO task 2.9: Reconciled project reporting. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Status comparisons require compatible definitions and the same reporting basis.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.9.
3.1 Decision authority and oversight
A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority.
Evidence not yet verified: the applicable organizational policies and authority constraints.
Verified evidence in the review file: agreed decision rights and escalation thresholds.
Verified evidence in the review file: approved success measures and governance reporting arrangements.
Verified evidence in the review file: a check that teams follow the approved authority model.
Which action should the project manager take next based on this evidence?
- Agree decision rights, escalation paths, and thresholds.
- Review each partner’s mandatory governance requirements.
- Approve success measures and the governance reporting cycle.
- Check decision records against the approved authority model.
Answer: B
ECO task 3.1: Decision authority and oversight. Evidence not yet verified: the applicable organizational policies and authority constraints. Project rules must respect existing authority, ethics, and mandatory policies.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.
3.3 Authorized change execution
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation.
Evidence not yet verified: a recorded change request with a clear business rationale.
Verified evidence in the review file: implementation records and updated baselines for the approved change.
Verified evidence in the review file: a documented decision by the authorized change authority.
Verified evidence in the review file: an integrated impact analysis of the requested feature.
Which action should the project manager take next based on this evidence?
- Assess scope, cost, schedule, risk, and benefit impacts.
- Submit the analysis to the authorized change authority.
- Record the request, its rationale, and requested outcome.
- Implement the approved change and update controlled documents.
Answer: C
ECO task 3.3: Authorized change execution. Evidence not yet verified: a recorded change request with a clear business rationale. A controlled change needs a traceable request before analysis and decision.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.
3.4 Resolving realized blockers
A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue.
Verified evidence in the review file: an authorized workaround or corrective intervention.
Verified evidence in the review file: a retest proving that testing can resume safely.
Evidence not yet verified: a current issue record and confirmed impact.
Verified evidence in the review file: an agreed priority, resolution owner, and escalation path.
Which action should the project manager take next based on this evidence?
- Record the realized issue and assess its current impact.
- Assign an issue owner and prioritize the required intervention.
- Coordinate and apply the authorized corrective intervention.
- Retest the blocked workflow before closing the issue.
Answer: A
ECO task 3.4: Resolving realized blockers. Evidence not yet verified: a current issue record and confirmed impact. An event that has occurred requires issue management, even if it began as a risk.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.
3.5 Uncertainty and response monitoring
A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite.
Verified evidence in the review file: a monitoring check of triggers and residual exposure.
Verified evidence in the review file: an approved response, trigger, and contingency owner.
Verified evidence in the review file: an assessed probability, impact, and risk priority.
Evidence not yet verified: a cause-event-effect risk statement and an owner.
Which action should the project manager take next based on this evidence?
- Analyze probability and impact against the agreed risk criteria.
- Agree the risk response, trigger, and contingency responsibility.
- Record the uncertain event, causes, effects, and risk owner.
- Monitor triggers, residual risk, and response effectiveness.
Answer: C
ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: a cause-event-effect risk statement and an owner. A useful risk record distinguishes uncertainty from an issue that has already occurred.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.
3.6 Testing and reusing improvements
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement.
Verified evidence in the review file: a small improvement experiment and an outcome measure.
Verified evidence in the review file: results from the improvement experiment.
Verified evidence in the review file: updated organizational standards and reusable lessons.
Evidence not yet verified: evidence of the recurring defect and its root cause.
Which action should the project manager take next based on this evidence?
- Run the experiment and compare outcomes with the baseline.
- Update the standard process and publish the validated lesson.
- Design a limited experiment with a measurable outcome.
- Analyze rework evidence and identify the root cause.
Answer: D
ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.
3.7 Readiness and organizational adoption
A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence.
Verified evidence in the review file: a role-impact assessment and agreed transition support.
Evidence not yet verified: an assessment of culture, concerns, and change readiness.
Verified evidence in the review file: adoption evidence and adjustments to transition support.
Verified evidence in the review file: a supported pilot with trained users and escalation access.
Which action should the project manager take next based on this evidence?
- Run a supported pilot before the wider transition.
- Measure adoption and adjust support using user feedback.
- Map role impacts and agree training and transition support.
- Assess culture and discuss concerns with affected departments.
Answer: D
ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Resistance can reflect real impacts that need understanding before a transition is planned.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.
3.8 Responding to external change
A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records.
Evidence not yet verified: verified details, applicability, and the effective date of the rule.
Verified evidence in the review file: an assessment of impacts on value, scope, and delivery.
Verified evidence in the review file: an authorized response and updated scope or backlog.
Verified evidence in the review file: a continuing scan for further external changes.
Which action should the project manager take next based on this evidence?
- Obtain the required decision and update the delivery plan.
- Verify the external change with authoritative sources.
- Assign ongoing monitoring and review further impacts.
- Assess and prioritize the change’s project impacts.
Answer: B
ECO task 3.8: Responding to external change. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Unverified announcements can't provide a reliable basis for changing project commitments.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.
3.2 Obligations and conformity evidence
A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties.
Verified evidence in the review file: a register of applicable legal and contractual obligations.
Verified evidence in the review file: evidence that implemented controls satisfy the obligations.
Verified evidence in the review file: assigned compliance controls and required approvals.
Evidence not yet verified: a gap assessment and consequences of noncompliance.
Which action should the project manager take next based on this evidence?
- Assess current gaps, threats, and consequences of noncompliance.
- Assign controls, owners, and required approval checkpoints.
- Verify compliance evidence before authorizing the release.
- Confirm and classify the applicable compliance obligations.
Answer: A
ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: a gap assessment and consequences of noncompliance. Controls should respond to assessed compliance gaps rather than assumed coverage.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.
3.1 Decision authority and oversight
A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority.
Evidence not yet verified: approved success measures and governance reporting arrangements.
Verified evidence in the review file: a check that teams follow the approved authority model.
Verified evidence in the review file: the applicable organizational policies and authority constraints.
Verified evidence in the review file: agreed decision rights and escalation thresholds.
Which action should the project manager take next based on this evidence?
- Check decision records against the approved authority model.
- Review each partner’s mandatory governance requirements.
- Agree decision rights, escalation paths, and thresholds.
- Approve success measures and the governance reporting cycle.
Answer: D
ECO task 3.1: Decision authority and oversight. Evidence not yet verified: approved success measures and governance reporting arrangements. Governance needs a defined basis for judging outcomes and receiving decisions.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.
3.3 Authorized change execution
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation.
Verified evidence in the review file: implementation records and updated baselines for the approved change.
Evidence not yet verified: a documented decision by the authorized change authority.
Verified evidence in the review file: an integrated impact analysis of the requested feature.
Verified evidence in the review file: a recorded change request with a clear business rationale.
Which action should the project manager take next based on this evidence?
- Submit the analysis to the authorized change authority.
- Implement the approved change and update controlled documents.
- Record the request, its rationale, and requested outcome.
- Assess scope, cost, schedule, risk, and benefit impacts.
Answer: A
ECO task 3.3: Authorized change execution. Evidence not yet verified: a documented decision by the authorized change authority. A customer request or favorable analysis doesn't replace the required approval.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.
3.4 Resolving realized blockers
A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue.
Verified evidence in the review file: an agreed priority, resolution owner, and escalation path.
Evidence not yet verified: an authorized workaround or corrective intervention.
Verified evidence in the review file: a retest proving that testing can resume safely.
Verified evidence in the review file: a current issue record and confirmed impact.
Which action should the project manager take next based on this evidence?
- Retest the blocked workflow before closing the issue.
- Record the realized issue and assess its current impact.
- Coordinate and apply the authorized corrective intervention.
- Assign an issue owner and prioritize the required intervention.
Answer: C
ECO task 3.4: Resolving realized blockers. Evidence not yet verified: an authorized workaround or corrective intervention. The assigned owner needs an implemented intervention rather than only an issue entry.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.
3.5 Uncertainty and response monitoring
A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite.
Verified evidence in the review file: an assessed probability, impact, and risk priority.
Verified evidence in the review file: a cause-event-effect risk statement and an owner.
Verified evidence in the review file: a monitoring check of triggers and residual exposure.
Evidence not yet verified: an approved response, trigger, and contingency owner.
Which action should the project manager take next based on this evidence?
- Monitor triggers, residual risk, and response effectiveness.
- Record the uncertain event, causes, effects, and risk owner.
- Analyze probability and impact against the agreed risk criteria.
- Agree the risk response, trigger, and contingency responsibility.
Answer: D
ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: an approved response, trigger, and contingency owner. A response needs an owner and an activation condition to be executable.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.
3.6 Testing and reusing improvements
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement.
Verified evidence in the review file: evidence of the recurring defect and its root cause.
Verified evidence in the review file: a small improvement experiment and an outcome measure.
Evidence not yet verified: results from the improvement experiment.
Verified evidence in the review file: updated organizational standards and reusable lessons.
Which action should the project manager take next based on this evidence?
- Run the experiment and compare outcomes with the baseline.
- Analyze rework evidence and identify the root cause.
- Design a limited experiment with a measurable outcome.
- Update the standard process and publish the validated lesson.
Answer: A
ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: results from the improvement experiment. An attractive proposal still needs observed results before it becomes a standard.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.
3.7 Readiness and organizational adoption
A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence.
Verified evidence in the review file: an assessment of culture, concerns, and change readiness.
Verified evidence in the review file: adoption evidence and adjustments to transition support.
Evidence not yet verified: a supported pilot with trained users and escalation access.
Verified evidence in the review file: a role-impact assessment and agreed transition support.
Which action should the project manager take next based on this evidence?
- Run a supported pilot before the wider transition.
- Assess culture and discuss concerns with affected departments.
- Map role impacts and agree training and transition support.
- Measure adoption and adjust support using user feedback.
Answer: A
ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: a supported pilot with trained users and escalation access. A supported pilot exposes adoption problems while the rollout remains limited.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.
3.8 Responding to external change
A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records.
Evidence not yet verified: an authorized response and updated scope or backlog.
Verified evidence in the review file: a continuing scan for further external changes.
Verified evidence in the review file: verified details, applicability, and the effective date of the rule.
Verified evidence in the review file: an assessment of impacts on value, scope, and delivery.
Which action should the project manager take next based on this evidence?
- Verify the external change with authoritative sources.
- Assess and prioritize the change’s project impacts.
- Obtain the required decision and update the delivery plan.
- Assign ongoing monitoring and review further impacts.
Answer: C
ECO task 3.8: Responding to external change. Evidence not yet verified: an authorized response and updated scope or backlog. External pressure doesn't remove internal authorization and planning obligations.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.
3.2 Obligations and conformity evidence
A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties.
Evidence not yet verified: evidence that implemented controls satisfy the obligations.
Verified evidence in the review file: assigned compliance controls and required approvals.
Verified evidence in the review file: a gap assessment and consequences of noncompliance.
Verified evidence in the review file: a register of applicable legal and contractual obligations.
Which action should the project manager take next based on this evidence?
- Verify compliance evidence before authorizing the release.
- Confirm and classify the applicable compliance obligations.
- Assess current gaps, threats, and consequences of noncompliance.
- Assign controls, owners, and required approval checkpoints.
Answer: A
ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Having a control plan is different from demonstrating that the obligations are satisfied.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.
3.1 Decision authority and oversight
A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority.
Evidence not yet verified: agreed decision rights and escalation thresholds.
Verified evidence in the review file: approved success measures and governance reporting arrangements.
Verified evidence in the review file: a check that teams follow the approved authority model.
Evidence not yet verified: the applicable organizational policies and authority constraints.
Which action should the project manager take next based on this evidence?
- Approve success measures and the governance reporting cycle.
- Check decision records against the approved authority model.
- Agree decision rights, escalation paths, and thresholds.
- Review each partner’s mandatory governance requirements.
Answer: D
ECO task 3.1: Decision authority and oversight. Evidence not yet verified: the applicable organizational policies and authority constraints. Project rules must respect existing authority, ethics, and mandatory policies.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.
3.3 Authorized change execution
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation.
Evidence not yet verified: an integrated impact analysis of the requested feature.
Evidence not yet verified: a recorded change request with a clear business rationale.
Verified evidence in the review file: implementation records and updated baselines for the approved change.
Verified evidence in the review file: a documented decision by the authorized change authority.
Which action should the project manager take next based on this evidence?
- Submit the analysis to the authorized change authority.
- Implement the approved change and update controlled documents.
- Assess scope, cost, schedule, risk, and benefit impacts.
- Record the request, its rationale, and requested outcome.
Answer: D
ECO task 3.3: Authorized change execution. Evidence not yet verified: a recorded change request with a clear business rationale. A controlled change needs a traceable request before analysis and decision.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.
3.4 Resolving realized blockers
A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue.
Evidence not yet verified: a current issue record and confirmed impact.
Evidence not yet verified: an agreed priority, resolution owner, and escalation path.
Verified evidence in the review file: an authorized workaround or corrective intervention.
Verified evidence in the review file: a retest proving that testing can resume safely.
Which action should the project manager take next based on this evidence?
- Record the realized issue and assess its current impact.
- Coordinate and apply the authorized corrective intervention.
- Retest the blocked workflow before closing the issue.
- Assign an issue owner and prioritize the required intervention.
Answer: A
ECO task 3.4: Resolving realized blockers. Evidence not yet verified: a current issue record and confirmed impact. An event that has occurred requires issue management, even if it began as a risk.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.
3.5 Uncertainty and response monitoring
A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite.
Evidence not yet verified: a cause-event-effect risk statement and an owner.
Verified evidence in the review file: a monitoring check of triggers and residual exposure.
Verified evidence in the review file: an approved response, trigger, and contingency owner.
Evidence not yet verified: an assessed probability, impact, and risk priority.
Which action should the project manager take next based on this evidence?
- Agree the risk response, trigger, and contingency responsibility.
- Monitor triggers, residual risk, and response effectiveness.
- Analyze probability and impact against the agreed risk criteria.
- Record the uncertain event, causes, effects, and risk owner.
Answer: D
ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: a cause-event-effect risk statement and an owner. A useful risk record distinguishes uncertainty from an issue that has already occurred.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.
3.6 Testing and reusing improvements
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement.
Verified evidence in the review file: results from the improvement experiment.
Verified evidence in the review file: updated organizational standards and reusable lessons.
Evidence not yet verified: evidence of the recurring defect and its root cause.
Evidence not yet verified: a small improvement experiment and an outcome measure.
Which action should the project manager take next based on this evidence?
- Update the standard process and publish the validated lesson.
- Design a limited experiment with a measurable outcome.
- Analyze rework evidence and identify the root cause.
- Run the experiment and compare outcomes with the baseline.
Answer: C
ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.
3.7 Readiness and organizational adoption
A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence.
Verified evidence in the review file: adoption evidence and adjustments to transition support.
Verified evidence in the review file: a supported pilot with trained users and escalation access.
Evidence not yet verified: a role-impact assessment and agreed transition support.
Evidence not yet verified: an assessment of culture, concerns, and change readiness.
Which action should the project manager take next based on this evidence?
- Assess culture and discuss concerns with affected departments.
- Measure adoption and adjust support using user feedback.
- Map role impacts and agree training and transition support.
- Run a supported pilot before the wider transition.
Answer: A
ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Resistance can reflect real impacts that need understanding before a transition is planned.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.
3.8 Responding to external change
A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records.
Evidence not yet verified: an assessment of impacts on value, scope, and delivery.
Verified evidence in the review file: an authorized response and updated scope or backlog.
Verified evidence in the review file: a continuing scan for further external changes.
Evidence not yet verified: verified details, applicability, and the effective date of the rule.
Which action should the project manager take next based on this evidence?
- Assign ongoing monitoring and review further impacts.
- Verify the external change with authoritative sources.
- Assess and prioritize the change’s project impacts.
- Obtain the required decision and update the delivery plan.
Answer: B
ECO task 3.8: Responding to external change. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Unverified announcements can't provide a reliable basis for changing project commitments.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.
3.2 Obligations and conformity evidence
A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties.
Verified evidence in the review file: a gap assessment and consequences of noncompliance.
Evidence not yet verified: a register of applicable legal and contractual obligations.
Verified evidence in the review file: evidence that implemented controls satisfy the obligations.
Evidence not yet verified: assigned compliance controls and required approvals.
Which action should the project manager take next based on this evidence?
- Verify compliance evidence before authorizing the release.
- Confirm and classify the applicable compliance obligations.
- Assess current gaps, threats, and consequences of noncompliance.
- Assign controls, owners, and required approval checkpoints.
Answer: B
ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: a register of applicable legal and contractual obligations. Compliance planning begins with the requirements that apply to the project.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.
3.1 Decision authority and oversight
A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority.
Evidence not yet verified: the applicable organizational policies and authority constraints.
Verified evidence in the review file: agreed decision rights and escalation thresholds.
Verified evidence in the review file: approved success measures and governance reporting arrangements.
Evidence not yet verified: a check that teams follow the approved authority model.
Which action should the project manager take next based on this evidence?
- Agree decision rights, escalation paths, and thresholds.
- Approve success measures and the governance reporting cycle.
- Review each partner’s mandatory governance requirements.
- Check decision records against the approved authority model.
Answer: C
ECO task 3.1: Decision authority and oversight. Evidence not yet verified: the applicable organizational policies and authority constraints. Project rules must respect existing authority, ethics, and mandatory policies.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.
3.3 Authorized change execution
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation.
Evidence not yet verified: a recorded change request with a clear business rationale.
Evidence not yet verified: implementation records and updated baselines for the approved change.
Verified evidence in the review file: a documented decision by the authorized change authority.
Verified evidence in the review file: an integrated impact analysis of the requested feature.
Which action should the project manager take next based on this evidence?
- Record the request, its rationale, and requested outcome.
- Assess scope, cost, schedule, risk, and benefit impacts.
- Submit the analysis to the authorized change authority.
- Implement the approved change and update controlled documents.
Answer: A
ECO task 3.3: Authorized change execution. Evidence not yet verified: a recorded change request with a clear business rationale. A controlled change needs a traceable request before analysis and decision.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.
3.4 Resolving realized blockers
A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue.
Verified evidence in the review file: an authorized workaround or corrective intervention.
Evidence not yet verified: a retest proving that testing can resume safely.
Evidence not yet verified: a current issue record and confirmed impact.
Verified evidence in the review file: an agreed priority, resolution owner, and escalation path.
Which action should the project manager take next based on this evidence?
- Record the realized issue and assess its current impact.
- Assign an issue owner and prioritize the required intervention.
- Coordinate and apply the authorized corrective intervention.
- Retest the blocked workflow before closing the issue.
Answer: A
ECO task 3.4: Resolving realized blockers. Evidence not yet verified: a current issue record and confirmed impact. An event that has occurred requires issue management, even if it began as a risk.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.
3.5 Uncertainty and response monitoring
A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite.
Evidence not yet verified: a monitoring check of triggers and residual exposure.
Verified evidence in the review file: an approved response, trigger, and contingency owner.
Verified evidence in the review file: an assessed probability, impact, and risk priority.
Evidence not yet verified: a cause-event-effect risk statement and an owner.
Which action should the project manager take next based on this evidence?
- Analyze probability and impact against the agreed risk criteria.
- Agree the risk response, trigger, and contingency responsibility.
- Record the uncertain event, causes, effects, and risk owner.
- Monitor triggers, residual risk, and response effectiveness.
Answer: C
ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: a cause-event-effect risk statement and an owner. A useful risk record distinguishes uncertainty from an issue that has already occurred.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.
3.6 Testing and reusing improvements
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement.
Verified evidence in the review file: a small improvement experiment and an outcome measure.
Verified evidence in the review file: results from the improvement experiment.
Evidence not yet verified: updated organizational standards and reusable lessons.
Evidence not yet verified: evidence of the recurring defect and its root cause.
Which action should the project manager take next based on this evidence?
- Run the experiment and compare outcomes with the baseline.
- Update the standard process and publish the validated lesson.
- Design a limited experiment with a measurable outcome.
- Analyze rework evidence and identify the root cause.
Answer: D
ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.
3.7 Readiness and organizational adoption
A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence.
Verified evidence in the review file: a role-impact assessment and agreed transition support.
Evidence not yet verified: an assessment of culture, concerns, and change readiness.
Evidence not yet verified: adoption evidence and adjustments to transition support.
Verified evidence in the review file: a supported pilot with trained users and escalation access.
Which action should the project manager take next based on this evidence?
- Run a supported pilot before the wider transition.
- Measure adoption and adjust support using user feedback.
- Map role impacts and agree training and transition support.
- Assess culture and discuss concerns with affected departments.
Answer: D
ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Resistance can reflect real impacts that need understanding before a transition is planned.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.
3.8 Responding to external change
A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records.
Evidence not yet verified: verified details, applicability, and the effective date of the rule.
Verified evidence in the review file: an assessment of impacts on value, scope, and delivery.
Verified evidence in the review file: an authorized response and updated scope or backlog.
Evidence not yet verified: a continuing scan for further external changes.
Which action should the project manager take next based on this evidence?
- Obtain the required decision and update the delivery plan.
- Assign ongoing monitoring and review further impacts.
- Verify the external change with authoritative sources.
- Assess and prioritize the change’s project impacts.
Answer: C
ECO task 3.8: Responding to external change. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Unverified announcements can't provide a reliable basis for changing project commitments.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.
3.2 Obligations and conformity evidence
A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties.
Verified evidence in the review file: a register of applicable legal and contractual obligations.
Verified evidence in the review file: evidence that implemented controls satisfy the obligations.
Evidence not yet verified: assigned compliance controls and required approvals.
Evidence not yet verified: a gap assessment and consequences of noncompliance.
Which action should the project manager take next based on this evidence?
- Assign controls, owners, and required approval checkpoints.
- Assess current gaps, threats, and consequences of noncompliance.
- Verify compliance evidence before authorizing the release.
- Confirm and classify the applicable compliance obligations.
Answer: B
ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: a gap assessment and consequences of noncompliance. Controls should respond to assessed compliance gaps rather than assumed coverage.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.
3.1 Decision authority and oversight
A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority.
Verified evidence in the review file: approved success measures and governance reporting arrangements.
Evidence not yet verified: a check that teams follow the approved authority model.
Verified evidence in the review file: the applicable organizational policies and authority constraints.
Evidence not yet verified: agreed decision rights and escalation thresholds.
Which action should the project manager take next based on this evidence?
- Agree decision rights, escalation paths, and thresholds.
- Check decision records against the approved authority model.
- Review each partner’s mandatory governance requirements.
- Approve success measures and the governance reporting cycle.
Answer: A
ECO task 3.1: Decision authority and oversight. Evidence not yet verified: agreed decision rights and escalation thresholds. Explicit thresholds prevent decisions being made by people without the required authority.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.
3.3 Authorized change execution
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation.
Evidence not yet verified: implementation records and updated baselines for the approved change.
Verified evidence in the review file: a documented decision by the authorized change authority.
Evidence not yet verified: an integrated impact analysis of the requested feature.
Verified evidence in the review file: a recorded change request with a clear business rationale.
Which action should the project manager take next based on this evidence?
- Implement the approved change and update controlled documents.
- Record the request, its rationale, and requested outcome.
- Assess scope, cost, schedule, risk, and benefit impacts.
- Submit the analysis to the authorized change authority.
Answer: C
ECO task 3.3: Authorized change execution. Evidence not yet verified: an integrated impact analysis of the requested feature. Approval requires the combined effects of a change, not one favorable dimension.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.
3.4 Resolving realized blockers
A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue.
Evidence not yet verified: an agreed priority, resolution owner, and escalation path.
Verified evidence in the review file: an authorized workaround or corrective intervention.
Evidence not yet verified: a retest proving that testing can resume safely.
Verified evidence in the review file: a current issue record and confirmed impact.
Which action should the project manager take next based on this evidence?
- Retest the blocked workflow before closing the issue.
- Record the realized issue and assess its current impact.
- Assign an issue owner and prioritize the required intervention.
- Coordinate and apply the authorized corrective intervention.
Answer: C
ECO task 3.4: Resolving realized blockers. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Impact determines urgency and the authority needed to remove the blocker.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.
3.5 Uncertainty and response monitoring
A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite.
Evidence not yet verified: an assessed probability, impact, and risk priority.
Verified evidence in the review file: a cause-event-effect risk statement and an owner.
Evidence not yet verified: a monitoring check of triggers and residual exposure.
Verified evidence in the review file: an approved response, trigger, and contingency owner.
Which action should the project manager take next based on this evidence?
- Monitor triggers, residual risk, and response effectiveness.
- Record the uncertain event, causes, effects, and risk owner.
- Analyze probability and impact against the agreed risk criteria.
- Agree the risk response, trigger, and contingency responsibility.
Answer: C
ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: an assessed probability, impact, and risk priority. The response should reflect assessed exposure instead of treating every risk equally.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.
3.6 Testing and reusing improvements
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement.
Verified evidence in the review file: evidence of the recurring defect and its root cause.
Evidence not yet verified: a small improvement experiment and an outcome measure.
Verified evidence in the review file: results from the improvement experiment.
Evidence not yet verified: updated organizational standards and reusable lessons.
Which action should the project manager take next based on this evidence?
- Analyze rework evidence and identify the root cause.
- Run the experiment and compare outcomes with the baseline.
- Update the standard process and publish the validated lesson.
- Design a limited experiment with a measurable outcome.
Answer: D
ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: a small improvement experiment and an outcome measure. A controlled trial tests the proposed improvement before organization-wide adoption.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.
3.7 Readiness and organizational adoption
A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence.
Verified evidence in the review file: an assessment of culture, concerns, and change readiness.
Evidence not yet verified: adoption evidence and adjustments to transition support.
Verified evidence in the review file: a supported pilot with trained users and escalation access.
Evidence not yet verified: a role-impact assessment and agreed transition support.
Which action should the project manager take next based on this evidence?
- Map role impacts and agree training and transition support.
- Assess culture and discuss concerns with affected departments.
- Run a supported pilot before the wider transition.
- Measure adoption and adjust support using user feedback.
Answer: A
ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: a role-impact assessment and agreed transition support. Support must address changed work and responsibilities rather than only announcing the platform.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.
3.8 Responding to external change
A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records.
Verified evidence in the review file: an authorized response and updated scope or backlog.
Evidence not yet verified: a continuing scan for further external changes.
Verified evidence in the review file: verified details, applicability, and the effective date of the rule.
Evidence not yet verified: an assessment of impacts on value, scope, and delivery.
Which action should the project manager take next based on this evidence?
- Assess and prioritize the change’s project impacts.
- Verify the external change with authoritative sources.
- Obtain the required decision and update the delivery plan.
- Assign ongoing monitoring and review further impacts.
Answer: A
ECO task 3.8: Responding to external change. Evidence not yet verified: an assessment of impacts on value, scope, and delivery. An external change needs project-specific impact analysis before a response is chosen.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.
3.2 Obligations and conformity evidence
A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties.
Evidence not yet verified: evidence that implemented controls satisfy the obligations.
Evidence not yet verified: assigned compliance controls and required approvals.
Verified evidence in the review file: a gap assessment and consequences of noncompliance.
Verified evidence in the review file: a register of applicable legal and contractual obligations.
Which action should the project manager take next based on this evidence?
- Confirm and classify the applicable compliance obligations.
- Assess current gaps, threats, and consequences of noncompliance.
- Assign controls, owners, and required approval checkpoints.
- Verify compliance evidence before authorizing the release.
Answer: C
ECO task 3.2: Obligations and conformity evidence. Evidence not yet verified: assigned compliance controls and required approvals. Each gap needs a controlled response with ownership and authorized approval.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.2.
3.1 Decision authority and oversight
A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority.
Evidence not yet verified: agreed decision rights and escalation thresholds.
Evidence not yet verified: approved success measures and governance reporting arrangements.
Verified evidence in the review file: a check that teams follow the approved authority model.
Evidence not yet verified: the applicable organizational policies and authority constraints.
Which action should the project manager take next based on this evidence?
- Approve success measures and the governance reporting cycle.
- Check decision records against the approved authority model.
- Review each partner’s mandatory governance requirements.
- Agree decision rights, escalation paths, and thresholds.
Answer: C
ECO task 3.1: Decision authority and oversight. Evidence not yet verified: the applicable organizational policies and authority constraints. Project rules must respect existing authority, ethics, and mandatory policies.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.1.
3.3 Authorized change execution
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation.
Evidence not yet verified: an integrated impact analysis of the requested feature.
Evidence not yet verified: a recorded change request with a clear business rationale.
Verified evidence in the review file: implementation records and updated baselines for the approved change.
Evidence not yet verified: a documented decision by the authorized change authority.
Which action should the project manager take next based on this evidence?
- Record the request, its rationale, and requested outcome.
- Submit the analysis to the authorized change authority.
- Implement the approved change and update controlled documents.
- Assess scope, cost, schedule, risk, and benefit impacts.
Answer: A
ECO task 3.3: Authorized change execution. Evidence not yet verified: a recorded change request with a clear business rationale. A controlled change needs a traceable request before analysis and decision.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.3.
3.4 Resolving realized blockers
A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue.
Evidence not yet verified: a current issue record and confirmed impact.
Evidence not yet verified: an agreed priority, resolution owner, and escalation path.
Evidence not yet verified: an authorized workaround or corrective intervention.
Verified evidence in the review file: a retest proving that testing can resume safely.
Which action should the project manager take next based on this evidence?
- Coordinate and apply the authorized corrective intervention.
- Retest the blocked workflow before closing the issue.
- Record the realized issue and assess its current impact.
- Assign an issue owner and prioritize the required intervention.
Answer: C
ECO task 3.4: Resolving realized blockers. Evidence not yet verified: a current issue record and confirmed impact. An event that has occurred requires issue management, even if it began as a risk.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.4.
3.5 Uncertainty and response monitoring
A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite.
Evidence not yet verified: a cause-event-effect risk statement and an owner.
Verified evidence in the review file: a monitoring check of triggers and residual exposure.
Evidence not yet verified: an approved response, trigger, and contingency owner.
Evidence not yet verified: an assessed probability, impact, and risk priority.
Which action should the project manager take next based on this evidence?
- Agree the risk response, trigger, and contingency responsibility.
- Monitor triggers, residual risk, and response effectiveness.
- Record the uncertain event, causes, effects, and risk owner.
- Analyze probability and impact against the agreed risk criteria.
Answer: C
ECO task 3.5: Uncertainty and response monitoring. Evidence not yet verified: a cause-event-effect risk statement and an owner. A useful risk record distinguishes uncertainty from an issue that has already occurred.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.5.
3.6 Testing and reusing improvements
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement.
Evidence not yet verified: results from the improvement experiment.
Verified evidence in the review file: updated organizational standards and reusable lessons.
Evidence not yet verified: evidence of the recurring defect and its root cause.
Evidence not yet verified: a small improvement experiment and an outcome measure.
Which action should the project manager take next based on this evidence?
- Update the standard process and publish the validated lesson.
- Design a limited experiment with a measurable outcome.
- Run the experiment and compare outcomes with the baseline.
- Analyze rework evidence and identify the root cause.
Answer: D
ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.
3.7 Readiness and organizational adoption
A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence.
Verified evidence in the review file: adoption evidence and adjustments to transition support.
Evidence not yet verified: a supported pilot with trained users and escalation access.
Evidence not yet verified: a role-impact assessment and agreed transition support.
Evidence not yet verified: an assessment of culture, concerns, and change readiness.
Which action should the project manager take next based on this evidence?
- Measure adoption and adjust support using user feedback.
- Assess culture and discuss concerns with affected departments.
- Map role impacts and agree training and transition support.
- Run a supported pilot before the wider transition.
Answer: B
ECO task 3.7: Readiness and organizational adoption. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Resistance can reflect real impacts that need understanding before a transition is planned.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.7.
3.8 Responding to external change
A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records.
Evidence not yet verified: an assessment of impacts on value, scope, and delivery.
Evidence not yet verified: an authorized response and updated scope or backlog.
Verified evidence in the review file: a continuing scan for further external changes.
Evidence not yet verified: verified details, applicability, and the effective date of the rule.
Which action should the project manager take next based on this evidence?
- Assign ongoing monitoring and review further impacts.
- Assess and prioritize the change’s project impacts.
- Obtain the required decision and update the delivery plan.
- Verify the external change with authoritative sources.
Answer: D
ECO task 3.8: Responding to external change. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Unverified announcements can't provide a reliable basis for changing project commitments.
Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.8.