        PMP practice exam and questions: 2026 outline

        Work through 360 original PMP questions with explanations linked to the July 2026 examination outline. Choose a domain set or a 180-question, 240-minute knowledge mock. Then use the project workbench to edit schedules, risk registers and stakeholder plans. The first set in each domain and the first mock are free. This practice provides no contact hours or PDUs.

        A project dependency diagram, a risk matrix and an answer sheet for PMP practice.

        Exam at a glance

        Version
        PMP Examination Content Outline, July 2026; PMI doesn't list a separate alphanumeric exam code
        Official format
        180 questions in 240 minutes: 170 scored and 10 unscored pretest questions
        Official domains
        People 33%; Process 41%; Business Environment 26%
        Official question types
        Single and multiple response, matching and drag-and-drop, case studies, graphics and practicum tasks; availability varies by delivery mode
        Official breaks
        Two 10-minute breaks; completed sections can't be reopened. Check the current delivery rules with PMI
        Official pass score
        PMI doesn't publish a fixed percentage of correct answers. Our 80% target is for practice only
        Our format
        Two different 180-question single-response knowledge mocks. Checked practical tasks are separate; our mocks don't reproduce the official interface, break schedule or scoring
        Training hours
        Our practice provides no contact hours, 35-hour eligibility certificate or PDUs
        Booking
        Apply to PMI, obtain approval, pay and schedule. Pearson VUE test centers and online proctoring have local availability and exceptions
        Exam fee
        PMI displays USD 405 for members and USD 655 at full price. Check your country, currency, taxes and membership at checkout
        Set by
        Project Management Institute (PMI)
        Practice target
        80%
        Practice language
        English

        Parts to practice

        • People
        • Process
        • Business Environment

        Your practice

        Finish a set to see your best scores and which part to practice next.

        0 of 2 mock exams completed

        Start your first free set

        These scores are saved in this browser. Clearing its data removes them.

        July 2026 changes

        The previous outline weighted People at 42%, Process at 50% and Business Environment at 8%. The July 2026 outline changes these to 33%, 41% and 26%, adds more case and graphic work, and gives business value, sustainability and responsible technology decisions more attention.

        PMI's transition notice announced the new exam for July 9, 2026 and told candidates for the previous version to sit before July 8, 2026. Its current page confirms the July update and a 240-minute exam. We offer practice for the July 2026 outline only.

        Statistics

        Practice by part

        Each domain has lesson links and original worked answers. The first set in each domain is free.

        Full mock exams

        Two different 180-question knowledge papers, each on a 240-minute clock. The first is free; the second is in Full access. Practical work is separate.

        1. PMP knowledge mock 1Free180 original single-response questions in 240 minutes. Each mock uses different questions. Checked practical tasks are separate. Practice target: 144.180 questions · 4 h
        2. PMP knowledge mock 2Exam pass180 original single-response questions in 240 minutes. Each mock uses different questions. Checked practical tasks are separate. Practice target: 144.180 questions · 4 h

        Sample questions

        One question from each part, with the worked answer.

        1. People

          A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Evidence not yet verified: an assessment of each group’s influence and needs. Verified evidence in the review file: a complete list of affected groups. Verified evidence in the review file: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Which action should the project manager take next based on this evidence?

          1. Agree suitable workshops, updates, and responsible owners.
          2. Analyze influence, impact, and information needs.
          3. Check participation and adjust the engagement approach.
          4. Identify the affected groups with operations representatives.
          Answer: B

          ECO task 1.4: Stakeholder involvement. Evidence not yet verified: an assessment of each group’s influence and needs. An inventory names people; analysis determines how to engage them.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 1.4.

        2. Process

          A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an estimate of costs and identified financial risks. Verified evidence in the review file: a governance review of the forecast and funding variance. Verified evidence in the review file: reconciled actual spending and remaining cost estimates. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Which action should the project manager take next based on this evidence?

          1. Reconcile actual costs and estimate the remaining work.
          2. Obtain baseline approval and justify contingency reserves.
          3. Report the forecast and seek required funding decisions.
          4. Estimate costs and identify relevant financial uncertainty.
          Answer: B

          ECO task 2.6: Financial forecasting and control. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Contingency addresses identified risk and needs authorization under the funding rules.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 2.6.

        3. Business Environment

          A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: a small improvement experiment and an outcome measure. Verified evidence in the review file: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Which action should the project manager take next based on this evidence?

          1. Run the experiment and compare outcomes with the baseline.
          2. Update the standard process and publish the validated lesson.
          3. Design a limited experiment with a measurable outcome.
          4. Analyze rework evidence and identify the root cause.
          Answer: D

          ECO task 3.6: Testing and reusing improvements. Evidence not yet verified: evidence of the recurring defect and its root cause. An improvement should address an evidenced cause rather than a convenient assumption.

          Source: July 2026 ECO; scope mapping checked 2026-11-22. Original practice case, not an official exam item. ECO task 3.6.

        About the exam

        The July 2026 outline tests project decisions across predictive, adaptive and hybrid work. Its approximate approach split is 40% predictive and 60% adaptive/agile or hybrid. The outline, rather than a single book, defines the exam scope.

        Our two knowledge mocks use 59 People, 74 Process and 47 Business Environment questions each. These whole-number allocations approximate the official weights; PMI doesn't promise those counts on your form. All 180 questions count toward our practice result. PMI scores 170 questions and doesn't identify its 10 pretest items.

        People sets map to stakeholder engagement, communication planning and team conflict. Use the engagement grid and matching tasks to test your decisions after each set.

        Process sets map to scope change control, critical paths, earned value and sprint planning. Edit the worksheets and schedule, then check your result.

        Business Environment sets map to project charters, risk registers, outcome measures and the clinic move case. These are checked workplace tasks, not copies of PMI practicum items.

        For multiple-response and matching practice, take the course's shortened PMP-style mock. It has 30 questions in 40 minutes. Our full knowledge mocks use single-response questions on one clock, without the official case-section locks or scheduled breaks.

        Common questions

        Is this the official PMP exam?
        No. The Work Gym writes its own questions and is independent of PMI. Our results don't predict a certification result.
        Does this count toward the 35 training hours?
        No. Our practice provides no contact hours or PDUs. PMI excludes practice exams alone from qualifying training. Check the separate requirements guide before applying.
        What score do I need to pass PMP?
        PMI doesn't publish a fixed raw percentage. We use 80% correct as a study target, not an official passing score. Review the decisions behind wrong answers.
        Do the two mocks share questions?
        No. The 360-question bank supplies two disjoint 180-question mocks. Domain practice sets use those same banks, so a question you practiced can appear in a mock.
        Does this reproduce the new practicum?
        The knowledge mocks use single-response questions. Separate course lessons let you edit project artifacts and check the results, and the short course mock includes matching and multiple response. They don't reproduce PMI's interface or confidential exam items.
        Can I book an online PMP exam?
        PMI offers online proctoring and test-center delivery, with local exceptions. Japanese and Korean local-language online delivery uses ATA; mainland China uses paper-based ATA delivery. Confirm the option offered during booking.

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.