Agile teams often estimate in story points: a relative size for each backlog item, compared with items already done. A 5-point story is about as big as other 5s, and bigger than a 3. Points blend effort, complexity and uncertainty, and they belong to the team that estimated them.
Planning poker gets the whole team estimating at once: everyone shows a card together, and the highest and lowest explain their reasons. The discussion finds the missing information, not the average.
Velocity is the points a team finishes per sprint. To forecast:
- Use the last few sprints, not the best one.
- Sprints needed = remaining points ÷ velocity, rounded up: a team does not finish 0.3 of a sprint.
- Give a range, using the lowest and highest recent velocity.
Velocity is for the team's own planning. Comparing one team's velocity with another's means nothing: their points are on different scales.
A velocity forecast with a range.