        PMP Business Environment practice questions: set 1

        Answer 19 original business Environment questions in 25 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 16 correct is our practice target, not a PMI pass score.

        A project dependency diagram, a risk matrix and an answer sheet for PMP practice.
        Questions
        19
        Time
        25 min
        Our study target
        16 (80%)
        Part
        Business Environment
        Mode
        Timed or untimed
        Access
        Free

        The practice test needs JavaScript. These are its questions:

        1. A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Verified evidence in the review file: approved success measures and governance reporting arrangements. Verified evidence in the review file: a check that teams follow the approved authority model. Which action should the project manager take next based on this evidence?

          1. Agree decision rights, escalation paths, and thresholds.
          2. Review each partner’s mandatory governance requirements.
          3. Approve success measures and the governance reporting cycle.
          4. Check decision records against the approved authority model.
        2. A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: a role-impact assessment and agreed transition support. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Verified evidence in the review file: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Which action should the project manager take next based on this evidence?

          1. Run a supported pilot before the wider transition.
          2. Measure adoption and adjust support using user feedback.
          3. Map role impacts and agree training and transition support.
          4. Assess culture and discuss concerns with affected departments.
        3. A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Verified evidence in the review file: an agreed priority, resolution owner, and escalation path. Evidence not yet verified: an authorized workaround or corrective intervention. Verified evidence in the review file: a retest proving that testing can resume safely. Verified evidence in the review file: a current issue record and confirmed impact. Which action should the project manager take next based on this evidence?

          1. Retest the blocked workflow before closing the issue.
          2. Record the realized issue and assess its current impact.
          3. Coordinate and apply the authorized corrective intervention.
          4. Assign an issue owner and prioritize the required intervention.
        4. A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Verified evidence in the review file: assigned compliance controls and required approvals. Verified evidence in the review file: a gap assessment and consequences of noncompliance. Verified evidence in the review file: a register of applicable legal and contractual obligations. Which action should the project manager take next based on this evidence?

          1. Verify compliance evidence before authorizing the release.
          2. Confirm and classify the applicable compliance obligations.
          3. Assess current gaps, threats, and consequences of noncompliance.
          4. Assign controls, owners, and required approval checkpoints.
        5. A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Evidence not yet verified: a small improvement experiment and an outcome measure. Which action should the project manager take next based on this evidence?

          1. Update the standard process and publish the validated lesson.
          2. Design a limited experiment with a measurable outcome.
          3. Analyze rework evidence and identify the root cause.
          4. Run the experiment and compare outcomes with the baseline.
        6. A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Evidence not yet verified: a recorded change request with a clear business rationale. Evidence not yet verified: implementation records and updated baselines for the approved change. Verified evidence in the review file: a documented decision by the authorized change authority. Verified evidence in the review file: an integrated impact analysis of the requested feature. Which action should the project manager take next based on this evidence?

          1. Record the request, its rationale, and requested outcome.
          2. Assess scope, cost, schedule, risk, and benefit impacts.
          3. Submit the analysis to the authorized change authority.
          4. Implement the approved change and update controlled documents.
        7. A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Verified evidence in the review file: an assessment of impacts on value, scope, and delivery. Verified evidence in the review file: an authorized response and updated scope or backlog. Evidence not yet verified: a continuing scan for further external changes. Which action should the project manager take next based on this evidence?

          1. Obtain the required decision and update the delivery plan.
          2. Assign ongoing monitoring and review further impacts.
          3. Verify the external change with authoritative sources.
          4. Assess and prioritize the change’s project impacts.
        8. A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Evidence not yet verified: an assessed probability, impact, and risk priority. Verified evidence in the review file: a cause-event-effect risk statement and an owner. Evidence not yet verified: a monitoring check of triggers and residual exposure. Verified evidence in the review file: an approved response, trigger, and contingency owner. Which action should the project manager take next based on this evidence?

          1. Monitor triggers, residual risk, and response effectiveness.
          2. Record the uncertain event, causes, effects, and risk owner.
          3. Analyze probability and impact against the agreed risk criteria.
          4. Agree the risk response, trigger, and contingency responsibility.
        9. A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: agreed decision rights and escalation thresholds. Evidence not yet verified: approved success measures and governance reporting arrangements. Verified evidence in the review file: a check that teams follow the approved authority model. Evidence not yet verified: the applicable organizational policies and authority constraints. Which action should the project manager take next based on this evidence?

          1. Approve success measures and the governance reporting cycle.
          2. Check decision records against the approved authority model.
          3. Review each partner’s mandatory governance requirements.
          4. Agree decision rights, escalation paths, and thresholds.
        10. A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: adoption evidence and adjustments to transition support. Evidence not yet verified: a supported pilot with trained users and escalation access. Evidence not yet verified: a role-impact assessment and agreed transition support. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Which action should the project manager take next based on this evidence?

          1. Measure adoption and adjust support using user feedback.
          2. Assess culture and discuss concerns with affected departments.
          3. Map role impacts and agree training and transition support.
          4. Run a supported pilot before the wider transition.
        11. A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Verified evidence in the review file: a recorded change request with a clear business rationale. Verified evidence in the review file: implementation records and updated baselines for the approved change. Verified evidence in the review file: a documented decision by the authorized change authority. Evidence not yet verified: an integrated impact analysis of the requested feature. Which action should the project manager take next based on this evidence?

          1. Record the request, its rationale, and requested outcome.
          2. Submit the analysis to the authorized change authority.
          3. Assess scope, cost, schedule, risk, and benefit impacts.
          4. Implement the approved change and update controlled documents.
        12. A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Verified evidence in the review file: an assessed probability, impact, and risk priority. Verified evidence in the review file: a cause-event-effect risk statement and an owner. Evidence not yet verified: a monitoring check of triggers and residual exposure. Verified evidence in the review file: an approved response, trigger, and contingency owner. Which action should the project manager take next based on this evidence?

          1. Agree the risk response, trigger, and contingency responsibility.
          2. Record the uncertain event, causes, effects, and risk owner.
          3. Analyze probability and impact against the agreed risk criteria.
          4. Monitor triggers, residual risk, and response effectiveness.
        13. A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: evidence of the recurring defect and its root cause. Verified evidence in the review file: a small improvement experiment and an outcome measure. Verified evidence in the review file: results from the improvement experiment. Evidence not yet verified: updated organizational standards and reusable lessons. Which action should the project manager take next based on this evidence?

          1. Analyze rework evidence and identify the root cause.
          2. Design a limited experiment with a measurable outcome.
          3. Update the standard process and publish the validated lesson.
          4. Run the experiment and compare outcomes with the baseline.
        14. A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Verified evidence in the review file: evidence that implemented controls satisfy the obligations. Verified evidence in the review file: assigned compliance controls and required approvals. Evidence not yet verified: a gap assessment and consequences of noncompliance. Evidence not yet verified: a register of applicable legal and contractual obligations. Which action should the project manager take next based on this evidence?

          1. Assess current gaps, threats, and consequences of noncompliance.
          2. Assign controls, owners, and required approval checkpoints.
          3. Verify compliance evidence before authorizing the release.
          4. Confirm and classify the applicable compliance obligations.
        15. A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Evidence not yet verified: a current issue record and confirmed impact. Verified evidence in the review file: an agreed priority, resolution owner, and escalation path. Evidence not yet verified: an authorized workaround or corrective intervention. Verified evidence in the review file: a retest proving that testing can resume safely. Which action should the project manager take next based on this evidence?

          1. Coordinate and apply the authorized corrective intervention.
          2. Record the realized issue and assess its current impact.
          3. Retest the blocked workflow before closing the issue.
          4. Assign an issue owner and prioritize the required intervention.
        16. A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Verified evidence in the review file: verified details, applicability, and the effective date of the rule. Evidence not yet verified: an assessment of impacts on value, scope, and delivery. Evidence not yet verified: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Which action should the project manager take next based on this evidence?

          1. Assess and prioritize the change’s project impacts.
          2. Obtain the required decision and update the delivery plan.
          3. Assign ongoing monitoring and review further impacts.
          4. Verify the external change with authoritative sources.
        17. A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: approved success measures and governance reporting arrangements. Evidence not yet verified: a check that teams follow the approved authority model. Verified evidence in the review file: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Which action should the project manager take next based on this evidence?

          1. Check decision records against the approved authority model.
          2. Review each partner’s mandatory governance requirements.
          3. Agree decision rights, escalation paths, and thresholds.
          4. Approve success measures and the governance reporting cycle.
        18. A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: an assessment of culture, concerns, and change readiness. Evidence not yet verified: adoption evidence and adjustments to transition support. Evidence not yet verified: a supported pilot with trained users and escalation access. Verified evidence in the review file: a role-impact assessment and agreed transition support. Which action should the project manager take next based on this evidence?

          1. Assess culture and discuss concerns with affected departments.
          2. Map role impacts and agree training and transition support.
          3. Run a supported pilot before the wider transition.
          4. Measure adoption and adjust support using user feedback.
        19. A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Verified evidence in the review file: a current issue record and confirmed impact. Evidence not yet verified: a retest proving that testing can resume safely. Evidence not yet verified: an authorized workaround or corrective intervention. Which action should the project manager take next based on this evidence?

          1. Coordinate and apply the authorized corrective intervention.
          2. Assign an issue owner and prioritize the required intervention.
          3. Retest the blocked workflow before closing the issue.
          4. Record the realized issue and assess its current impact.

        What this set covers

        • 3.1 Decision authority and oversight3 questions
        • 3.7 Readiness and organizational adoption3 questions
        • 3.4 Resolving realized blockers3 questions
        • 3.2 Obligations and conformity evidence2 questions
        • 3.6 Testing and reusing improvements2 questions
        • 3.3 Authorized change execution2 questions
        • 3.8 Responding to external change2 questions
        • 3.5 Uncertainty and response monitoring2 questions

        Next: Business Environment, set 2

        More practice for this exam

        1. Business Environment, set 219 questions · 25 min
        2. Business Environment, set 319 questions · 25 min
        3. Business Environment, set 419 questions · 25 min
        4. Business Environment, set 518 questions · 24 min
        5. PMP knowledge mock 1180 questions · 4 h
        6. PMP knowledge mock 2180 questions · 4 h

        All practice for the PMP

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.