        PMP Business Environment practice questions: set 5

        Answer 18 original business Environment questions in 24 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 15 correct is our practice target, not a PMI pass score.

        A project dependency diagram, a risk matrix and an answer sheet for PMP practice.
        Questions
        18
        Time
        24 min
        Our study target
        15 (80%)
        Part
        Business Environment
        Mode
        Timed or untimed
        Access
        Exam pass

        The practice test needs JavaScript. These are its questions:

        1. A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: a small improvement experiment and an outcome measure. Verified evidence in the review file: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Which action should the project manager take next based on this evidence?

          1. Run the experiment and compare outcomes with the baseline.
          2. Update the standard process and publish the validated lesson.
          3. Design a limited experiment with a measurable outcome.
          4. Analyze rework evidence and identify the root cause.
        2. A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Verified evidence in the review file: implementation records and updated baselines for the approved change. Evidence not yet verified: a documented decision by the authorized change authority. Verified evidence in the review file: an integrated impact analysis of the requested feature. Verified evidence in the review file: a recorded change request with a clear business rationale. Which action should the project manager take next based on this evidence?

          1. Submit the analysis to the authorized change authority.
          2. Implement the approved change and update controlled documents.
          3. Record the request, its rationale, and requested outcome.
          4. Assess scope, cost, schedule, risk, and benefit impacts.
        3. A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Evidence not yet verified: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Verified evidence in the review file: verified details, applicability, and the effective date of the rule. Verified evidence in the review file: an assessment of impacts on value, scope, and delivery. Which action should the project manager take next based on this evidence?

          1. Verify the external change with authoritative sources.
          2. Assess and prioritize the change’s project impacts.
          3. Obtain the required decision and update the delivery plan.
          4. Assign ongoing monitoring and review further impacts.
        4. A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Evidence not yet verified: a cause-event-effect risk statement and an owner. Verified evidence in the review file: a monitoring check of triggers and residual exposure. Verified evidence in the review file: an approved response, trigger, and contingency owner. Evidence not yet verified: an assessed probability, impact, and risk priority. Which action should the project manager take next based on this evidence?

          1. Agree the risk response, trigger, and contingency responsibility.
          2. Monitor triggers, residual risk, and response effectiveness.
          3. Analyze probability and impact against the agreed risk criteria.
          4. Record the uncertain event, causes, effects, and risk owner.
        5. A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Verified evidence in the review file: approved success measures and governance reporting arrangements. Evidence not yet verified: a check that teams follow the approved authority model. Which action should the project manager take next based on this evidence?

          1. Agree decision rights, escalation paths, and thresholds.
          2. Approve success measures and the governance reporting cycle.
          3. Review each partner’s mandatory governance requirements.
          4. Check decision records against the approved authority model.
        6. A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: a role-impact assessment and agreed transition support. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Evidence not yet verified: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Which action should the project manager take next based on this evidence?

          1. Run a supported pilot before the wider transition.
          2. Measure adoption and adjust support using user feedback.
          3. Map role impacts and agree training and transition support.
          4. Assess culture and discuss concerns with affected departments.
        7. A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Verified evidence in the review file: an authorized workaround or corrective intervention. Evidence not yet verified: a retest proving that testing can resume safely. Verified evidence in the review file: a current issue record and confirmed impact. Which action should the project manager take next based on this evidence?

          1. Retest the blocked workflow before closing the issue.
          2. Record the realized issue and assess its current impact.
          3. Assign an issue owner and prioritize the required intervention.
          4. Coordinate and apply the authorized corrective intervention.
        8. A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Evidence not yet verified: assigned compliance controls and required approvals. Verified evidence in the review file: a gap assessment and consequences of noncompliance. Verified evidence in the review file: a register of applicable legal and contractual obligations. Which action should the project manager take next based on this evidence?

          1. Confirm and classify the applicable compliance obligations.
          2. Assess current gaps, threats, and consequences of noncompliance.
          3. Assign controls, owners, and required approval checkpoints.
          4. Verify compliance evidence before authorizing the release.
        9. A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Evidence not yet verified: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Evidence not yet verified: a small improvement experiment and an outcome measure. Which action should the project manager take next based on this evidence?

          1. Update the standard process and publish the validated lesson.
          2. Design a limited experiment with a measurable outcome.
          3. Run the experiment and compare outcomes with the baseline.
          4. Analyze rework evidence and identify the root cause.
        10. A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Verified evidence in the review file: an authorized workaround or corrective intervention. Verified evidence in the review file: a retest proving that testing can resume safely. Verified evidence in the review file: a current issue record and confirmed impact. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Which action should the project manager take next based on this evidence?

          1. Record the realized issue and assess its current impact.
          2. Assign an issue owner and prioritize the required intervention.
          3. Coordinate and apply the authorized corrective intervention.
          4. Retest the blocked workflow before closing the issue.
        11. A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Evidence not yet verified: a role-impact assessment and agreed transition support. Verified evidence in the review file: an assessment of culture, concerns, and change readiness. Verified evidence in the review file: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Which action should the project manager take next based on this evidence?

          1. Run a supported pilot before the wider transition.
          2. Measure adoption and adjust support using user feedback.
          3. Map role impacts and agree training and transition support.
          4. Assess culture and discuss concerns with affected departments.
        12. A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Verified evidence in the review file: approved success measures and governance reporting arrangements. Evidence not yet verified: a check that teams follow the approved authority model. Verified evidence in the review file: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Which action should the project manager take next based on this evidence?

          1. Check decision records against the approved authority model.
          2. Approve success measures and the governance reporting cycle.
          3. Review each partner’s mandatory governance requirements.
          4. Agree decision rights, escalation paths, and thresholds.
        13. A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Verified evidence in the review file: an integrated impact analysis of the requested feature. Evidence not yet verified: a recorded change request with a clear business rationale. Verified evidence in the review file: implementation records and updated baselines for the approved change. Evidence not yet verified: a documented decision by the authorized change authority. Which action should the project manager take next based on this evidence?

          1. Submit the analysis to the authorized change authority.
          2. Implement the approved change and update controlled documents.
          3. Record the request, its rationale, and requested outcome.
          4. Assess scope, cost, schedule, risk, and benefit impacts.
        14. A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Verified evidence in the review file: an assessment of impacts on value, scope, and delivery. Evidence not yet verified: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Which action should the project manager take next based on this evidence?

          1. Assign ongoing monitoring and review further impacts.
          2. Assess and prioritize the change’s project impacts.
          3. Verify the external change with authoritative sources.
          4. Obtain the required decision and update the delivery plan.
        15. A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Verified evidence in the review file: a monitoring check of triggers and residual exposure. Evidence not yet verified: an approved response, trigger, and contingency owner. Evidence not yet verified: an assessed probability, impact, and risk priority. Verified evidence in the review file: a cause-event-effect risk statement and an owner. Which action should the project manager take next based on this evidence?

          1. Record the uncertain event, causes, effects, and risk owner.
          2. Analyze probability and impact against the agreed risk criteria.
          3. Agree the risk response, trigger, and contingency responsibility.
          4. Monitor triggers, residual risk, and response effectiveness.
        16. A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Verified evidence in the review file: a register of applicable legal and contractual obligations. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Verified evidence in the review file: assigned compliance controls and required approvals. Evidence not yet verified: a gap assessment and consequences of noncompliance. Which action should the project manager take next based on this evidence?

          1. Assign controls, owners, and required approval checkpoints.
          2. Assess current gaps, threats, and consequences of noncompliance.
          3. Verify compliance evidence before authorizing the release.
          4. Confirm and classify the applicable compliance obligations.
        17. A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: evidence of the recurring defect and its root cause. Verified evidence in the review file: a small improvement experiment and an outcome measure. Evidence not yet verified: results from the improvement experiment. Evidence not yet verified: updated organizational standards and reusable lessons. Which action should the project manager take next based on this evidence?

          1. Analyze rework evidence and identify the root cause.
          2. Run the experiment and compare outcomes with the baseline.
          3. Design a limited experiment with a measurable outcome.
          4. Update the standard process and publish the validated lesson.
        18. A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Evidence not yet verified: an integrated impact analysis of the requested feature. Evidence not yet verified: a documented decision by the authorized change authority. Evidence not yet verified: implementation records and updated baselines for the approved change. Verified evidence in the review file: a recorded change request with a clear business rationale. Which action should the project manager take next based on this evidence?

          1. Submit the analysis to the authorized change authority.
          2. Assess scope, cost, schedule, risk, and benefit impacts.
          3. Implement the approved change and update controlled documents.
          4. Record the request, its rationale, and requested outcome.

        What this set covers

        • 3.6 Testing and reusing improvements3 questions
        • 3.3 Authorized change execution3 questions
        • 3.8 Responding to external change2 questions
        • 3.5 Uncertainty and response monitoring2 questions
        • 3.1 Decision authority and oversight2 questions
        • 3.7 Readiness and organizational adoption2 questions
        • 3.4 Resolving realized blockers2 questions
        • 3.2 Obligations and conformity evidence2 questions

        Next: PMP knowledge mock 1

        More practice for this exam

        1. Business Environment, set 119 questions · 25 min
        2. Business Environment, set 219 questions · 25 min
        3. Business Environment, set 319 questions · 25 min
        4. Business Environment, set 419 questions · 25 min
        5. PMP knowledge mock 1180 questions · 4 h
        6. PMP knowledge mock 2180 questions · 4 h

        All practice for the PMP

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.