PMP Business Environment practice questions: set 5
Answer 18 original business Environment questions in 24 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 15 correct is our practice target, not a PMI pass score.
- Questions
- 18
- Time
- 24 min
- Our study target
- 15 (80%)
- Part
- Business Environment
- Mode
- Timed or untimed
- Access
- Exam pass
The practice test needs JavaScript. These are its questions:
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: a small improvement experiment and an outcome measure. Verified evidence in the review file: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Which action should the project manager take next based on this evidence?
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Verified evidence in the review file: implementation records and updated baselines for the approved change. Evidence not yet verified: a documented decision by the authorized change authority. Verified evidence in the review file: an integrated impact analysis of the requested feature. Verified evidence in the review file: a recorded change request with a clear business rationale. Which action should the project manager take next based on this evidence?
A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Evidence not yet verified: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Verified evidence in the review file: verified details, applicability, and the effective date of the rule. Verified evidence in the review file: an assessment of impacts on value, scope, and delivery. Which action should the project manager take next based on this evidence?
A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Evidence not yet verified: a cause-event-effect risk statement and an owner. Verified evidence in the review file: a monitoring check of triggers and residual exposure. Verified evidence in the review file: an approved response, trigger, and contingency owner. Evidence not yet verified: an assessed probability, impact, and risk priority. Which action should the project manager take next based on this evidence?
A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Evidence not yet verified: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Verified evidence in the review file: approved success measures and governance reporting arrangements. Evidence not yet verified: a check that teams follow the approved authority model. Which action should the project manager take next based on this evidence?
A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Verified evidence in the review file: a role-impact assessment and agreed transition support. Evidence not yet verified: an assessment of culture, concerns, and change readiness. Evidence not yet verified: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Which action should the project manager take next based on this evidence?
A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Verified evidence in the review file: an authorized workaround or corrective intervention. Evidence not yet verified: a retest proving that testing can resume safely. Verified evidence in the review file: a current issue record and confirmed impact. Which action should the project manager take next based on this evidence?
A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Evidence not yet verified: assigned compliance controls and required approvals. Verified evidence in the review file: a gap assessment and consequences of noncompliance. Verified evidence in the review file: a register of applicable legal and contractual obligations. Which action should the project manager take next based on this evidence?
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Evidence not yet verified: results from the improvement experiment. Verified evidence in the review file: updated organizational standards and reusable lessons. Evidence not yet verified: evidence of the recurring defect and its root cause. Evidence not yet verified: a small improvement experiment and an outcome measure. Which action should the project manager take next based on this evidence?
A supplier authentication incident interrupted testing earlier in the project. A review checks the records needed to resolve and close that realized issue. Verified evidence in the review file: an authorized workaround or corrective intervention. Verified evidence in the review file: a retest proving that testing can resume safely. Verified evidence in the review file: a current issue record and confirmed impact. Evidence not yet verified: an agreed priority, resolution owner, and escalation path. Which action should the project manager take next based on this evidence?
A shared-service platform replaces local approval routines. A change-readiness review examines department concerns, transition support, and adoption evidence. Evidence not yet verified: a role-impact assessment and agreed transition support. Verified evidence in the review file: an assessment of culture, concerns, and change readiness. Verified evidence in the review file: adoption evidence and adjustments to transition support. Verified evidence in the review file: a supported pilot with trained users and escalation access. Which action should the project manager take next based on this evidence?
A joint venture starts a construction project. Its partners use different approval rules, and no one may assume the other partner’s spending authority. Verified evidence in the review file: approved success measures and governance reporting arrangements. Evidence not yet verified: a check that teams follow the approved authority model. Verified evidence in the review file: the applicable organizational policies and authority constraints. Verified evidence in the review file: agreed decision rights and escalation thresholds. Which action should the project manager take next based on this evidence?
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Verified evidence in the review file: an integrated impact analysis of the requested feature. Evidence not yet verified: a recorded change request with a clear business rationale. Verified evidence in the review file: implementation records and updated baselines for the approved change. Evidence not yet verified: a documented decision by the authorized change authority. Which action should the project manager take next based on this evidence?
A new market-access rule may affect a planned export service. An external-change review examines the rule and the response records. Verified evidence in the review file: an assessment of impacts on value, scope, and delivery. Evidence not yet verified: an authorized response and updated scope or backlog. Verified evidence in the review file: a continuing scan for further external changes. Evidence not yet verified: verified details, applicability, and the effective date of the rule. Which action should the project manager take next based on this evidence?
A coastal equipment project faces a possible storm disruption next month. The storm hasn't occurred, and the team must prepare within its risk appetite. Verified evidence in the review file: a monitoring check of triggers and residual exposure. Evidence not yet verified: an approved response, trigger, and contingency owner. Evidence not yet verified: an assessed probability, impact, and risk priority. Verified evidence in the review file: a cause-event-effect risk statement and an owner. Which action should the project manager take next based on this evidence?
A packaging project must satisfy food-contact rules and a contractual waste limit. Commercial pressure can't waive legal duties. Verified evidence in the review file: a register of applicable legal and contractual obligations. Evidence not yet verified: evidence that implemented controls satisfy the obligations. Verified evidence in the review file: assigned compliance controls and required approvals. Evidence not yet verified: a gap assessment and consequences of noncompliance. Which action should the project manager take next based on this evidence?
A delivery team is reviewing lessons from rework caused by incomplete supplier specifications. The review examines evidence for reusing an improvement. Verified evidence in the review file: evidence of the recurring defect and its root cause. Verified evidence in the review file: a small improvement experiment and an outcome measure. Evidence not yet verified: results from the improvement experiment. Evidence not yet verified: updated organizational standards and reusable lessons. Which action should the project manager take next based on this evidence?
A customer requests an extra reporting feature in a baselined delivery. The contract requires impact analysis and authorized approval before implementation. Evidence not yet verified: an integrated impact analysis of the requested feature. Evidence not yet verified: a documented decision by the authorized change authority. Evidence not yet verified: implementation records and updated baselines for the approved change. Verified evidence in the review file: a recorded change request with a clear business rationale. Which action should the project manager take next based on this evidence?
What this set covers
- 3.6 Testing and reusing improvements3 questions
- 3.3 Authorized change execution3 questions
- 3.8 Responding to external change2 questions
- 3.5 Uncertainty and response monitoring2 questions
- 3.1 Decision authority and oversight2 questions
- 3.7 Readiness and organizational adoption2 questions
- 3.4 Resolving realized blockers2 questions
- 3.2 Obligations and conformity evidence2 questions
More practice for this exam
Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.