Country or region and language

    Choose your country or region and your language.

    Suggested for you

      All countries and regions

        Choose your character

        It shows in the top bar and on your profile. Change it any time.

        PMP People practice questions: set 2

        Answer 20 original people questions in 27 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 16 correct is our practice target, not a PMI pass score.

        A project dependency diagram, a risk matrix and an answer sheet for PMP practice.
        Questions
        20
        Time
        27 min
        Our study target
        16 (80%)
        Part
        People
        Mode
        Timed or untimed
        Access
        Exam pass

        The practice test needs JavaScript. These are its questions:

        1. Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Verified evidence in the review file: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Verified evidence in the review file: a neutral account of the underlying approval dispute. Which action should the project manager take next based on this evidence?

          1. Establish and enforce respectful discussion rules.
          2. Hear both teams and establish the source of the dispute.
          3. Facilitate an agreement on approval responsibilities.
          4. Review the next approval cycle with both teams.
        2. A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Verified evidence in the review file: confirmation that recipients understand and can respond. Verified evidence in the review file: delivery of a tailored report through the agreed channels. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Which action should the project manager take next based on this evidence?

          1. Agree the communication plan with the intended audiences.
          2. Distribute the tailored report using the agreed plan.
          3. Ask recipients for feedback and adjust future reports.
          4. Determine reporting needs and confidentiality requirements.
        3. A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Verified evidence in the review file: a complete list of affected groups. Evidence not yet verified: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Verified evidence in the review file: an assessment of each group’s influence and needs. Which action should the project manager take next based on this evidence?

          1. Check participation and adjust the engagement approach.
          2. Identify the affected groups with operations representatives.
          3. Analyze influence, impact, and information needs.
          4. Agree suitable workshops, updates, and responsible owners.
        4. A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: a classification of stakeholder groups and decision authority. Verified evidence in the review file: support for department leads applying the agreed target. Verified evidence in the review file: a negotiated response-time target and accepted trade-offs. Evidence not yet verified: explicit response-time expectations from both departments. Which action should the project manager take next based on this evidence?

          1. Classify stakeholders by role and decision authority.
          2. Facilitate agreement on the target and its trade-offs.
          3. Coach department leads on applying the agreed target.
          4. Ask both departments to state measurable expectations.
        5. A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: the operators’ intended outcomes. Verified evidence in the review file: an agreed vision with measurable success criteria. Verified evidence in the review file: evidence that each operator interprets the vision consistently. Evidence not yet verified: a communication owner and a date to review the vision. Which action should the project manager take next based on this evidence?

          1. Agree a shared vision and measurable success criteria.
          2. Interview the operators about their intended outcomes.
          3. Test understanding and investigate conflicting interpretations.
          4. Assign the vision’s communication owner and review date.
        6. A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Verified evidence in the review file: confirmed expectations of internal and external customers. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. Verified evidence in the review file: a repeat measurement after the agreed response. Which action should the project manager take next based on this evidence?

          1. Agree a response with customers and the accountable owner.
          2. Measure satisfaction again after the response is applied.
          3. Confirm expectations with internal and external customers.
          4. Compare pilot evidence with the confirmed expectations.
        7. A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: an inventory of critical diagnostic knowledge. Evidence not yet verified: captured diagnostic examples and decision rules. Verified evidence in the review file: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Which action should the project manager take next based on this evidence?

          1. Capture failure examples and the specialist’s decision rules.
          2. Identify critical knowledge with the specialist and operations.
          3. Run paired diagnostic practice with the receiving team.
          4. Have operations diagnose a fresh failure without coaching.
        8. A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a shared release goal and clear decision responsibilities. Evidence not yet verified: a review of members’ experience and support needs. Evidence not yet verified: a tailored delegation and coaching arrangement. Verified evidence in the review file: a feedback review of delegation and team concerns. Which action should the project manager take next based on this evidence?

          1. Delegate within agreed limits and coach where support is needed.
          2. Review results with the team and adjust leadership support.
          3. Agree the release goal and each role’s decision authority.
          4. Assess experience and ask members what support they need.
        9. Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Evidence not yet verified: a follow-up check that the agreement is working. Evidence not yet verified: a mutually agreed resolution and decision rights. Verified evidence in the review file: a neutral account of the underlying approval dispute. Which action should the project manager take next based on this evidence?

          1. Hear both teams and establish the source of the dispute.
          2. Facilitate an agreement on approval responsibilities.
          3. Review the next approval cycle with both teams.
          4. Establish and enforce respectful discussion rules.
        10. A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Evidence not yet verified: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Evidence not yet verified: an agreed channel, cadence, owner, and feedback method. Which action should the project manager take next based on this evidence?

          1. Distribute the tailored report using the agreed plan.
          2. Ask recipients for feedback and adjust future reports.
          3. Agree the communication plan with the intended audiences.
          4. Determine reporting needs and confidentiality requirements.
        11. A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Verified evidence in the review file: evidence that each operator interprets the vision consistently. Verified evidence in the review file: a communication owner and a date to review the vision. Verified evidence in the review file: the operators’ intended outcomes. Evidence not yet verified: an agreed vision with measurable success criteria. Which action should the project manager take next based on this evidence?

          1. Interview the operators about their intended outcomes.
          2. Agree a shared vision and measurable success criteria.
          3. Test understanding and investigate conflicting interpretations.
          4. Assign the vision’s communication owner and review date.
        12. A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. Verified evidence in the review file: a repeat measurement after the agreed response. Verified evidence in the review file: confirmed expectations of internal and external customers. Verified evidence in the review file: a comparison between pilot outcomes and customer expectations. Which action should the project manager take next based on this evidence?

          1. Measure satisfaction again after the response is applied.
          2. Confirm expectations with internal and external customers.
          3. Agree a response with customers and the accountable owner.
          4. Compare pilot evidence with the confirmed expectations.
        13. A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Verified evidence in the review file: a classification of stakeholder groups and decision authority. Evidence not yet verified: support for department leads applying the agreed target. Verified evidence in the review file: a negotiated response-time target and accepted trade-offs. Verified evidence in the review file: explicit response-time expectations from both departments. Which action should the project manager take next based on this evidence?

          1. Classify stakeholders by role and decision authority.
          2. Ask both departments to state measurable expectations.
          3. Coach department leads on applying the agreed target.
          4. Facilitate agreement on the target and its trade-offs.
        14. A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Verified evidence in the review file: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Evidence not yet verified: an assessment of each group’s influence and needs. Evidence not yet verified: a complete list of affected groups. Which action should the project manager take next based on this evidence?

          1. Analyze influence, impact, and information needs.
          2. Identify the affected groups with operations representatives.
          3. Agree suitable workshops, updates, and responsible owners.
          4. Check participation and adjust the engagement approach.
        15. A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a review of members’ experience and support needs. Evidence not yet verified: a tailored delegation and coaching arrangement. Verified evidence in the review file: a feedback review of delegation and team concerns. Verified evidence in the review file: a shared release goal and clear decision responsibilities. Which action should the project manager take next based on this evidence?

          1. Delegate within agreed limits and coach where support is needed.
          2. Review results with the team and adjust leadership support.
          3. Assess experience and ask members what support they need.
          4. Agree the release goal and each role’s decision authority.
        16. A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: an inventory of critical diagnostic knowledge. Evidence not yet verified: captured diagnostic examples and decision rules. Evidence not yet verified: guided practice for the receiving operations team. Verified evidence in the review file: an independent diagnosis and accepted handover evidence. Which action should the project manager take next based on this evidence?

          1. Capture failure examples and the specialist’s decision rules.
          2. Run paired diagnostic practice with the receiving team.
          3. Have operations diagnose a fresh failure without coaching.
          4. Identify critical knowledge with the specialist and operations.
        17. A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Verified evidence in the review file: a classification of stakeholder groups and decision authority. Evidence not yet verified: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Verified evidence in the review file: explicit response-time expectations from both departments. Which action should the project manager take next based on this evidence?

          1. Facilitate agreement on the target and its trade-offs.
          2. Classify stakeholders by role and decision authority.
          3. Ask both departments to state measurable expectations.
          4. Coach department leads on applying the agreed target.
        18. Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Evidence not yet verified: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Evidence not yet verified: a neutral account of the underlying approval dispute. Which action should the project manager take next based on this evidence?

          1. Facilitate an agreement on approval responsibilities.
          2. Establish and enforce respectful discussion rules.
          3. Review the next approval cycle with both teams.
          4. Hear both teams and establish the source of the dispute.
        19. A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. Evidence not yet verified: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method. Which action should the project manager take next based on this evidence?

          1. Determine reporting needs and confidentiality requirements.
          2. Agree the communication plan with the intended audiences.
          3. Distribute the tailored report using the agreed plan.
          4. Ask recipients for feedback and adjust future reports.
        20. A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. Evidence not yet verified: a repeat measurement after the agreed response. Evidence not yet verified: confirmed expectations of internal and external customers. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Which action should the project manager take next based on this evidence?

          1. Measure satisfaction again after the response is applied.
          2. Confirm expectations with internal and external customers.
          3. Compare pilot evidence with the confirmed expectations.
          4. Agree a response with customers and the accountable owner.

        What this set covers

        • 1.2 Conflict diagnosis and resolution3 questions
        • 1.8 Audience-specific reporting3 questions
        • 1.4 Stakeholder involvement2 questions
        • 1.5 Negotiating shared expectations3 questions
        • 1.1 Shared outcomes and understanding2 questions
        • 1.6 Customer satisfaction evidence3 questions
        • 1.7 Operational knowledge handover2 questions
        • 1.3 Team authority and tailored support2 questions

        Next: People, set 3

        More practice for this exam

        1. People, set 120 questions · 27 min
        2. People, set 320 questions · 27 min
        3. People, set 419 questions · 25 min
        4. People, set 520 questions · 27 min
        5. People, set 619 questions · 25 min
        6. PMP knowledge mock 1180 questions · 4 h
        7. PMP knowledge mock 2180 questions · 4 h

        All practice for the PMP

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.