        PMP People practice questions: set 3

        Answer 20 original people questions in 27 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 16 correct is our practice target, not a PMI pass score.

        A project dependency diagram, a risk matrix and an answer sheet for PMP practice.
        Questions
        20
        Time
        27 min
        Our study target
        16 (80%)
        Part
        People
        Mode
        Timed or untimed
        Access
        Exam pass

        The practice test needs JavaScript. These are its questions:

        1. A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Verified evidence in the review file: a tailored delegation and coaching arrangement. Verified evidence in the review file: a feedback review of delegation and team concerns. Evidence not yet verified: a shared release goal and clear decision responsibilities. Verified evidence in the review file: a review of members’ experience and support needs. Which action should the project manager take next based on this evidence?

          1. Agree the release goal and each role’s decision authority.
          2. Assess experience and ask members what support they need.
          3. Delegate within agreed limits and coach where support is needed.
          4. Review results with the team and adjust leadership support.
        2. A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: evidence that each operator interprets the vision consistently. Verified evidence in the review file: a communication owner and a date to review the vision. Verified evidence in the review file: the operators’ intended outcomes. Verified evidence in the review file: an agreed vision with measurable success criteria. Which action should the project manager take next based on this evidence?

          1. Assign the vision’s communication owner and review date.
          2. Interview the operators about their intended outcomes.
          3. Agree a shared vision and measurable success criteria.
          4. Test understanding and investigate conflicting interpretations.
        3. A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Verified evidence in the review file: an agreed response to the confirmed satisfaction gap. Evidence not yet verified: a repeat measurement after the agreed response. Verified evidence in the review file: confirmed expectations of internal and external customers. Verified evidence in the review file: a comparison between pilot outcomes and customer expectations. Which action should the project manager take next based on this evidence?

          1. Confirm expectations with internal and external customers.
          2. Compare pilot evidence with the confirmed expectations.
          3. Agree a response with customers and the accountable owner.
          4. Measure satisfaction again after the response is applied.
        4. A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: guided practice for the receiving operations team. Verified evidence in the review file: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Evidence not yet verified: captured diagnostic examples and decision rules. Which action should the project manager take next based on this evidence?

          1. Have operations diagnose a fresh failure without coaching.
          2. Identify critical knowledge with the specialist and operations.
          3. Capture failure examples and the specialist’s decision rules.
          4. Run paired diagnostic practice with the receiving team.
        5. A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: support for department leads applying the agreed target. Verified evidence in the review file: a negotiated response-time target and accepted trade-offs. Verified evidence in the review file: explicit response-time expectations from both departments. Evidence not yet verified: a classification of stakeholder groups and decision authority. Which action should the project manager take next based on this evidence?

          1. Classify stakeholders by role and decision authority.
          2. Ask both departments to state measurable expectations.
          3. Facilitate agreement on the target and its trade-offs.
          4. Coach department leads on applying the agreed target.
        6. Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Evidence not yet verified: a neutral account of the underlying approval dispute. Verified evidence in the review file: the immediate enforcement of respectful discussion rules. Which action should the project manager take next based on this evidence?

          1. Review the next approval cycle with both teams.
          2. Establish and enforce respectful discussion rules.
          3. Facilitate an agreement on approval responsibilities.
          4. Hear both teams and establish the source of the dispute.
        7. A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Evidence not yet verified: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Which action should the project manager take next based on this evidence?

          1. Determine reporting needs and confidentiality requirements.
          2. Agree the communication plan with the intended audiences.
          3. Ask recipients for feedback and adjust future reports.
          4. Distribute the tailored report using the agreed plan.
        8. A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Evidence not yet verified: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Evidence not yet verified: an assessment of each group’s influence and needs. Evidence not yet verified: a complete list of affected groups. Which action should the project manager take next based on this evidence?

          1. Identify the affected groups with operations representatives.
          2. Check participation and adjust the engagement approach.
          3. Analyze influence, impact, and information needs.
          4. Agree suitable workshops, updates, and responsible owners.
        9. A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a tailored delegation and coaching arrangement. Evidence not yet verified: a feedback review of delegation and team concerns. Evidence not yet verified: a shared release goal and clear decision responsibilities. Verified evidence in the review file: a review of members’ experience and support needs. Which action should the project manager take next based on this evidence?

          1. Assess experience and ask members what support they need.
          2. Delegate within agreed limits and coach where support is needed.
          3. Review results with the team and adjust leadership support.
          4. Agree the release goal and each role’s decision authority.
        10. A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Evidence not yet verified: explicit response-time expectations from both departments. Evidence not yet verified: a classification of stakeholder groups and decision authority. Which action should the project manager take next based on this evidence?

          1. Coach department leads on applying the agreed target.
          2. Classify stakeholders by role and decision authority.
          3. Ask both departments to state measurable expectations.
          4. Facilitate agreement on the target and its trade-offs.
        11. Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Verified evidence in the review file: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Evidence not yet verified: a neutral account of the underlying approval dispute. Verified evidence in the review file: the immediate enforcement of respectful discussion rules. Which action should the project manager take next based on this evidence?

          1. Establish and enforce respectful discussion rules.
          2. Hear both teams and establish the source of the dispute.
          3. Facilitate an agreement on approval responsibilities.
          4. Review the next approval cycle with both teams.
        12. A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Verified evidence in the review file: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method. Verified evidence in the review file: audience needs, confidentiality limits, and reporting obligations. Which action should the project manager take next based on this evidence?

          1. Distribute the tailored report using the agreed plan.
          2. Ask recipients for feedback and adjust future reports.
          3. Determine reporting needs and confidentiality requirements.
          4. Agree the communication plan with the intended audiences.
        13. A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Verified evidence in the review file: an inventory of critical diagnostic knowledge. Verified evidence in the review file: captured diagnostic examples and decision rules. Which action should the project manager take next based on this evidence?

          1. Identify critical knowledge with the specialist and operations.
          2. Capture failure examples and the specialist’s decision rules.
          3. Have operations diagnose a fresh failure without coaching.
          4. Run paired diagnostic practice with the receiving team.
        14. A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Verified evidence in the review file: an agreed response to the confirmed satisfaction gap. Verified evidence in the review file: a repeat measurement after the agreed response. Evidence not yet verified: confirmed expectations of internal and external customers. Which action should the project manager take next based on this evidence?

          1. Confirm expectations with internal and external customers.
          2. Agree a response with customers and the accountable owner.
          3. Measure satisfaction again after the response is applied.
          4. Compare pilot evidence with the confirmed expectations.
        15. A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: the operators’ intended outcomes. Verified evidence in the review file: an agreed vision with measurable success criteria. Evidence not yet verified: evidence that each operator interprets the vision consistently. Verified evidence in the review file: a communication owner and a date to review the vision. Which action should the project manager take next based on this evidence?

          1. Test understanding and investigate conflicting interpretations.
          2. Interview the operators about their intended outcomes.
          3. Assign the vision’s communication owner and review date.
          4. Agree a shared vision and measurable success criteria.
        16. A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Verified evidence in the review file: a complete list of affected groups. Evidence not yet verified: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Evidence not yet verified: an assessment of each group’s influence and needs. Which action should the project manager take next based on this evidence?

          1. Agree suitable workshops, updates, and responsible owners.
          2. Check participation and adjust the engagement approach.
          3. Analyze influence, impact, and information needs.
          4. Identify the affected groups with operations representatives.
        17. A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Verified evidence in the review file: a shared release goal and clear decision responsibilities. Verified evidence in the review file: a review of members’ experience and support needs. Evidence not yet verified: a tailored delegation and coaching arrangement. Evidence not yet verified: a feedback review of delegation and team concerns. Which action should the project manager take next based on this evidence?

          1. Delegate within agreed limits and coach where support is needed.
          2. Agree the release goal and each role’s decision authority.
          3. Assess experience and ask members what support they need.
          4. Review results with the team and adjust leadership support.
        18. A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Evidence not yet verified: an agreed response to the confirmed satisfaction gap. Verified evidence in the review file: a repeat measurement after the agreed response. Evidence not yet verified: confirmed expectations of internal and external customers. Which action should the project manager take next based on this evidence?

          1. Agree a response with customers and the accountable owner.
          2. Measure satisfaction again after the response is applied.
          3. Compare pilot evidence with the confirmed expectations.
          4. Confirm expectations with internal and external customers.
        19. A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Evidence not yet verified: captured diagnostic examples and decision rules. Verified evidence in the review file: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Which action should the project manager take next based on this evidence?

          1. Have operations diagnose a fresh failure without coaching.
          2. Capture failure examples and the specialist’s decision rules.
          3. Identify critical knowledge with the specialist and operations.
          4. Run paired diagnostic practice with the receiving team.
        20. A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Evidence not yet verified: explicit response-time expectations from both departments. Verified evidence in the review file: a classification of stakeholder groups and decision authority. Evidence not yet verified: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Which action should the project manager take next based on this evidence?

          1. Facilitate agreement on the target and its trade-offs.
          2. Coach department leads on applying the agreed target.
          3. Classify stakeholders by role and decision authority.
          4. Ask both departments to state measurable expectations.

        What this set covers

        • 1.3 Team authority and tailored support3 questions
        • 1.1 Shared outcomes and understanding2 questions
        • 1.6 Customer satisfaction evidence3 questions
        • 1.7 Operational knowledge handover3 questions
        • 1.5 Negotiating shared expectations3 questions
        • 1.2 Conflict diagnosis and resolution2 questions
        • 1.8 Audience-specific reporting2 questions
        • 1.4 Stakeholder involvement2 questions

        Next: People, set 4

        More practice for this exam

        1. People, set 120 questions · 27 min
        2. People, set 220 questions · 27 min
        3. People, set 419 questions · 25 min
        4. People, set 520 questions · 27 min
        5. People, set 619 questions · 25 min
        6. PMP knowledge mock 1180 questions · 4 h
        7. PMP knowledge mock 2180 questions · 4 h

        All practice for the PMP

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.