PMP People practice questions: set 6
Answer 19 original people questions in 25 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 16 correct is our practice target, not a PMI pass score.
- Questions
- 19
- Time
- 25 min
- Our study target
- 16 (80%)
- Part
- People
- Mode
- Timed or untimed
- Access
- Exam pass
The practice test needs JavaScript. These are its questions:
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Evidence not yet verified: an assessment of each group’s influence and needs. Verified evidence in the review file: a complete list of affected groups. Verified evidence in the review file: feedback showing whether engagement reaches each group. Verified evidence in the review file: an engagement approach agreed with affected groups. Which action should the project manager take next based on this evidence?
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Verified evidence in the review file: explicit response-time expectations from both departments. Verified evidence in the review file: a classification of stakeholder groups and decision authority. Verified evidence in the review file: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Which action should the project manager take next based on this evidence?
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Evidence not yet verified: a neutral account of the underlying approval dispute. Evidence not yet verified: the immediate enforcement of respectful discussion rules. Verified evidence in the review file: a follow-up check that the agreement is working. Verified evidence in the review file: a mutually agreed resolution and decision rights. Which action should the project manager take next based on this evidence?
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. Verified evidence in the review file: confirmation that recipients understand and can respond. Evidence not yet verified: delivery of a tailored report through the agreed channels. Which action should the project manager take next based on this evidence?
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: captured diagnostic examples and decision rules. Verified evidence in the review file: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Which action should the project manager take next based on this evidence?
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a review of members’ experience and support needs. Verified evidence in the review file: a tailored delegation and coaching arrangement. Evidence not yet verified: a feedback review of delegation and team concerns. Verified evidence in the review file: a shared release goal and clear decision responsibilities. Which action should the project manager take next based on this evidence?
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Evidence not yet verified: an agreed vision with measurable success criteria. Evidence not yet verified: evidence that each operator interprets the vision consistently. Verified evidence in the review file: a communication owner and a date to review the vision. Evidence not yet verified: the operators’ intended outcomes. Which action should the project manager take next based on this evidence?
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Evidence not yet verified: a comparison between pilot outcomes and customer expectations. Verified evidence in the review file: an agreed response to the confirmed satisfaction gap. Evidence not yet verified: a repeat measurement after the agreed response. Evidence not yet verified: confirmed expectations of internal and external customers. Which action should the project manager take next based on this evidence?
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Evidence not yet verified: an assessment of each group’s influence and needs. Verified evidence in the review file: a complete list of affected groups. Evidence not yet verified: feedback showing whether engagement reaches each group. Evidence not yet verified: an engagement approach agreed with affected groups. Which action should the project manager take next based on this evidence?
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Evidence not yet verified: captured diagnostic examples and decision rules. Evidence not yet verified: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Evidence not yet verified: an inventory of critical diagnostic knowledge. Which action should the project manager take next based on this evidence?
A billing service is in pilot use. A customer-outcomes review checks expectations, pilot evidence, responses, and follow-up measurements. Evidence not yet verified: confirmed expectations of internal and external customers. Verified evidence in the review file: a comparison between pilot outcomes and customer expectations. Verified evidence in the review file: an agreed response to the confirmed satisfaction gap. Verified evidence in the review file: a repeat measurement after the agreed response. Which action should the project manager take next based on this evidence?
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Evidence not yet verified: a review of members’ experience and support needs. Verified evidence in the review file: a tailored delegation and coaching arrangement. Verified evidence in the review file: a feedback review of delegation and team concerns. Verified evidence in the review file: a shared release goal and clear decision responsibilities. Which action should the project manager take next based on this evidence?
A customer portal serves both sales and support. A readiness review examines how the departments have established their response-time expectations. Verified evidence in the review file: support for department leads applying the agreed target. Evidence not yet verified: a negotiated response-time target and accepted trade-offs. Verified evidence in the review file: explicit response-time expectations from both departments. Evidence not yet verified: a classification of stakeholder groups and decision authority. Which action should the project manager take next based on this evidence?
A health-service project has clinical users, a steering committee, and a supplier. Reports must protect confidential information. Evidence not yet verified: audience needs, confidentiality limits, and reporting obligations. Evidence not yet verified: confirmation that recipients understand and can respond. Verified evidence in the review file: delivery of a tailored report through the agreed channels. Verified evidence in the review file: an agreed channel, cadence, owner, and feedback method. Which action should the project manager take next based on this evidence?
A regional transport project involves several operators. A readiness review examines its shared vision, journey-time objectives, and operating-cost objectives. Verified evidence in the review file: an agreed vision with measurable success criteria. Evidence not yet verified: evidence that each operator interprets the vision consistently. Evidence not yet verified: a communication owner and a date to review the vision. Verified evidence in the review file: the operators’ intended outcomes. Which action should the project manager take next based on this evidence?
Design and operations teams have worked through an approval dispute. A review examines records of the discussion, its resolution, and follow-up. Verified evidence in the review file: a neutral account of the underlying approval dispute. Verified evidence in the review file: the immediate enforcement of respectful discussion rules. Evidence not yet verified: a follow-up check that the agreement is working. Evidence not yet verified: a mutually agreed resolution and decision rights. Which action should the project manager take next based on this evidence?
A distributed team is taking over a new product release. Experienced specialists want autonomy, while new members need support. Verified evidence in the review file: a tailored delegation and coaching arrangement. Evidence not yet verified: a feedback review of delegation and team concerns. Evidence not yet verified: a shared release goal and clear decision responsibilities. Evidence not yet verified: a review of members’ experience and support needs. Which action should the project manager take next based on this evidence?
A warehouse automation project changes the daily work of employees, suppliers, and the safety regulator. Verified evidence in the review file: an assessment of each group’s influence and needs. Evidence not yet verified: a complete list of affected groups. Evidence not yet verified: feedback showing whether engagement reaches each group. Evidence not yet verified: an engagement approach agreed with affected groups. Which action should the project manager take next based on this evidence?
A specialist will leave before the operations handover. A replacement must diagnose service failures without relying on the departing specialist. Verified evidence in the review file: an inventory of critical diagnostic knowledge. Evidence not yet verified: captured diagnostic examples and decision rules. Evidence not yet verified: guided practice for the receiving operations team. Evidence not yet verified: an independent diagnosis and accepted handover evidence. Which action should the project manager take next based on this evidence?
What this set covers
- 1.4 Stakeholder involvement3 questions
- 1.5 Negotiating shared expectations2 questions
- 1.2 Conflict diagnosis and resolution2 questions
- 1.8 Audience-specific reporting2 questions
- 1.7 Operational knowledge handover3 questions
- 1.3 Team authority and tailored support3 questions
- 1.1 Shared outcomes and understanding2 questions
- 1.6 Customer satisfaction evidence2 questions
More practice for this exam
Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.