Country or region and language

    Choose your country or region and your language.

    Suggested for you

      All countries and regions

        Choose your character

        It shows in the top bar and on your profile. Change it any time.

        PMP Process practice questions: set 2

        Answer 19 original process questions in 25 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 16 correct is our practice target, not a PMI pass score.

        A project dependency diagram, a risk matrix and an answer sheet for PMP practice.
        Questions
        19
        Time
        25 min
        Our study target
        16 (80%)
        Part
        Process
        Mode
        Timed or untimed
        Access
        Exam pass

        The practice test needs JavaScript. These are its questions:

        1. A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Evidence not yet verified: documented requirements and acceptance criteria. Verified evidence in the review file: a completeness review of the scope breakdown. Verified evidence in the review file: a breakdown into assignable work with traceability. Verified evidence in the review file: an agreed release boundary and explicit exclusions. Which action should the project manager take next based on this evidence?

          1. Agree included services and exclusions with stakeholders.
          2. Break the agreed scope into traceable work packages.
          3. Check the breakdown for omissions and unauthorized additions.
          4. Elicit requirements and define testable acceptance criteria.
        2. A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release. Verified evidence in the review file: operations readiness and an accepted support handover. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Verified evidence in the review file: confirmation of the agreed closure and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Obtain acceptance evidence from the authorized stakeholders.
          2. Complete financial closure, archive lessons, and release resources.
          3. Confirm the contractual and project closure criteria.
          4. Validate operations readiness and complete the support handover.
        3. A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an authorized baseline and risk-based contingency allocation. Verified evidence in the review file: an estimate of costs and identified financial risks. Evidence not yet verified: a governance review of the forecast and funding variance. Verified evidence in the review file: reconciled actual spending and remaining cost estimates. Which action should the project manager take next based on this evidence?

          1. Report the forecast and seek required funding decisions.
          2. Obtain baseline approval and justify contingency reserves.
          3. Reconcile actual costs and estimate the remaining work.
          4. Estimate costs and identify relevant financial uncertainty.
        4. A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Verified evidence in the review file: an accessible version-controlled report for decision makers. Verified evidence in the review file: an interpretation of progress, variance, and forecast implications. Evidence not yet verified: reconciled data from the authoritative project records. Which action should the project manager take next based on this evidence?

          1. Reconcile the report data against authoritative records.
          2. Agree metric definitions and the reporting cutoff.
          3. Analyze reconciled progress and explain forecast implications.
          4. Publish the reviewed report with access and version controls.
        5. A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Evidence not yet verified: verified supplier performance and acceptance evidence. Verified evidence in the review file: an authorized contract with measurable acceptance terms. Verified evidence in the review file: a documented supplier evaluation under the agreed criteria. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Which action should the project manager take next based on this evidence?

          1. Compare supplier evidence with the contractual acceptance terms.
          2. Evaluate bids using the published procurement criteria.
          3. Define evaluation criteria and select suitable contract terms.
          4. Negotiate and authorize the contract’s acceptance obligations.
        6. A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Evidence not yet verified: an agreed hybrid approach for installation and iterative software. Verified evidence in the review file: an integrated dependency, resource, and delivery plan. Evidence not yet verified: a review of plan gaps and continuing business value. Verified evidence in the review file: an assessment of requirement stability and delivery constraints. Which action should the project manager take next based on this evidence?

          1. Agree a hybrid approach with explicit integration points.
          2. Integrate dependencies, resources, and delivery milestones.
          3. Review the integrated plan for gaps and continued value.
          4. Assess uncertainty, constraints, and required delivery outcomes.
        7. A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Verified evidence in the review file: validated activity dependencies and external operating constraints. Verified evidence in the review file: duration estimates and resource calendars. Evidence not yet verified: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Which action should the project manager take next based on this evidence?

          1. Validate dependencies and the permitted shutdown window.
          2. Estimate durations using team input and resource calendars.
          3. Coordinate dates with operations and approve the baseline.
          4. Compare actual progress with the baseline and assess impact.
        8. Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: an agreed allocation that respects authorized capacity. Evidence not yet verified: a utilization check against the agreed allocation. Evidence not yet verified: the required skills and estimated effort for each test. Evidence not yet verified: confirmed technician and laboratory availability. Which action should the project manager take next based on this evidence?

          1. Monitor utilization and address new resource conflicts.
          2. Confirm calendars and competing resource commitments.
          3. Negotiate a feasible allocation with both project owners.
          4. Define test resource requirements and estimate the effort.
        9. A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Verified evidence in the review file: a quality plan with preventive controls and test methods. Evidence not yet verified: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Evidence not yet verified: testable quality requirements and applicable standards. Which action should the project manager take next based on this evidence?

          1. Execute the approved tests and record pilot results.
          2. Analyze defects, improve the process, and verify the result.
          3. Confirm quality criteria and mandatory seal standards.
          4. Plan prevention, inspection, and evidence collection.
        10. A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Evidence not yet verified: an agreed usable increment and release test. Evidence not yet verified: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Which action should the project manager take next based on this evidence?

          1. Measure realized benefit and use it to reprioritize work.
          2. Rank delivery options by benefit, feedback, and dependencies.
          3. Plan a usable increment that tests the prioritized benefit.
          4. Agree the benefit metric and its accountable business owner.
        11. A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Verified evidence in the review file: verified supplier performance and acceptance evidence. Verified evidence in the review file: an authorized contract with measurable acceptance terms. Evidence not yet verified: a documented supplier evaluation under the agreed criteria. Verified evidence in the review file: evaluation criteria and an appropriate allocation of contract risk. Which action should the project manager take next based on this evidence?

          1. Compare supplier evidence with the contractual acceptance terms.
          2. Define evaluation criteria and select suitable contract terms.
          3. Negotiate and authorize the contract’s acceptance obligations.
          4. Evaluate bids using the published procurement criteria.
        12. A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Verified evidence in the review file: an agreed hybrid approach for installation and iterative software. Verified evidence in the review file: an integrated dependency, resource, and delivery plan. Evidence not yet verified: a review of plan gaps and continuing business value. Verified evidence in the review file: an assessment of requirement stability and delivery constraints. Which action should the project manager take next based on this evidence?

          1. Review the integrated plan for gaps and continued value.
          2. Agree a hybrid approach with explicit integration points.
          3. Integrate dependencies, resources, and delivery milestones.
          4. Assess uncertainty, constraints, and required delivery outcomes.
        13. A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release. Verified evidence in the review file: operations readiness and an accepted support handover. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Which action should the project manager take next based on this evidence?

          1. Obtain acceptance evidence from the authorized stakeholders.
          2. Validate operations readiness and complete the support handover.
          3. Confirm the contractual and project closure criteria.
          4. Complete financial closure, archive lessons, and release resources.
        14. A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Evidence not yet verified: a governance review of the forecast and funding variance. Verified evidence in the review file: reconciled actual spending and remaining cost estimates. Verified evidence in the review file: an authorized baseline and risk-based contingency allocation. Evidence not yet verified: an estimate of costs and identified financial risks. Which action should the project manager take next based on this evidence?

          1. Report the forecast and seek required funding decisions.
          2. Obtain baseline approval and justify contingency reserves.
          3. Reconcile actual costs and estimate the remaining work.
          4. Estimate costs and identify relevant financial uncertainty.
        15. A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Evidence not yet verified: an agreed usable increment and release test. Verified evidence in the review file: benefit measurement after customers use the increment. Verified evidence in the review file: a measurable benefit agreed with the business owner. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Which action should the project manager take next based on this evidence?

          1. Agree the benefit metric and its accountable business owner.
          2. Plan a usable increment that tests the prioritized benefit.
          3. Rank delivery options by benefit, feedback, and dependencies.
          4. Measure realized benefit and use it to reprioritize work.
        16. A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Verified evidence in the review file: an agreed release boundary and explicit exclusions. Verified evidence in the review file: documented requirements and acceptance criteria. Evidence not yet verified: a completeness review of the scope breakdown. Evidence not yet verified: a breakdown into assignable work with traceability. Which action should the project manager take next based on this evidence?

          1. Check the breakdown for omissions and unauthorized additions.
          2. Elicit requirements and define testable acceptance criteria.
          3. Agree included services and exclusions with stakeholders.
          4. Break the agreed scope into traceable work packages.
        17. A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Evidence not yet verified: an accessible version-controlled report for decision makers. Verified evidence in the review file: an interpretation of progress, variance, and forecast implications. Evidence not yet verified: reconciled data from the authoritative project records. Which action should the project manager take next based on this evidence?

          1. Reconcile the report data against authoritative records.
          2. Agree metric definitions and the reporting cutoff.
          3. Analyze reconciled progress and explain forecast implications.
          4. Publish the reviewed report with access and version controls.
        18. Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Evidence not yet verified: an agreed allocation that respects authorized capacity. Evidence not yet verified: a utilization check against the agreed allocation. Evidence not yet verified: the required skills and estimated effort for each test. Verified evidence in the review file: confirmed technician and laboratory availability. Which action should the project manager take next based on this evidence?

          1. Confirm calendars and competing resource commitments.
          2. Negotiate a feasible allocation with both project owners.
          3. Define test resource requirements and estimate the effort.
          4. Monitor utilization and address new resource conflicts.
        19. A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Evidence not yet verified: a quality plan with preventive controls and test methods. Evidence not yet verified: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Verified evidence in the review file: testable quality requirements and applicable standards. Which action should the project manager take next based on this evidence?

          1. Analyze defects, improve the process, and verify the result.
          2. Confirm quality criteria and mandatory seal standards.
          3. Execute the approved tests and record pilot results.
          4. Plan prevention, inspection, and evidence collection.

        What this set covers

        • 2.2 Release boundaries and work breakdown2 questions
        • 2.10 Acceptance and operational transition2 questions
        • 2.6 Financial forecasting and control2 questions
        • 2.9 Reconciled project reporting2 questions
        • 2.5 Supplier selection and acceptance2 questions
        • 2.1 Integrated delivery planning2 questions
        • 2.8 Schedule dependencies and baselines1 question
        • 2.4 Capacity and resource commitments2 questions
        • 2.7 Quality evidence and improvement2 questions
        • 2.3 Incremental benefit realization2 questions

        Next: Process, set 3

        More practice for this exam

        1. Process, set 119 questions · 25 min
        2. Process, set 319 questions · 25 min
        3. Process, set 419 questions · 25 min
        4. Process, set 518 questions · 24 min
        5. Process, set 618 questions · 24 min
        6. Process, set 718 questions · 24 min
        7. Process, set 818 questions · 24 min
        8. PMP knowledge mock 1180 questions · 4 h
        9. PMP knowledge mock 2180 questions · 4 h

        All practice for the PMP

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.