        PMP Process practice questions: set 6

        Answer 18 original process questions in 24 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 15 correct is our practice target, not a PMI pass score.

        A project dependency diagram, a risk matrix and an answer sheet for PMP practice.
        Questions
        18
        Time
        24 min
        Our study target
        15 (80%)
        Part
        Process
        Mode
        Timed or untimed
        Access
        Exam pass

        The practice test needs JavaScript. These are its questions:

        1. A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Verified evidence in the review file: reconciled data from the authoritative project records. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Verified evidence in the review file: an accessible version-controlled report for decision makers. Verified evidence in the review file: an interpretation of progress, variance, and forecast implications. Which action should the project manager take next based on this evidence?

          1. Analyze reconciled progress and explain forecast implications.
          2. Agree metric definitions and the reporting cutoff.
          3. Publish the reviewed report with access and version controls.
          4. Reconcile the report data against authoritative records.
        2. A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Verified evidence in the review file: evaluation criteria and an appropriate allocation of contract risk. Verified evidence in the review file: verified supplier performance and acceptance evidence. Evidence not yet verified: an authorized contract with measurable acceptance terms. Verified evidence in the review file: a documented supplier evaluation under the agreed criteria. Which action should the project manager take next based on this evidence?

          1. Define evaluation criteria and select suitable contract terms.
          2. Evaluate bids using the published procurement criteria.
          3. Compare supplier evidence with the contractual acceptance terms.
          4. Negotiate and authorize the contract’s acceptance obligations.
        3. A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Verified evidence in the review file: a completeness review of the scope breakdown. Verified evidence in the review file: a breakdown into assignable work with traceability. Evidence not yet verified: an agreed release boundary and explicit exclusions. Evidence not yet verified: documented requirements and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Check the breakdown for omissions and unauthorized additions.
          2. Elicit requirements and define testable acceptance criteria.
          3. Agree included services and exclusions with stakeholders.
          4. Break the agreed scope into traceable work packages.
        4. A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Verified evidence in the review file: formal stakeholder acceptance of completed deliverables. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release. Evidence not yet verified: operations readiness and an accepted support handover. Which action should the project manager take next based on this evidence?

          1. Validate operations readiness and complete the support handover.
          2. Complete financial closure, archive lessons, and release resources.
          3. Confirm the contractual and project closure criteria.
          4. Obtain acceptance evidence from the authorized stakeholders.
        5. A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an estimate of costs and identified financial risks. Verified evidence in the review file: a governance review of the forecast and funding variance. Evidence not yet verified: reconciled actual spending and remaining cost estimates. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Which action should the project manager take next based on this evidence?

          1. Estimate costs and identify relevant financial uncertainty.
          2. Reconcile actual costs and estimate the remaining work.
          3. Report the forecast and seek required funding decisions.
          4. Obtain baseline approval and justify contingency reserves.
        6. A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Verified evidence in the review file: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Verified evidence in the review file: testable quality requirements and applicable standards. Evidence not yet verified: a quality plan with preventive controls and test methods. Which action should the project manager take next based on this evidence?

          1. Analyze defects, improve the process, and verify the result.
          2. Confirm quality criteria and mandatory seal standards.
          3. Execute the approved tests and record pilot results.
          4. Plan prevention, inspection, and evidence collection.
        7. A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Evidence not yet verified: an agreed usable increment and release test. Verified evidence in the review file: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Which action should the project manager take next based on this evidence?

          1. Agree the benefit metric and its accountable business owner.
          2. Plan a usable increment that tests the prioritized benefit.
          3. Measure realized benefit and use it to reprioritize work.
          4. Rank delivery options by benefit, feedback, and dependencies.
        8. A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Evidence not yet verified: an assessment of requirement stability and delivery constraints. Verified evidence in the review file: an agreed hybrid approach for installation and iterative software. Evidence not yet verified: an integrated dependency, resource, and delivery plan. Evidence not yet verified: a review of plan gaps and continuing business value. Which action should the project manager take next based on this evidence?

          1. Agree a hybrid approach with explicit integration points.
          2. Integrate dependencies, resources, and delivery milestones.
          3. Assess uncertainty, constraints, and required delivery outcomes.
          4. Review the integrated plan for gaps and continued value.
        9. A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Evidence not yet verified: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Verified evidence in the review file: validated activity dependencies and external operating constraints. Evidence not yet verified: duration estimates and resource calendars. Which action should the project manager take next based on this evidence?

          1. Compare actual progress with the baseline and assess impact.
          2. Estimate durations using team input and resource calendars.
          3. Validate dependencies and the permitted shutdown window.
          4. Coordinate dates with operations and approve the baseline.
        10. Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: an agreed allocation that respects authorized capacity. Verified evidence in the review file: a utilization check against the agreed allocation. Evidence not yet verified: the required skills and estimated effort for each test. Verified evidence in the review file: confirmed technician and laboratory availability. Which action should the project manager take next based on this evidence?

          1. Define test resource requirements and estimate the effort.
          2. Confirm calendars and competing resource commitments.
          3. Negotiate a feasible allocation with both project owners.
          4. Monitor utilization and address new resource conflicts.
        11. A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an estimate of costs and identified financial risks. Verified evidence in the review file: a governance review of the forecast and funding variance. Evidence not yet verified: reconciled actual spending and remaining cost estimates. Verified evidence in the review file: an authorized baseline and risk-based contingency allocation. Which action should the project manager take next based on this evidence?

          1. Estimate costs and identify relevant financial uncertainty.
          2. Obtain baseline approval and justify contingency reserves.
          3. Report the forecast and seek required funding decisions.
          4. Reconcile actual costs and estimate the remaining work.
        12. A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Verified evidence in the review file: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Verified evidence in the review file: testable quality requirements and applicable standards. Verified evidence in the review file: a quality plan with preventive controls and test methods. Which action should the project manager take next based on this evidence?

          1. Execute the approved tests and record pilot results.
          2. Confirm quality criteria and mandatory seal standards.
          3. Plan prevention, inspection, and evidence collection.
          4. Analyze defects, improve the process, and verify the result.
        13. A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Verified evidence in the review file: a documented supplier evaluation under the agreed criteria. Evidence not yet verified: evaluation criteria and an appropriate allocation of contract risk. Verified evidence in the review file: verified supplier performance and acceptance evidence. Evidence not yet verified: an authorized contract with measurable acceptance terms. Which action should the project manager take next based on this evidence?

          1. Define evaluation criteria and select suitable contract terms.
          2. Negotiate and authorize the contract’s acceptance obligations.
          3. Compare supplier evidence with the contractual acceptance terms.
          4. Evaluate bids using the published procurement criteria.
        14. A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: reconciled data from the authoritative project records. Verified evidence in the review file: metric definitions, data owners, and a common reporting date. Verified evidence in the review file: an accessible version-controlled report for decision makers. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Which action should the project manager take next based on this evidence?

          1. Reconcile the report data against authoritative records.
          2. Analyze reconciled progress and explain forecast implications.
          3. Publish the reviewed report with access and version controls.
          4. Agree metric definitions and the reporting cutoff.
        15. Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Verified evidence in the review file: the required skills and estimated effort for each test. Evidence not yet verified: confirmed technician and laboratory availability. Verified evidence in the review file: an agreed allocation that respects authorized capacity. Evidence not yet verified: a utilization check against the agreed allocation. Which action should the project manager take next based on this evidence?

          1. Negotiate a feasible allocation with both project owners.
          2. Monitor utilization and address new resource conflicts.
          3. Confirm calendars and competing resource commitments.
          4. Define test resource requirements and estimate the effort.
        16. A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Verified evidence in the review file: closed contracts, archived lessons, and authorized resource release. Evidence not yet verified: operations readiness and an accepted support handover. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Which action should the project manager take next based on this evidence?

          1. Validate operations readiness and complete the support handover.
          2. Complete financial closure, archive lessons, and release resources.
          3. Obtain acceptance evidence from the authorized stakeholders.
          4. Confirm the contractual and project closure criteria.
        17. A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Evidence not yet verified: a ranked comparison of delivery options and dependencies. Verified evidence in the review file: an agreed usable increment and release test. Evidence not yet verified: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Which action should the project manager take next based on this evidence?

          1. Measure realized benefit and use it to reprioritize work.
          2. Rank delivery options by benefit, feedback, and dependencies.
          3. Plan a usable increment that tests the prioritized benefit.
          4. Agree the benefit metric and its accountable business owner.
        18. A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Evidence not yet verified: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Evidence not yet verified: validated activity dependencies and external operating constraints. Evidence not yet verified: duration estimates and resource calendars. Which action should the project manager take next based on this evidence?

          1. Validate dependencies and the permitted shutdown window.
          2. Estimate durations using team input and resource calendars.
          3. Coordinate dates with operations and approve the baseline.
          4. Compare actual progress with the baseline and assess impact.

        What this set covers

        • 2.9 Reconciled project reporting2 questions
        • 2.5 Supplier selection and acceptance2 questions
        • 2.2 Release boundaries and work breakdown1 question
        • 2.10 Acceptance and operational transition2 questions
        • 2.6 Financial forecasting and control2 questions
        • 2.7 Quality evidence and improvement2 questions
        • 2.3 Incremental benefit realization2 questions
        • 2.1 Integrated delivery planning1 question
        • 2.8 Schedule dependencies and baselines2 questions
        • 2.4 Capacity and resource commitments2 questions

        Next: Process, set 7

        More practice for this exam

        1. Process, set 119 questions · 25 min
        2. Process, set 219 questions · 25 min
        3. Process, set 319 questions · 25 min
        4. Process, set 419 questions · 25 min
        5. Process, set 518 questions · 24 min
        6. Process, set 718 questions · 24 min
        7. Process, set 818 questions · 24 min
        8. PMP knowledge mock 1180 questions · 4 h
        9. PMP knowledge mock 2180 questions · 4 h

        All practice for the PMP

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.