        Answer 19 original process questions in 25 min. Review the explanation and use the linked course tasks to work on the decisions you missed. 16 correct is our practice target, not a PMI pass score.

        A project dependency diagram, a risk matrix and an answer sheet for PMP practice.
        Questions
        19
        Time
        25 min
        Our study target
        16 (80%)
        Part
        Process
        Mode
        Timed or untimed
        Access
        Exam pass

        The practice test needs JavaScript. These are its questions:

        1. A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Verified evidence in the review file: an agreed usable increment and release test. Verified evidence in the review file: benefit measurement after customers use the increment. Evidence not yet verified: a measurable benefit agreed with the business owner. Verified evidence in the review file: a ranked comparison of delivery options and dependencies. Which action should the project manager take next based on this evidence?

          1. Rank delivery options by benefit, feedback, and dependencies.
          2. Plan a usable increment that tests the prioritized benefit.
          3. Measure realized benefit and use it to reprioritize work.
          4. Agree the benefit metric and its accountable business owner.
        2. A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Verified evidence in the review file: an agreed hybrid approach for installation and iterative software. Evidence not yet verified: an integrated dependency, resource, and delivery plan. Verified evidence in the review file: a review of plan gaps and continuing business value. Verified evidence in the review file: an assessment of requirement stability and delivery constraints. Which action should the project manager take next based on this evidence?

          1. Review the integrated plan for gaps and continued value.
          2. Integrate dependencies, resources, and delivery milestones.
          3. Assess uncertainty, constraints, and required delivery outcomes.
          4. Agree a hybrid approach with explicit integration points.
        3. A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Verified evidence in the review file: validated activity dependencies and external operating constraints. Verified evidence in the review file: duration estimates and resource calendars. Verified evidence in the review file: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Which action should the project manager take next based on this evidence?

          1. Estimate durations using team input and resource calendars.
          2. Compare actual progress with the baseline and assess impact.
          3. Coordinate dates with operations and approve the baseline.
          4. Validate dependencies and the permitted shutdown window.
        4. Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Evidence not yet verified: an agreed allocation that respects authorized capacity. Verified evidence in the review file: a utilization check against the agreed allocation. Evidence not yet verified: the required skills and estimated effort for each test. Verified evidence in the review file: confirmed technician and laboratory availability. Which action should the project manager take next based on this evidence?

          1. Confirm calendars and competing resource commitments.
          2. Define test resource requirements and estimate the effort.
          3. Negotiate a feasible allocation with both project owners.
          4. Monitor utilization and address new resource conflicts.
        5. A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Verified evidence in the review file: a quality plan with preventive controls and test methods. Verified evidence in the review file: pilot measurements collected using the approved test method. Evidence not yet verified: an evidence-based improvement and effectiveness review. Evidence not yet verified: testable quality requirements and applicable standards. Which action should the project manager take next based on this evidence?

          1. Analyze defects, improve the process, and verify the result.
          2. Plan prevention, inspection, and evidence collection.
          3. Execute the approved tests and record pilot results.
          4. Confirm quality criteria and mandatory seal standards.
        6. A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Verified evidence in the review file: evaluation criteria and an appropriate allocation of contract risk. Evidence not yet verified: verified supplier performance and acceptance evidence. Verified evidence in the review file: an authorized contract with measurable acceptance terms. Evidence not yet verified: a documented supplier evaluation under the agreed criteria. Which action should the project manager take next based on this evidence?

          1. Evaluate bids using the published procurement criteria.
          2. Negotiate and authorize the contract’s acceptance obligations.
          3. Compare supplier evidence with the contractual acceptance terms.
          4. Define evaluation criteria and select suitable contract terms.
        7. A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Verified evidence in the review file: a completeness review of the scope breakdown. Evidence not yet verified: a breakdown into assignable work with traceability. Evidence not yet verified: an agreed release boundary and explicit exclusions. Evidence not yet verified: documented requirements and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Elicit requirements and define testable acceptance criteria.
          2. Agree included services and exclusions with stakeholders.
          3. Break the agreed scope into traceable work packages.
          4. Check the breakdown for omissions and unauthorized additions.
        8. A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Evidence not yet verified: formal stakeholder acceptance of completed deliverables. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Evidence not yet verified: closed contracts, archived lessons, and authorized resource release. Verified evidence in the review file: operations readiness and an accepted support handover. Which action should the project manager take next based on this evidence?

          1. Confirm the contractual and project closure criteria.
          2. Complete financial closure, archive lessons, and release resources.
          3. Obtain acceptance evidence from the authorized stakeholders.
          4. Validate operations readiness and complete the support handover.
        9. A battery installation has uncertain supplier costs and an approved funding ceiling. The steering committee needs a defensible financial forecast. Verified evidence in the review file: an estimate of costs and identified financial risks. Evidence not yet verified: a governance review of the forecast and funding variance. Evidence not yet verified: reconciled actual spending and remaining cost estimates. Evidence not yet verified: an authorized baseline and risk-based contingency allocation. Which action should the project manager take next based on this evidence?

          1. Obtain baseline approval and justify contingency reserves.
          2. Reconcile actual costs and estimate the remaining work.
          3. Report the forecast and seek required funding decisions.
          4. Estimate costs and identify relevant financial uncertainty.
        10. A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: metric definitions, data owners, and a common reporting date. Evidence not yet verified: an accessible version-controlled report for decision makers. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Evidence not yet verified: reconciled data from the authoritative project records. Which action should the project manager take next based on this evidence?

          1. Reconcile the report data against authoritative records.
          2. Agree metric definitions and the reporting cutoff.
          3. Analyze reconciled progress and explain forecast implications.
          4. Publish the reviewed report with access and version controls.
        11. A reusable medical container must meet a defined seal standard. A quality review examines the pilot batch and its supporting records. Evidence not yet verified: a quality plan with preventive controls and test methods. Verified evidence in the review file: pilot measurements collected using the approved test method. Verified evidence in the review file: an evidence-based improvement and effectiveness review. Verified evidence in the review file: testable quality requirements and applicable standards. Which action should the project manager take next based on this evidence?

          1. Analyze defects, improve the process, and verify the result.
          2. Confirm quality criteria and mandatory seal standards.
          3. Plan prevention, inspection, and evidence collection.
          4. Execute the approved tests and record pilot results.
        12. A utility is buying a specialist inspection service. The scope is well defined, and the supplier must meet documented safety and acceptance conditions. Verified evidence in the review file: evaluation criteria and an appropriate allocation of contract risk. Evidence not yet verified: verified supplier performance and acceptance evidence. Verified evidence in the review file: an authorized contract with measurable acceptance terms. Verified evidence in the review file: a documented supplier evaluation under the agreed criteria. Which action should the project manager take next based on this evidence?

          1. Evaluate bids using the published procurement criteria.
          2. Negotiate and authorize the contract’s acceptance obligations.
          3. Compare supplier evidence with the contractual acceptance terms.
          4. Define evaluation criteria and select suitable contract terms.
        13. A manufacturer combines a fixed-date factory installation with software whose requirements will evolve through trials. Evidence not yet verified: an integrated dependency, resource, and delivery plan. Verified evidence in the review file: a review of plan gaps and continuing business value. Evidence not yet verified: an assessment of requirement stability and delivery constraints. Verified evidence in the review file: an agreed hybrid approach for installation and iterative software. Which action should the project manager take next based on this evidence?

          1. Assess uncertainty, constraints, and required delivery outcomes.
          2. Agree a hybrid approach with explicit integration points.
          3. Integrate dependencies, resources, and delivery milestones.
          4. Review the integrated plan for gaps and continued value.
        14. A data center migration depends on electrical testing and a shared network shutdown. The shutdown can occur only in an agreed operating window. Verified evidence in the review file: duration estimates and resource calendars. Verified evidence in the review file: an approved schedule baseline coordinated with operations. Evidence not yet verified: an analysis of actual progress and schedule variation. Evidence not yet verified: validated activity dependencies and external operating constraints. Which action should the project manager take next based on this evidence?

          1. Compare actual progress with the baseline and assess impact.
          2. Estimate durations using team input and resource calendars.
          3. Validate dependencies and the permitted shutdown window.
          4. Coordinate dates with operations and approve the baseline.
        15. A retailer can release demand forecasting before a larger merchandising platform. The sponsor wants demonstrated business benefit. Verified evidence in the review file: a measurable benefit agreed with the business owner. Verified evidence in the review file: a ranked comparison of delivery options and dependencies. Evidence not yet verified: an agreed usable increment and release test. Evidence not yet verified: benefit measurement after customers use the increment. Which action should the project manager take next based on this evidence?

          1. Agree the benefit metric and its accountable business owner.
          2. Plan a usable increment that tests the prioritized benefit.
          3. Rank delivery options by benefit, feedback, and dependencies.
          4. Measure realized benefit and use it to reprioritize work.
        16. A steering report combines completed work, supplier invoices, and benefit measures from several source systems. A review checks its reporting basis. Evidence not yet verified: an accessible version-controlled report for decision makers. Evidence not yet verified: an interpretation of progress, variance, and forecast implications. Verified evidence in the review file: reconciled data from the authoritative project records. Verified evidence in the review file: metric definitions, data owners, and a common reporting date. Which action should the project manager take next based on this evidence?

          1. Analyze reconciled progress and explain forecast implications.
          2. Agree metric definitions and the reporting cutoff.
          3. Reconcile the report data against authoritative records.
          4. Publish the reviewed report with access and version controls.
        17. A city commissions a permit portal for inspectors and applicants. A scope review checks the first release and its supporting records. Evidence not yet verified: a completeness review of the scope breakdown. Verified evidence in the review file: a breakdown into assignable work with traceability. Evidence not yet verified: an agreed release boundary and explicit exclusions. Evidence not yet verified: documented requirements and acceptance criteria. Which action should the project manager take next based on this evidence?

          1. Elicit requirements and define testable acceptance criteria.
          2. Check the breakdown for omissions and unauthorized additions.
          3. Agree included services and exclusions with stakeholders.
          4. Break the agreed scope into traceable work packages.
        18. A payment platform is preparing to move to operations. A closure review checks acceptance, transition, and remaining obligations before the team disperses. Verified evidence in the review file: formal stakeholder acceptance of completed deliverables. Evidence not yet verified: confirmation of the agreed closure and acceptance criteria. Evidence not yet verified: closed contracts, archived lessons, and authorized resource release. Evidence not yet verified: operations readiness and an accepted support handover. Which action should the project manager take next based on this evidence?

          1. Validate operations readiness and complete the support handover.
          2. Confirm the contractual and project closure criteria.
          3. Complete financial closure, archive lessons, and release resources.
          4. Obtain acceptance evidence from the authorized stakeholders.
        19. Two projects share laboratory technicians and a restricted testing window. A capacity review checks their resource commitments; overtime requires separate authorization. Evidence not yet verified: the required skills and estimated effort for each test. Evidence not yet verified: confirmed technician and laboratory availability. Evidence not yet verified: an agreed allocation that respects authorized capacity. Evidence not yet verified: a utilization check against the agreed allocation. Which action should the project manager take next based on this evidence?

          1. Define test resource requirements and estimate the effort.
          2. Confirm calendars and competing resource commitments.
          3. Negotiate a feasible allocation with both project owners.
          4. Monitor utilization and address new resource conflicts.

        What this set covers

        • 2.3 Incremental benefit realization2 questions
        • 2.1 Integrated delivery planning2 questions
        • 2.8 Schedule dependencies and baselines2 questions
        • 2.4 Capacity and resource commitments2 questions
        • 2.7 Quality evidence and improvement2 questions
        • 2.5 Supplier selection and acceptance2 questions
        • 2.2 Release boundaries and work breakdown2 questions
        • 2.10 Acceptance and operational transition2 questions
        • 2.6 Financial forecasting and control1 question
        • 2.9 Reconciled project reporting2 questions

        Next: Process, set 4

        More practice for this exam

        1. Process, set 119 questions · 25 min
        2. Process, set 219 questions · 25 min
        3. Process, set 419 questions · 25 min
        4. Process, set 518 questions · 24 min
        5. Process, set 618 questions · 24 min
        6. Process, set 718 questions · 24 min
        7. Process, set 818 questions · 24 min
        8. PMP knowledge mock 1180 questions · 4 h
        9. PMP knowledge mock 2180 questions · 4 h

        All practice for the PMP

        Independent practice by The Work Gym. PMP and PMI are trademarks of Project Management Institute. We aren't affiliated with or endorsed by PMI. No contact hours, PDUs or certification guarantee.

        Your Work Gym account

        Save your progress and pick up on another device. Your browser's progress comes with you.

        New accounts get 12 hours of full access: every course, unit, project and exam. The clock starts when you open your first lesson.

        Plan your practice from a job ad or syllabus

        Have a referral code?

        or

        You can keep practicing without an account.

        Change your plan

        Checking the price

        Help and feedback

        Ask a question, tell us what is not working, or share an idea. We reply by email.

        What is it about?

        We use it only to reply to you.